An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GROUNDWATER DEPARTMENT - KERALA NATIONAL HYDROLOGY PROJECT(NHP)- WORLD BANK MISSION C – 1ST MEETING – 17th - 18th August 2017 BENGALURU Shajatnan, superintending engineer i/cnhp and Thomas scaria, senior hydro geologist, Groundwater department Kerala KERALA GROUNDWATER DEPARTMENT

  2. NATIONAL HYDROLOGY PROJECT- SPMU KERALA GROUND WATER Vide go(MS) No. 44/2016/wrd dated 15/07/2016 Govt of Kerala constituted SPMU • Coordinator:- Director Groundwater Department KS MADHU • Project Coordinator, Training Coordinator and nodal Officer :- Superintending Hydro geologist (HP), State Data Centre, Thiruvanathapuram. SABU K DAMODAR • Procurement Officer:- Superintending Engineer(HP), State Data Centre, Thiruvanathapuram. VACANTSince 31st Aug 2016, Full additional charge to EE (Hydrology)- SHAJATNAN • PDS Hydrochemistry :- Chief Chemist Lab Level II, Thiruvananthapuram.. VACANTSince 31st MARCH 2016, Full additional charge to CHEMIST- TESSY • PDS Hydrogeology :- Senior Hydro geologist(HP) State data centre Thiruvananthapuram. AG GOPAKUMAR • Accounts officer :- Senior Finance Officer Groundwater Department . LATHA KERALA GROUNDWATER DEPARTMENT NHP

  3. NHP FUNDS RECEIVED AND EXPENDITURE Expenditure of 3.24 lakhs incurred for trainings and TA, but not updated in MIS due to administrative reasons. KERALA GROUNDWATER DEPARTMENT

  4. MAJOR PROCUREMENT ITEM IN PIP KERALA GROUNDWATER DEPARTMENT

  5. MAJOR PROCUREMENT ITEM IN awP 2016-17 KERALA GROUNDWATER DEPARTMENT

  6. MAJOR PROCUREMENT ITEM IN awP 2017-18 KERALA GROUNDWATER DEPARTMENT

  7. PHYSICAL PROGRESS • Completed • Design of piezometers/low diameter wells approved by CGWB • Selection of wells in association with CGWB as one each in One Block. • Requirement of computer and peripherals consolidated. • Status of DWLR installed in previous projects examined by CWPRS team. • Team constituted for digitization of available data VES etc. • Demonstration for DWLR made. • Process Underway : • Permission from various departments for slim hole installations awaiting. • Mobile applications for well census under process. • Furnishing of district data centers, regional and state data centers. • Proposed: • Purchase of vehicles . * Computer and peripherals. * Purchase of DWLR’s * Lab Equipments KERALA GROUNDWATER DEPARTMENT

  8. Status of bid document KERALA GROUNDWATER DEPARTMENT

  9. Pds status KERALA GROUNDWATER DEPARTMENT

  10. Hydromet station status KERALA GROUNDWATER DEPARTMENT

  11. Status of state wris • Major activities 1.Expand and upgrade water resources monitoring systems including automation with Real Time Data Acquisition System (DWLR Telemetry) decided to select one each in one block ( 152 Nos Proposed immediately) 2. Mobile application for well census - preliminary discussion with kesrc done and fields identified. 3. Upgrading/ procurement of IT equipments, requirement formulated. 4. Up gradation of DATA Processing Centre's, in progress. KERALA GROUNDWATER DEPARTMENT

  12. Public finance management SYSTEM - status Pfms status is approved • pfms id is kltu 00002056 KERALA GROUNDWATER DEPARTMENT

  13. Other issues Major issues • Fill up the vacant positions in SPMU and in the project not Materialized. • Possibility to include expenditure incurred for the construction of Regional Data Possessing Centre Ernakulam in the current PIP. • Possibility for the construction of Regional Data Possessing Centre at Kozhikode. • Engagement of Contract Staff for the implementation of the project – Guidelines to fix salary and allowances ? • Accounts officer is senior finance officer deputed from finance department of government of Kerala ( Frequent Transfers) • ------ KERALA GROUNDWATER DEPARTMENT

  14. Way forward Major activities • Planning to compensate the shortage of regular staff by appointing contract staff. • Infrastructure of the department will be strengthened to progress the project as planned. • Finance wing to be strengthened. • Pursue with the government to fill up the vacant positions. • Institutional strengthening by providing Trainings. • ---- KERALA GROUNDWATER DEPARTMENT

  15. ......... Thank you KERALA GROUNDWATER DEPARTMENT