Introduction: global GFR safety approach 1/2

P erformance Assessment of Passive Ga seous P rovisions (PGAP) - FRA 1 Short description of the GFR Part of the slides presented during ICCAP’07 (May 2007, Nice, France) Authors : J-Y. Malo et al. (CEA/DEN/DER/SESI). Introduction: global GFR safety approach 1/2. Fuel Robustness

liona
Download Presentation

Introduction: global GFR safety approach 1/2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Performance Assessment of Passive Gaseous Provisions (PGAP) - FRA 1Short description of the GFRPart of the slides presented during ICCAP’07 (May 2007, Nice, France)Authors : J-Y. Malo et al. (CEA/DEN/DER/SESI)

  2. Introduction: global GFR safety approach 1/2 • Fuel Robustness • - high temperatures, nominal and accidental situations •  Use of ceramics with good thermal conductivity, able to withstand “adiabatic” conditions • Performance of monitoring and protection systems • - detection of fuel failure • - detection of core cooling failure, low pressure, low blower speed, excessive inlet/outlet core temperatures (He transparency)… • - detection of neutronic overpower, reactivity changes… • - reliable shutdown system (CSD, DSD) • - reliable DHR systems (redundant, diversified) •  Based on gas circulation, conduction & radiation (used in HTR) are no longer attractive (high core power density and very limited core thermal inertia)

  3. Introduction, main reactor key design options 2/2 • Design • Nominal thermal-hydraulic conditions Fuel S/A (plate type)

  4. DHR issue, selection of a strategy : , Fully passive mode, considering Hdriving = 15 m 1 25 bar 29 bar (for TinCore 480°C/TfuelMax 1600°C, Hdriving required : ~15 m) (38 bar) pressure (Bar) pressure (Bar) 5 kWe ~ 10 kWe Fully Fully passive mode (15 m) passive mode 7 bar 12 bar 2 5 ~ 50 kWe kWe Forced convection required during a long time (many months) Backup Backup 7 bar 5 bar ~ 1400 kWe 265 kWe 3 Forced Forced convection convection required required during during a a very very long time long time 1 bar 1 bar 3%PN (~ 5 mn) 0,6%PN (1 day) 75,00% 75,00% 125,00% 125,00% 175,00% 175,00% 225,00% Residual power (ANS+10% : %PN) TinCore = 330°C (480°C) TinCore = 330°C Tfuel < 1600°C Tfuel < 1600°C Based on gas circulation, 3 possible strategies: depending on the primary pressure (backup pressure if depressurization) : Option 2 selected for the design and the benchmark 1 High Pressure strategy (DHR under fully NC) : 30 bar required: concrete guard containment pressurized all the time => too heavy and costly solution Medium Pressure (DHR under mixed FC & NC) : 5-10 bar, metallic guard cont., not pressurized in NCs)=> moderate pumping power: “light” self governing systems Low Press. (DHR under FC only) : no guard cont. => high pumping power required 2 3

  5. Main design options, reactor integration principle Guard containment & overall systems arrangement Guard containment spherical metallic structure, enclosing the primary systems Initially: N2, 1 bar Targeted back-up pressure: 5 -10 bar Reactor building, A reinforce concrete containment protection against external hazards includes heavy handlings means ultimate barrier

  6. Main design options, DHR systems pool Secondary loop H2 Exchanger #1 Exchanger #2 Primary loop H1 core Guard containment Schematic of the DHR loop (inside the guard cont.): - Secondary pressurized water loop, under natural convection - Water pool as tertiary circuit

  7. Main design options, 1st combination of possible systems Blower Blower , , with with batteries if batteries if Blower Blower needed needed (operating (operating (operating (operating under under under under 70 70 70 70 - - - - 5 bar 5 bar 5 bar 5 bar ) ) ) ) • Current reference • - 1st level systems: “light” forced convection systems • - 2nd level systems:possibility to rely on natural convection: • in short term for “high” pressure accidental situations • in a “reasonable” time ( 1 day), after LOCA Normal syst. Normal syst. Current systems specifications: Current systems specifications: Backup Backup syst. ( syst. ( necessity necessity to to be confirmed be confirmed ) ) (primary) (primary) ATM. ATM. press press : : NOMINAL NOMINAL press press : : LOCA: LOCA: small small vs vs large large - - med breaches med breaches (GC (GC depress depress 1 1 day day , , refuelling refuelling 1 1 week week ) ) ?  Transient Transient : 70 : 70 – – 5 bar, Final 5 bar, Final press press : 5 : 5 - - 10 bar 10 bar 70 bar 70 bar 1 bar 1 bar High High DH: DH: >1% >1% Alternative self Alternative self governing forced conv governing forced conv Natural Natural Benchmark : - 1 situation pressurized - 1 situation depressurized syst syst : : Turbopump with Turbopump with accu. ( accu. ( with with convection convection previously gas previously gas injection to injection to reach reach 10 10 bars OR bars OR wilful depress wilful depress if if needed needed ) ) ~1 ~1 day day Blower , with Blower Diesel or elec . . Low Low DH: DH: <1% <1% Natural Natural convection ( convection ( with previously gas with previously gas injection if injection if needed needed ) ) Transient Transient Various Various operation operation modes : modes :

  8. Main design options, 1st DHR systems arrangement • 1st global DHR systems lay out, main components pre-sizing • - 1st systems level, “light” forced convection systems, blowers (+ case 1 bar): • 3 x Loop_X (each 100%) in blueand for case 1 bar: 1 x Loop_Y in yellow • - 2nd systems level:“light” forced conv. syst. & natural convection: • 1 x Loop_Y in yellow or 2 x Loop_X (each 100%) in blue, under natural conv. Blowers, 120 kWe, Axial mono stage, Multi  (5-70 bar) Natural convection (70 or 10 bar) H1er+2nd 20 m Blower-turbine or ejector, tbd , gas accumulator (10 bar) Blower, 300 kWe Radial, Multi  ? (1-5 bar) Guard containment

  9. DHR systems evaluation, Cathare models CATHARE models : primary, secondary and a part of tertiairy circuits, and DHR systems