Engineering & Construction Management Department. January Report, 2012. EPIA Runway 8R-26L & Taxiway L Extension & Reconstruction of Taxiway W.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Construction Activities: Substantial completion walk-thru conducted. ' - loki


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

Engineering & Construction Management Department

JanuaryReport, 2012

EPIA Runway 8R-26L & Taxiway L Extension & Reconstruction of Taxiway W

  • General Project Description: The project will consist of the extension of Runway 8R-26L 1,100 feet to the east as well as the extension of Taxiway L to the east by approximately 1,100 feet, new runway and taxiway lighting for the extensions and a new hold pad for Runway 26L.

Construction Activities:

  • Substantial completion walk-thru conducted.

  • Contractor removing and replacing cracked concrete panels not meeting FAA specs.

  • Sub-contractor pending receipt and installation of transformers.

  • FAA flight check has been completed.

Project Schedule

Page 1 of 2


Engineering & Construction Management Department

JanuaryReport, 2012

EPIA Runway 8R-26L & Taxiway L Extension & Reconstruction of Taxiway W

  • General Project Description: The project will consist of the extension of Runway 8R-26L 1,100 feet to the east as well as the extension of Taxiway L to the east by approximately 1,100 feet, new runway and taxiway lighting for the extensions and a new hold pad for Runway 26L.

Project Budget: (includes approved project development, design and construction costs) $7,563,087.00

Notes

Funding Source: FAA Grant and PFC

Project Contact

Project Manager Victoria Ruiz

915-541-4357

Design Consultant Kimley-Horn

Construction Contractor J.A.R. Construction

Page 2 of 2