ECE620 – CURENT Course: Decision Support for Power System Restoration

ECE620 – CURENT Course: Decision Support for Power System Restoration. Kai Sun October 15, 2014. Content. Historical power system blackouts Industry practices in system restoration Why do we need decision support tools? Introduction of a Generic Restoration Milestone based approach

Download Presentation

ECE620 – CURENT Course: Decision Support for Power System Restoration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ECE620 – CURENT Course:Decision Support for Power System Restoration Kai Sun October 15, 2014

  2. Content • Historical power system blackouts • Industry practices in system restoration • Why do we need decision support tools? • Introduction of a Generic Restoration Milestone based approach • Case studies • System Restoration Navigator by EPRI

  3. Historical Blackout Events

  4. Sequence of Events in Blackouts • Initial event • Vulnerable conditions • System islanding • Load/generation imbalance in islands • Blackout of islands

  5. Tripped by Zone 3 relay 7 4 Faulty zone 3 relay 1GW generation tripped by SPS 9 3 2 1 5 Tree contact and relay mis-opt. 6 8 Loss of key hydro units 10 7 4 6 1 9 5 8 2 3 Example of Voltage Collapse - July 2nd, 1996 Western Cascading Event

  6. Blackout Event on August 10, 1996 970 MW loss 2,100 MW loss 11,600 MW loss 15,820MW loss Malin-Round Mountain #1 MW 15:48:51 1500 15:42:03 15:47:36 1400 0.276 Hz oscillations Damping>7% 1300 0.252 Hz oscillations Damping 1% 0.264 Hz oscillations 1200 3.46% Damping 1100 200 300 400 500 600 700 800 Time in Seconds 1. Initial event (15:42:03): Short circuit due to tree contact  Outages of 6 transformers and lines 2. Vulnerable conditions (minutes) Low-damped inter-area oscillations  Outages of generators and tie-lines 3. Blackouts (seconds) Unintentional separation  Loss of 24% load System islanding and blackouts

  7. Losses Due to Blackouts [1][2] The faster we bring the system back, the less we would lose

  8. Common Factors: The 3 “T”s • Tools • Inability of system operators or coordinators to visualize events on the entire system • Failure to ensure that system operation was within safe limits • Training • Inadequate training of operating personnel • Ineffective communication, failure to communicate status to neighboring systems • Trees • Conductor contact with trees, inadequate vegetation management

  9. Status of Power System Restoration • Restoration is basically manual work performed by operators in control rooms • Restoration plans or guidelines are offline designed by planning engineer and evaluated once/twice a year • Regional system restoration trainings/drills based on OTS (Operator Training Simulators) are conducted every year • Typical Restoration stages (assume 6-10 hours) [1]-[3]: • Preparation (1-2 hours) • System restoration (1-3 hours) • Load restoration (4-6 hours)

  10. Generating Units with Black-Start (BS) Capabilities [1]-[4] • Hydro • may be started in 5-10 min. • Diesel • small but has fast response • may provide the start-up requirement of larger units • cannot be used to pick up sizable loads or energize transmission lines. • Gas turbine • units with local battery power • larger units with an on-site diesel unit

  11. North American Electric Reliability Corporation (NERC) Standards for System Restoration

  12. Sample Restoration Procedure • Initial assessment • Assessment of the extent of a blackout • Communications (essential) • Verify communication with ISO/RTO, control centers, energy providers, hydro, and other affected systems • Verify backup communications • Effective communication with all stakeholders • Determine generator status • online/offline, location, type, • damaged equipment, stability, reserve, connectivity to the system, and • blackstart capability. • Call for extra manpower

  13. Sample Restoration Procedure (cont’d) • Start generation units • Restoration of offline units • Hydro: quickly started without an outside source • Combustion turbine: quickly (10min) started, may be voltage-dependent to allow starting • Thermal steam: 1-20 hours (24-48 hours for nuclear); hot units may be returned quicker • Prioritization of units to start • NERC requirements • Individual restoration plan • Start-up time of a unit • Availability of on-site auxiliary power • Distance to blackout resources • Generating plant operators • Safe plant shutdown (prepared for restoration) • Governors and AVR should be on • Plant operators control frequency around 60Hz

  14. Sample Restoration Procedure (cont’d) • Restore the system • Multiple islands (bottom-up) • Stabilize remaining available generation • Determine restoration transmission paths • Expand islands by restoring transmission and load • Synchronize islands when appropriate • Large islands (Top-down) • Restore the EHV transmission (maybe from outside sources if available) • Restore critical generating plants and substations along the restored transmission • Bring on more generation • Restore underlying transmission

  15. Sample Restoration Procedure (cont’d) • Restore load • Prioritize loads for restoration • Auxiliary power for generating plants • Auxiliary power for substations • Natural gas or oil supply facilities • Customers: • Critical (hospitals, airports, etc.) • Dispatchable (others) • Frequency control • Maintain frequency around 60Hz (e.g. 59.75-60.05Hz) • Increase frequency to >60Hz (e.g. 60-60.05Hz) prior to restoring a block of load

  16. Restoration Strategies Build-Upward (Bottom-Up) (e.g. PJM [4]): Build-Downward (Top-Down) (e.g. Hydro Quebec [5]): Re-energizing the transmission network to pool blackstartpower first Actions include: Start up BS units, Energize the transmission network Crank non-BS units Pick up loads • Based on offline define electrical islands with blackstart capabilities • Actions include • Start up BS units • Crank non-BS units • Restore multiple islands to pick up loads • Synchronize islands

  17. Decision Support Tools • Why important? • Supporting planning engineers in developing and evaluating restoration strategies • Supporting system operators in developing, rehearsing, coordinating and implementing restoration strategies Today’s Restoration plan Restoration decision support Offline, non-interactive Online, interactive

  18. Optimize the path (minimizing the restoration time) Able to re-calculate when necessary (operators make mistakes or meet unexpected events) Online Interactive Decision Support Tool TVA Control Center (source: TVA.com Duke Energy Control Center (source: Patrick Schneider Photo.Com)

  19. Restoration Milestone-based Decision Support Path (Strategy) Milestones • Stop 1 (Milestone 1) • Stop 2 (Milestone 2) • Turn Left (Action 1) • Turn Right (Action 2) • Turn Right (Action 3) • Turn Left(Action 4) • Turn Right (Action 5) • … Decision Support Tool Restoration Path Optimization (Minimizing Duration Time) Actions Simulation Tools (Security Constraints)

  20. Generic Restoration Milestones (GRMs) Generic Restoration Actions (GRAs) A Restoration Milestones based Approach for Developing and Evaluating Restoration Strategies [6][7] • A specific restoration strategy is a combination of specific milestones • Under each milestone, an optimization problem can be formulated to solve restoration actions achieving that milestone with the shortest time • Constraints about, e.g., voltages, overloading and stability, can be checked for each restoration action by a power system simulation tool • GRM1: Form BS_NBS_Building Blocks • GRM2: Establish Transmission Grid • GRM3: Form Electrical Island • GRM4: Synchronize Electrical Islands • GRM5: Serve Load in Area • GRM6: Connect with Neighboring System • GRA1: start_black_start_unit • GRA2: find_path • GRA3: energize_line • GRA4: pick_up_load • GRA5: synchronize • GRA6: connect_tie_line • GRA7: crank_unit • GRA8: energize_busbar

  21. Achieving GRMs by GRAs

  22. GRM1: Form BS-NBS Building Block • Objectives • crank all generators (from a BS unit to NBS units) • pick up all critical loads as quickly as possible. • Dispatchable loads are picked up when necessary to balance restored generation and maintain voltage. • GRAs: • Start the BS unit (GRA1) • Find transmission path from the BS unit to a NBS unit (GRA2) • Build a transmission path (GRA3) • Pick up load (GRA4) • Crank a NBS unit (GRA7)

  23. GRM1: Form BS-NBS Building Block (cont’d) • At stage S, solve the shortest time fS to restore all generators and critical loads by Dynamic Programing: S: the set of restored generators xi: the state (restored generators and loads) at stage S • Constraints: • Power flow equations are solved • No violation on generation limits, transmission limits or voltage limits

  24. Algorithms • Split the complex multistage optimization problem into two sub-problems Alg-1: Finding a neighboring region (within a given depth) around an energized block Alg-2: Finding a transmission path to crank a generator Alg-3: Solve OPF to find an operating point without violation to minimize the duration time Alg-4: Finding dispatchable loads by OPF

  25. Modeling of Generating Units

  26. Demonstration Using a WECC Model • 200-bus system • 31 generating units • 3 critical loads • 5 black start units • Time for energizing a line is 5minutes

  27. Generator and Load Characteristics Generators Critical Loads Dispatchable Loads

  28. Develop Restoration Strategies by GRMs • The system is restored as 5 islands first and then synchronized • GRMs: • GRM 1: Form BS_NBS_BuildingBlocks • GRM2: Establish Transmission Grid • GRM3: Form Electrical Island • GRM4: Synchronize Electrical Islands • GRM5: Serve Load in Area

  29. Restoration Strategy for GRM1 in Island 1

  30. Island 1

  31. Island 2

  32. Island 3

  33. Island 4

  34. Island 5

  35. Voltage Profiles GRM1 for Island 1 GRM3 for synchronizing Islands 1&2

  36. Total Generation Output During Restoration

  37. Comparison of Different Ramping Rates of the BS Unit (Island 5)

  38. “Detour” Function • If line 137-143 in Island 5 is unavailable Original Detour

  39. EPRI’s System Restoration Navigator [8] • Establish GRM-based algorithms to develop or evaluate a restoration strategy • Interactive GUI to provide automatic or interactive strategy development • Milestones and priorities assigned by users • Restoration report on on-line diagram or in text format • Accept PSS/E raw data

  40. Integration with OTS • Operator Training Simulator (OTS) • Simulation engine: • power-flow based pseudo-dynamic • transient simulation • Products: • EPRI OTS • PowerSimulator by POWERDATA and IncSys (Source: powersimulator.net)

  41. GIS Visualization

  42. On-line Diagram

  43. System Messages

  44. System Restoration Navigator

  45. References • M. M. Adibi and L. H. Fink, "Overcoming restoration challenges associated with major power system disturbances - Restoration from cascading failures," Power and Energy Magazine, IEEE, vol. 4, pp. 68-77, 2006. • M. M. Adibi and N. Martins, "Power system restoration dynamics issues," IEEE Power and Energy Society General Meeting 2008. • L. H. Fink, K.-L. Liou, and C.-C. Liu, "From generic restoration actions to specific restoration strategies," IEEE Trans. Power Syst., vol. 10, pp. 745-752, 1995 • J. W. Feltes and C. Grande-Moran, "Black start studies for system restoration," presented at Power and Energy Society General Meeting 2008 • F. Levesque, S. T. Phan, A. Dumas, and M. Boisvert, "Restoration plan — The Hydro-Québec experience," presented at Power and Energy Society General Meeting - Conversion and Delivery of Electrical Energy in the 21st Century, 2008 IEEE, 2008. • Y. Hou, C. C. Liu, K. Sun, et al, “Computation of Milestones for Decision Support during System Restoration”, IEEE Trans. Power Systems, vol. 26 , No. 3, pp. 1399 1409, Aug. 2011 • Y. Hou; C.-C. Liu; P. Zhang; K. Sun, “Constructing power system restoration strategies”, IEEE International Conference ELECO 2009. Page(s): I-8 - I-13, 2009 • System Restoration Navigator (SRN) Version 2.0, EPRI Product ID: 1021715, 2011

  46. Homework – Power System Restoration Find a real-world example for each of the Bottom-Up and Top-Down restoration strategies other than PJM and Hydro Quebec, and describe the restoration milestones Build-Upward (Bottom-Up) (e.g. PJM): Build-Downward (Top-Down) (e.g. Hydro Quebec): Re-energizing the transmission network to pool blackstartpower first Actions include: Start up BS units, Energize the transmission network Crank non-BS units Pick up loads • Based on offline define electrical islands with blackstart capabilities • Actions include • Start up BS units • Crank non-BS units • Restore multiple islands to pick up loads • Synchronize islands