Devico AS Olkiluoto September, 2007. Olkiluoto nuclear power plant. Olkiluoto Nuclear Power Plant is one of Finland's two nuclear power plants. The Olkiluoto plant consists of two reactors each 860 MW. One 1720 MW reactor is under construction. Supposed to start in 2011. Onkalo.

Download Presentation

Devico AS Olkiluoto September, 2007

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Devico as olkiluoto september 2007

Devico ASOlkiluotoSeptember, 2007


Olkiluoto nuclear power plant

Olkiluoto nuclear power plant

Olkiluoto Nuclear Power Plant is one of Finland's two nuclear power plants.

The Olkiluoto plant consists of two reactors each 860 MW.

One 1720 MW reactor is under construction. Supposed to start in 2011.


Onkalo

Onkalo

All nuclear waste produced in Finland must be disposed in Finland.

Olkiluoto has been determined to become the site of disposal of Finnish nuclear waste.

Long term project, intend to start up in 2020.


Repository

Repository

Access tunnel:5.5 km tunnel 1:10

Main characterisation

level –420 m

Lower characterisation

level –530 m

Repository

Ventilation shaft


Ventilation shaft

Ventilation shaft

Depth: 530 meter deep.

The ventilation shaft will be reamed up later.

Our drilling demands was less than 1,75 meter deviation from vertical axis.


Olkiluoto 2005

Olkiluoto 2005

Devico was first time hired in 2005 in Olkiluoto for a similar project

Successful results, no survey shows more than 2 meters deviation from vertical axis.

3 steerings on the way down.


Devico as olkiluoto september 2007

SMOY

  • Worked in cooperation with SMOY.

  • - Diamec U8 drill rig.

  • - NQ rods.

  • Triple tube Corac N3/50.

  • 2 shifts – App. 25 days to finish the borehole.


Directional drilling

Directional drilling

  • Challenges:

  • - Stringent demands

  • - Find the correct direction.

  • Find the toolface.

  • Solutions:

  • Accurate surveying.

  • Repeated and overlapping surveying.

  • Some statistical approaches.


Statistics

Statistics


Statistics1

Statistics


Drilling

Drilling

Drilled two sections à 9 meters.

100-110 meters:Dogleg setting 2.5 / Dogleg app. 7

320-330 meter:Dogleg setting 2.5 / Dogleg app. 5

No return water.

Dark, very hard granite. Almost without fractures, but quart veins.


Results 0 345 meters

Results – 0-345 meters.

PeeWee

DeviFlex

Smoy’s EMS

North - East


Conclusion

Conclusion

  • Possible to orientate hole within stringent demands.

  • Some “confusing” survey results.

  • Important to know the steering capabilities of the DeviDrill in the rock.

  • Teamwork, teamwork! Easy cooperation on the drill site in this project.