Project Management – Part 2. Yale Braunstein School of Information Management & Systems UC Berkeley. More on previous topics. The “weekend problem” We changed the working schedule, but this may cause problems if schedule changes (Alt-T-H)

Download Presentation

Project Management – Part 2

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Project management part 2

Project Management –

Part 2

Yale Braunstein

School of Information Management & SystemsUC Berkeley


More on previous topics

More on previous topics

  • The “weekend problem”

    • We changed the working schedule, but this may cause problems if schedule changes(Alt-T-H)

    • Alternate approach: assign “dummy resource” and change its schedule (Select resource on Resource Sheet, then either Alt-T-H or right click)

  • Splitting tasks

  • Finding and “using” slack (tasks off the critical path)

    • Free slack – delays don’t delay ANY other task

    • Total slack – delays don’t delay project finish date


Track progress with ms project

Track progress with MS Project

  • When tasks & timeline are set, save baseline

  • Several alternatives for tracking progress

    • Enter % completed

    • Enter time to complete

    • Enter date completed

      (more than one is allowed)

  • Review for changes in critical path

  • It is now possible to modify the baseline in Project 2000

    • But think about why you want to do this!

    • Work-around for Project 98


Project management part 2

Useful source of additional information


Wide variety of tables charts views reports

Wide variety of tables, charts, views, reports,…

  • Use Help to sort through the many options

    • Use the topic “What view to print?” to see what gets printed in each view

    • “Determine the report to print” gives information on the many reports that are available.

    • See handouts

  • Use page format options


Project summaries

Project Summaries

Alt-P-P-Statistics gives more than Alt-F-Properties-Contents