An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Preventive Maintenance Schedules

  2. ROLE OF C&W ORGANISATION • To Provide • Coaches & Wagon • In Good Fettle • To Traffic • To Keep In Good Fettle Requires • Maintenance

  3. MAINTENANCE • Break Down Maintenance • Fail & Fix • Preventive Maintenance • Periodic Maintenance • Attention at Specific Interval • Based on Time / km run

  4. MAINTENANCE • With a view to Increase • Availability of Rolling Stock • Upgradation of Material • Based on Past Experience • Interval has been Increased

  5. COACHING MAINTENANCE Preventive Maintenance Schedule (ICF) Pit Examination As Per RPC-4 A Schedule 30 Days + 3 Days B Schedule 3 Months + 7 Days Intermediate Overhaul 9 Months + 30 Days Coaches incld Pantry Car & VPH For Newly Built & OCV 12 Months Periodic Overhaul 18 Months + 30 Days Coaches incld Pantry Car & VPH For Newly Built & OCV 24 Months

  6. COACHING MAINTENANCE Preventive Maintenance Schedule (LHB) Pit Examination As Per RPC-4 D1 Schedule 7 Days + 1 D2 Schedule 30 Days + 3 Days D3 Schedule 6 Months + 15 Days Shop Schedule - I 18 Months Shop Schedule - II 36 Months Shop Schedule – III 72 Months

  7. PREVENTIVE MAINTENANCE • Coaches • Rake – KM/Time Based • Coach – A B Schedule • Time Based in Rake • Coach – IOH (ICF) D3/SS-I (LHB) • Time Based in Sickline • Coach – POH (ICF) SS-II & SS-III (LHB) • Time Based in Workshop • Out of Schedule Repair • In Rake – in Pitline • Coach – in Sickline/Workshop

  8. MAINTENANCE • Coach is Allotted to Division/Depot by COM • Called Primary Maintenance Depot • In Open Line RPC-4 is Followed • Rajdhani/Duranto • PrevMaint Schedules Primary Depot • Internal Cleaning Both End • External Cleaning Both End • Undergear Examination Both End • and Brake System Maint • Complete Air Brake Testing Both End • with Issue of Fresh BPC

  9. MAINTENANCE • Shatabdi • PrevMaint Schedules Primary Depot • Internal Cleaning Both End • External Cleaning Primary End • Undergear Examination Primary End • and Brake System Maint • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC

  10. MAINTENANCE • Mail/Express Round Trip Journey>3500 Km ICF • 4000 Km LHB • PrevMaint Schedules Primary Depot • Internal Cleaning Both End • External Cleaning Both End • Undergear Examination Both End • and Brake System Maint • Complete Air Brake Testing Both End • with Issue of Fresh BPC

  11. MAINTENANCE • Mail/Express Round Trip Journey<3500 Km ICF • 4000 Km LHB • PrevMaint Schedules Primary Depot • Internal Cleaning Both End • External Cleaning Primary End • Undergear Examination Primary End • and Brake System Maint • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC • Min 3 Hours halt required (expt Intercity Day Train) • At Other End for Cleaning/Bk Power Check

  12. MAINTENANCE • Mail/Express R/Trip Journey<3500 Km ICF • 4000 Km LHB • or 96 Hrs • Touching Primary End more than once • PrevMaint Schedules Primary Depot • Internal Cleaning Both End • External Cleaning Primary End • Undergear Examination Primary End once • and Brake System Maint in 3500/4000 Km or 96 Hrs

  13. MAINTENANCE • Mail/Express R/Trip Journey<3500 Km ICF • 4000 Km LHB • or 96 Hrs • Touching Primary End more than once • (Contd…) • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC • Min 3 Hours halt required • At Primary End for Intermediate Visit • At Other End for Cleaning/Bk Power Check

  14. MAINTENANCE • Mail/ExpressInterconnected <3500 Km ICF • 4000 Km LHB • PrevMaint Schedules Primary Depot • Internal Cleaning Primary End & • Each Terminal • External Cleaning Primary End • Undergear Examination Primary End Once • and Brake System Maint in 3500/4000 Km or 96 Hrs

  15. MAINTENANCE • Mail/ExpressInterconnected < 3500 Km ICF • 4000 Km LHB • (Contd…) • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC • Min 3 Hours halt required (expt Intercity Day Train) • At Other End for Cleaning/Bk Power Check

  16. MAINTENANCE • Passengers with Toilets • PrevMaint Schedules Primary Depot • Internal Cleaning Primary End & • Each Terminal • External Cleaning Primary End • Undergear Examination Primary End within • and Brake System Maint3500 Km/96 Hrs • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC

  17. MAINTENANCE • Passengers without Toilets • PrevMaint Schedules Primary Depot • Internal Cleaning Primary End & • Each Terminal • External Cleaning Primary End • Undergear Examination Primary End within • and Brake System Maint3500 Km/7 days • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC

  18. MAINTENANCE • Dedicated Parcel Trains • PrevMaint Schedules Primary Depot • Undergear Examination Primary End within • and Brake System Maint in 4500 km/10 days • Complete Air Brake Testing Both End • with Issue of Fresh BPC

  19. MAINTENANCE • Military/Election Special • PrevMaint Schedules Primary Depot • Internal Cleaning Primary End & • Each Terminal • External Cleaning Primary End • Undergear Examination Primary End within • and Brake System Maint3500 Km/4000 km /96 Hrs • If stabled at PF Only Brake System Continuity • Otherwise Brake Power Check and • Endorsement on Original BPC

  20. MAINTENANCE • DEMU/EMU/MEMU • PrevMaint Schedules Primary Depot • Internal Cleaning Primary End & • Night Stabling Point • External Cleaning Primary End • Undergear Examination 7 days 700HPDEMU • and Brake System Maint 10 days for Other DEMU/EMU/MEMU • Brake System Check by Crew and Guard

  21. MAINTENANCE • Primary Maintenance • PF Activity • Pit Examination • Periodic Maintenance Schedules • A & B for ICF • D2 for LHB • 6 Hrs Maintenance Time

  22. PRIMARY MAINTENANCE • PF Attention • Rolling in Examination • At Speed Less than 30 Kmph • Unusual Sound of Flat Tyre • Rubbing Grazing Sound • Hanging Parts • Axle Box Temperature Recording • By Infrared Thermometer • Piston Release and Wheel Tapping • To Detect Brake Binding • Finally Issue Brake Power Certificate • After Maintenance Format

  23. PRIMARY MAINTENANCE • Pit Examination • Placement at Pitline • Protection of Rake • By Skid to Prevent Roll Down • By Stop Board to Prevent • Dashing by Engine During Maintenance

  24. PRIMARY MAINTENANCE • Pit Occupation Chart • Shows the Occupation of • Pitline Stabling Line of the Depot • For 24 Hrs X 7 Days • Illustration • Very Important for • Introduction of New Train • Increase in Frequency of a Train • To See Whether • Maintenance Slot Available

  25. PRIMARY MAINTENANCE • Pit Examination • Cleaning • Outside • Inside • Bogie • Lavatory • Disposal Of Garbage • Doorway • Vestibule Area

  26. PRIMARY MAINTENANCE • Pit Examination • Upper Gear Visual Examination and Repair • Piping & Plumbing • Water System • Toilet Flush • Carpentry Work • Seat & Berth • Wall & Ceiling Broken Panels • Window & Shutters • Doors & Latch • Mirror • CDTS/Bio Toilet Attention

  27. PRIMARY MAINTENANCE • Pit Examination • Under Gear Visual Examination • Wheel • Profile • Brake Gear • Draw & Buffing Gear • Bogie • Its Components • Mountings • Reservoirs • All Underslung Items

  28. PRIMARY MAINTENANCE • Pit Examination • Air Brake Testing • Leakage Check & Rectification • Piston Stroke Check & Rectification • Identify Inactive Coach & Rectify • Check Of Brake Power • Should be 100% • Identify any Late Releasing Coach • Rectify • Air Pressure Continuity Check

  29. PRIMARY MAINTENANCE • Pit Examination • Preventive Schedule • A Schedule/D2 Schedule • B Schedule/D3 Schedule • Destination Board Attention • Coach Indication Board Attention • Detachment Of • Overdue POH/IOH Coach • Sick Coach not Rectified during • Pit Attention • Linen Management • Padlocking

  30. SECONDARY MAINTENANCE • Pit Examination Done • At Other End as per RPC-4 • Activities Same As Primary Maintenance • Except • Preventive Maintenance Schedule • Linen Management • Providing Fire Extinguisher • Maintaining Coach Biodata & History • Detaching Overdue POH/IOH Coach

  31. OTHER END ATTENTION • If Not Under Pit Examination • As per RPC-4 • Time Required 3:00 Hrs Minimum • (except Intercity Day Trains) • Rolling in Examination • Dry Sweeping • Lavatory Cleaning • Watering

  32. PREVENTIVE SCHEDULES – ICF • PITLINE • A Schedule 30 Days + 3 Days • All Items of Pit Examination • Dash Pot Oiling • Cleaning of Dirt Collector • Intensive Cleaning of Coach • B Schedule 3 Months + 7 Days • All Items of A Schedule • Attention to PEASD System

  33. PREVENTIVE SCHEDULES – LHB • PITLINE • D2 Schedule 30 Days + 3 Days • All Items of Pit Examination/D1 • Gap between Brake Pad and Disc • Check Wear on Brake Pads • Washing of Bogie • Tread Dia and Wheel Profile • Lubricate Pins and Moving Parts • Intensive Cleaning of Coach • Inspection of Earthing Equipment • WSP Attention as per OEM

  34. PREVENTIVE SCHEDULES – ICF • SICKLINE • IOH 9 Months + 30 Days • Main Job • Overhauling of Bogie • Bogie Overhauling at Workshop • IOH Carried Out at Depot • Coach to be Placed at Sickline • Coach Lifting on Jacks • Bogie Run Out • Fitment of Overhauled Bogie • For Mail/Express Coach

  35. PREVENTIVE SCHEDULES – ICF • SICKLINE • IOH (Contd...) • In Addition • Thorough Inspection of • Coach Body from Under • Centre Pivot • Side Bearer • Draw & Buffing Gear In Situ Condition • Air Brake Testing by Single Coach Test Rig • Attention to Upper Gear • Adjustment of Buffer Height • All Items of B Schedule

  36. PREVENTIVE SCHEDULES – LHB • SICKLINE • D3 Schedule 6 Months + 15 Days • All Activities of D2 Schedule • Examine Bogie Frame for • Corrosion & Cracks • Paint Touch up • Check Wheel Offset • Renew Protection Treatment • On Rubber Joints of Control Arm • Replace Carbon Brush of • Earthing Equipment

  37. PREVENTIVE SCHEDULES – LHB • SICKLINE • Shop Schedule-I 18 Months + 15 Days • 6 Lakhs KM • Main Job • Overhauling of Bogie • Bogie Overhauling at Workshop • Attention to Body Floor • Attention to Couplers • Bogie Run Out • Fitment of Overhauled Bogie • For Mail/Express Coach

  38. PREVENTIVE SCHEDULES – LHB • SICKLINE • SS-I (Contd...) • In Addition • Air Brake Testing by Single Coach Test Rig • Attention to Upper Gear • Adjustment of CBC Height • All Items of D3 Schedule

  39. PREVENTIVE SCHEDULES IN SHOP • POH 18 Months + 30 Days ICF • Shop Schedule-II 36 Months + 30 Days LHB • 12 Lakhs KM • Shop Schedule-III 72 Months + 30 Days LHB • 24 Lakhs KM • MLR 12 Years ICF • MLR 12 Years LHB

  40. PREVENTIVE SCHEDULES IN SHOP • Coaches are sent to Workshop by Division • As per Calling in Program • Calling in Program is made by HQ • As per Capacity of Workshop • If Coaches could not be sent due to • Capacity Constraint of Workshop • Return Date to be Extended

  41. PREVENTIVE SCHEDULES IN SHOP • Periodic Overhaul • Carried Out at Workshop • Cycle Time 18 Days for Non AC • 20 Days for AC & LHB • Lifting Line/Stripping Line • Segregation of Coach based on • Body Repair Work • Light Medium Heavy • Coach Body to Body Shop for • Corrosion Repair • Upper Seat Floor Repair

  42. PREVENTIVE SCHEDULES IN SHOP • POH (Contd...) • Bogie Frame to Bogie Shop for Overhauling • Wheels to Wheel Shop • Wheel to Turning and Gauging • Ultrasonic Testing of Axles • Bearing Attention • Air Brake Items to Air Brake Shop • Electrical Items to Electrical Shop

  43. PREVENTIVE SCHEDULES IN SHOP • Items Specific to LHB • Disc Brake • Brake Calipers • Wheel Slide Protection • Control Arm • Centre Buffer Couplers • Dropping of CBC in SS-III • Changing of Dampers in SS-III

  44. PREVENTIVE SCHEDULES IN SHOP • POH (Contd...) • After Repair of Coach Body • Fitment of All Overhauled Items • Final Air Brake Testing • Final Finishing • Buffer Height Adjustment • NTXR Checking

  45. PREVENTIVE MAINTENANCE • Wagons • Rake – KM/Time Based • Wagon – ROH • Time Based in ROH Depot • Wagon – POH • Time Based in Workshop • Out of Schedule Repair • In Rake – in Yard • Wagon – in Sickline/Workshop

  46. WAGON MAINTENANCE • Preventive Maintenance • At Freight Examination Yard • Called Intensive Examination • End To End Examination Upto Unloading Point • Formed with Empty/Loaded Wagons • Yardstick 56 Manhours • Only One Loading and Unloading

  47. MAINTENANCE • Validity • Closed Circuit Rake 35 Days or 7500 Km A Cat • 30 Days or 6000 Km B Cat • Formed with Off POH/ROH Empty Wagons • Rake Assigned to a Depot • Yardstick 100 Manhours • Multiple Loading and Unloading Between Examination • Premium Examination 12 Days + 3 Days • Formed With Empty Wagons • No Yardstick but taken as 80 Manhours • Multiple Loading and Unloading Between Examination

  48. MAINTENANCE Routine Overhaul Periodicity

  49. MAINTENANCE Periodic Overhaul Periodicity

  50. INTENSIVE EXAMINATION • Rolling In Examination • Axle Box Bearing Temperature • Examination • Air Brake Testing • Repair of Wagons In Situ Condition • Detachment of • Overdue POH/ROH/Overage Empty Wagons • Sick Wagons not repaired during examination