40 likes | 158 Views
Work Breakdown Schedule. Components. Research and find all components Pressure Sensor Micro controller LED Display Operational Amplifier Order components Est. time: 1 week Est. Cost Op Amp: $ 4 each Micro Controller : $6 LED Display: $1.50 Pressure Sensor: $2 each. Circuit Design.
E N D
Components • Research and find all components • Pressure Sensor • Micro controller • LED Display • Operational Amplifier • Order components • Est. time: 1 week • Est. Cost • Op Amp: $ 4 each • Micro Controller: $6 • LED Display: $1.50 • Pressure Sensor: $2 each
Circuit Design • Design circuits for different parts of the network • Create circuit for pressure sensors • Create circuit for LED Display • Create circuit for Micro Controller • Implement circuits into overall network • Test and refine at each stage • Est. time for each stage: 3 weeks
Programming • Create program for the Micro Controller • Test with individual parts of the project • Est. time: 4 weeks