HF FE schedule

HF FE schedule. Ulrich Heintz Brown University. QIE10 production. June 2014: submitted engineering run includes QIE10 and QIE11 chips September 2014 : expect delivery of chips One wafer will be packaged for preproduction boards December 2014: bench testing complete

lorie
Download Presentation

HF FE schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HF FE schedule Ulrich Heintz Brown University Ulrich Heintz - HF FE schedule

  2. QIE10 production • June 2014: submitted engineering run • includes QIE10 and QIE11 chips • September 2014: expect delivery of chips • One wafer will be packaged for preproduction boards • December 2014: bench testing complete • February 2015: packaged chips delivered • April 2015: robot chip testing complete •  production QIE10 ASICs available for shipment Ulrich Heintz - HF FE schedule

  3. prototype phase • backplane & crates • done – start production of backplanes following today’s review • QIE cards • July 2014: revised QIE card design complete • September 2014: preproduction QIE cards (US) • November 2014: preproduction QIE cards from Turkey/Brazil • ngCCM • September 2014: IGLOO2 mezzanine design complete • October 2014: preproduction ngCCM • calib module • September 2014: prototype of pulser and light distribution system • December 2014 – electronics system review of HF FE Ulrich Heintz - HF FE schedule

  4. production phase • January 2015 – start of production • frontend crates & backplanes (Brazil) • April 2015 – could be earlier (backplane design ready/crates are off the shelf) • QIE cards (Brazil & Turkey) • need packaged and tested QIE10 chips (April 2015??) • July 2015 – QIE cards at CERN • acceptance testing at CERN bat. 904 • calibration system (Brazil) • April 2014 – light mixer shipped to Brazil (US) • July 2015 – calib modules at CERN • ngCCM(US) • August 2015 – ngCCMs at CERN Ulrich Heintz - HF FE schedule

  5. burn-in and installation phase • August 2015 assemble crates in bat. 904 • Aug – Dec 2015 burn-in • December 2015 start installation • February 2016 installation complete • March 2016 commissioning complete Ulrich Heintz - HF FE schedule