Lavs Issues. Lav 12. Tube 26-28. Planning future activities. Conclusions. Lav 12. Details drawings are ready. Panel light tight has been defined (inner radius 280mm material aluminum 0.4mm). Orders for top part and lower carriage has been placed and the company received both of them.

Download Presentation

Lavs Issues

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Lavs issues

Lavs Issues

  • Lav 12.

  • Tube 26-28.

  • Planning future activities.

  • Conclusions.


Lav 12

Lav12.

  • Details drawings are ready.

  • Panel light tight has been defined (inner radius 280mm material aluminum 0.4mm).

  • Orders for top part and lower carriage has been placed and the company received both of them.

  • Next step is to interact with production company to finalized drawings for construction.

  • The delivery time is two month after the approval of final drawing for construction.

  • The company is preparing a detail fabrication steps planning.


Lavs issues

Survey holes

DETAIL FROM G.DRAWING:

- LAV 12 SCHEME

Verification of the access to the survey holes to be able adjusting the Lav 12

During an external survey we can traslate it outside.


Lavs issues

Aluminum sheet panels

Panel light tight

Aluminum 0.4mm

Inner Cylinder radius 280mm


Lavs issues

LAV 12

GENERAL DRAWING

WITH MAIN REFERENCES

EDMS: 1320184 v.1

Survey holesR=3200


Lavs issues

Details drawings of Lav 12


Tube 26 28 status

Tube 26-28 status

  • A final versing of drawings has been made and approved.

  • We verify fabrication drawings and final dimensions and tolerances.

  • Final drawing has been summited to FERDI and Olivier for further comments.

  • The deliver schedule has been update.

  • The deliver of tube 26-28 at CERN is envisaged in the end of April 2014 (22/04/2014).

  • A late of delivered of the special stainless steel AISI 304LN has caused a week of delay in the pervious schedule.

  • All material for construction now it is at the company and reparation is taking place for welding.


Tube 26 drawing

Tube 26 drawing


Tube 28 drawing

Tube 28 drawing


Planning of future activities

Planning of future activities

  • Mounting and test the Lav 12 structures at the company to verifying the mechanic.

  • The transportation of LAV 12 implies a new insulation case and a new isolation system.

  • Tooling for mounting and handling LAV 12 Mechanic and crystal must be designed and made.

  • Verification of construction of Tube 26 and 28 and tests.

  • Installation of the tube 26 and 28 and the rest of LAVs in the experimental area.


Conclusions

Conclusions

  • We can consider to receive the lav 12 in Frascati at the end of April 2014 and transport it at CERN during the summer time.

  • Integration and organization of the transportation of LAV12 can take place in the following three months.

  • The Tube 26-28 can be delivered at CERN end of April.

  • After the end of March we can installed the rest of LAVS.