An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Spill Response Overview 2013 Clean Gulf Associates

  2. A Not-For-Profit Oil Spill Cooperative Formed By 33 Operators in 1972 “By industry for industry” Mission focused on Gulf of Mexico E & P Oil Spill Response Currently has 130 Members $52 Million in Existing Inventory $13.5 Million in Planned Growth CGA

  3. Mission “Clean Gulf Associates is committed to maintaining a state of the art continuous oil spill response capability with equipment and highly trained and experienced personnel that are ready to meet the on-water oil spill response needs and requirements of our membership.”

  4. The Role of CGA “A Layered Approach to Spill Response”

  5. OFFSHORE

  6. Dispersant Delivery CGA – Airborne Support, Inc. • Airborne Delivery Capabilities via Contract with Airborne Support, Inc. • Waterborne Delivery Capabilities via 4 CGA FRV’s • 34,620 Gallons Dispersant Inventory – CGA (GOM) • 90,000+ Gallons Total Inventory Available to CGA via Cooperative Agreements

  7. Airborne Support, Inc. • 2000 gallon capacity • 5 gallon / acre – appl. rate • 200 gallon per minute • 7 hour flight time / 200 MPH Operational Requirements Loading Crew Dispersant (Corexit 9500) Spotter Aircraft

  8. Dispersant Delivery Fast Response Vessel Self Contained Spray System with Dispersant Pump and Metering Spray by Specially Designed Fire Monitor Dispersant Storage with 350 Gallon Capacity

  9. Elastec Hydro Fire Boom New capability – 2 sets 12-16 burns each In Macondo spill, an estimated 5% of the oil was burned

  10. Oil Spill Containment 25,000 Feet of 43” Auto Boom

  11. Offshore Boom Barge 180’ x 54’ Offshore Boom Barge (25,000 Feet of 43” Auto Boom)

  12. Oil Spill Detection and Tracking • 24/7 (night) spill tracking and response • Aptomar/SeCurus • Radar & Infrared Camera • Installed on HOSS Barge • Capability on 95’FRVs • 3 handheld Diop Cadet 75

  13. Allows Day & Night Skimming/Tracking Operations

  14. X-Band/IR

  15. Oil Spill Recovery Fast Response Vessels • HOSS Barge • Koseq Arms & Aqua Guard Skimmers • Fast Response Vessels 46’ & 95’ • Fast Response Units • Shallow Water Skimmers – Marco, Egmopol, and Trinity Oil Spill Recovery

  16. HOSS Barge High Volume Open Sea Skimmer System System Highlights • Draft: 6 feet, Storage 4,000 bbls • 30 bbl / min recovery rate • 16 Man Living Quarters Operational Requirements • Personnel: 4 CGA/8 OSRO • Offshore Tugs: 2 - 1200 hp • Offshore Tugs: 1 - 1600 hp

  17. HOSS Barge High Volume Open Sea Skimmer System System Highlights • 24 Hour Response Time • 4 – 36” Marco Oleophilic Belts • EDRC – 43,000 bbls Requirements • 2,640’ – 67” Sea Sentry Boom • Helipad: 52’ X 52’ – 20k lbs capacity

  18. KOSEQ Arms & Aqua Guard Skimmers T&T Marine Contract = EDRC 241,000 bbls

  19. KOSEQ Skimming Arms

  20. NEARSHORE

  21. New GenerationFast Response Vessels • Three vessels are completed and operational • Equipped with State-of-the-Art AptomarSECurus Integrated Oil Detection System • Staged in Leeville, Venice, Galveston TX • All aluminum construction with up to 200 mile range and speed of 24+ knots

  22. 46’ Fast Response Vessel (FRV) • Max Speed 25 knots, Cruising Speed 23 knots • Lori Brush Skimmers (2) – Built into Hull • Oil Directed Through Doors by Outrigger Booms • EDRC – 5,000 bbls • Located at Venice, Leeville, Lake Charles and Aransas Pass, TX

  23. Fast Response Unit (FRU) All Sites Operational Requirements • Transportation – 18 Wheeler • UTV – 140‘ • Ideal – 30’x 65’ deck • 10 Ton Crane • 1 CGA/3 OSRO Highlights • High Mobility, Long Duration • 100 bbl Storage • EDRC – 4,251 bbls

  24. New GenerationFast Response Units • All completed • 9 new high viscosity offload pumps • New FRU skimmer heads and boom • Larger and longer boom for existing FRU’s resulting in significantly increased swath width and capability

  25. Offshore Skimming Tactical Direction Cessna CJ3 Citation

  26. INSHORE

  27. Trinity Shallow Water Skimmers • Trinity SWS- Four built • New high capacity shallow water skimmer • Length 56 feet • EDRC 21,500 bbls each • 249 bbls storage each • Two Marco Belt skimmers • Enhanced capability in adverse weather

  28. Recovered Oil Storage Locations – Galveston, Lake Charles, Leeville, Venice Four– 249 Barrel Recovered Oil Storage Barges

  29. Wildlife Rehabilitation • CGA Built Equipment – Designed by Wildlife Rehab Experts • Store, Maintain, and Deployment on a 24/7 Basis • Support Personnel – Set up, Operate, and Assist Clean Gulf’s Role

  30. Wildlife Rehab Trailer

  31. Current EDRC Capability

  32. CGA SITE LOCATIONS Lake Charles Harvey Morgan City Galveston Intracoastal City Venice Leeville Aransas Pass

  33. Current Threats By Location and Volume

  34. CGA Response Strategy Based on the regulatory drivers, potential spill threats and existing gaps in response coverage, CGA’s response strategy is four fold: Provide a robust rapid 6-hour response capability to any near shore oil spill threat Provide a rapid and targeted aerial dispersant response within 2-hours of notification Provide an on water 48-hour surge capability of +600K bbls of EDRC/day Provide a dedicated air asset(s) to tactically direct all on-water response assets

  35. CGA Business Plan • Approved CGA Equipment 2013-2014 • Phase 1 –Immediate Implementation • Purchase One Offshore Oil Spill Recovery Vessel >7500 BBLS EDRC located at Intracoastal City, LA • Purchase Four Shallow Water Skimming Systems located at Intracoastal City, LA, Lake Charles, LA, Ingleside, TX, Pascagoula, MS - 86,000 bbls EDRC • Establish New Shore Base in Intracoastal City, LA • Enhanced Aerial Skimming Surveillance Aircraft • Conduct Koseq Arm system study • Phase 2- 2015 - TBD based on Drilling Activity in the Eastern GOM

  36. EDRC 2014

  37. Future CGA Equipment 2013-2015

  38. New Website www.cleangulfassoc.com

  39. Contact Information (24 Hour) 888-242-2007 Frank Paskewich Email: paskewich@cleangulfassoc.com Phone: 504-799-3035 James Hanzalik Email: hanzalik@cleangulfassoc.com Phone 504-799-3037