FORMWORK for Civil Engineering Construction Works

FORMWORK for Civil Engineering Construction Works. Dr V Srinivasa Reddy Professor of Civil Engineering GRIET Lecture 2. Formwork v. Falsework. Formwork includes Falsework Formwork and Falsework are separate Formwork is the Mould that holds fresh concrete

lewismartha
Download Presentation

FORMWORK for Civil Engineering Construction Works

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FORMWORKforCivil Engineering Construction Works Dr V Srinivasa Reddy Professor of Civil Engineering GRIET Lecture 2

  2. Formwork v. Falsework • Formwork includes Falsework • Formwork and Falsework are separate • Formwork is the Mould that holds fresh concrete • False work supports formwork and other structures (such as precast girders) There are two types of Formwork: 1. Vertical Forms 2. Horizontal Forms Vertical Forms are used to hold pressure Horizontal Forms are used to hold weight

  3. Vertical Forms Vertical Forms are used to form: • Walls • Columns • Piers • Abutments • Beamsides • Other Vertical Concrete Surfaces

  4. Vertical Form: Wall Form

  5. Vertical Form: Shear Wall

  6. Vertical Form: Retaining Wall

  7. Vertical Form: Sidewall/Abutment

  8. Horizontal Forms • Horizontal Forms are used to form: • Bridge Decks • Floors • Overhangs • Other Horizontal Concrete Elements

  9. Horizontal Form: Metal Bridge Deck

  10. Horizontal Form: Bridge Overhang

  11. Horizontal Form: Bridge Overhang (Cantilevered Beams)

  12. Pressure • Vertical Forms are designed to resist pressure. Form Pressure is affected by: • The Concrete Mix • The Rate of Placement • The Temperature of the Concrete • The Weight of the Concrete

  13. Weight • Horizontal Forms are designed to hold the weight of the concrete. The design weight is determined by: • The Depth of the Concrete • The Unit Weight of Concrete • The Amount of Reinforcing

  14. Manufactured Forms What is the Pressure Capacity?

  15. Job-Built Forms Is it designed according to specification? Is it constructed according to the design?

  16. The Perfect Wall?? Bad Joint Blemish

  17. What do you think?

  18. Is the concrete being placed properly?

  19. Falsework Supporting Pier Cap Formwork

  20. Falsework Supporting Precast Concrete Girders

  21. Formwork for Foundations • Wall foundations • It consists of • Plywood Sheeting • Struts

  22. Formwork for Foundations • Column Foundations • It consists of • Side Supports • Side Planks • Cleats Cleats Side Support Side Planks

  23. Formwork for Wall Vertical Posts • It consists of • Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges • After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided. Struts

  24. Formwork for Column • It consists of the following • Side & End Planks • Yoke • Nut & Bolts • Two end & two side planks are joined by the yokes and bolts.

  25. Formwork for Slabs & beams • It consists of • Sole plates • Wedges • Props • Head tree • Planks • Batten • Ledgers • Beam formwork rests on head tree • Slab form work rests on battens and joists • If prop height are more than 8’ provide horizontal braces.

  26. Formwork for Stairs • It consists of • Vertical & inclined posts • Inclined members • Wooden Planks or sheeting • Stringer • Riser Planks Riser Planks

  27. Removal of formwork • Time of formwork removal depends on the following factors • Type of Cement • Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) • Ratio of concrete mix • Rich ratio concrete gain strength earlier as compared to weak ratio concrete. • Weather condition • Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions.

  28. Time of Removal of formwork

  29. Maintenance of formwork • Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. • For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. • For steel formwork plates must be leveled by mallet and loose corners must be welded.

  30. Cost of formwork • For normal works cost of formwork is about 30%-40% of the concrete cost. • For special works cost of formwork is about 50%-60% of the concrete cost. • Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges.

  31. Types of Scaffolding Following are the types of scaffolds • Brick layer’s Scaffolding or Single Scaffolding • Mason’s Scaffolding or Double Scaffolding • Ladder Scaffolds • Needle Scaffolding or Cantilever Scaffolding • Suspended Scaffolds • Steel or Tubular Scaffolds

  32. Definition • Scaffold • It is the temporary support system provided for the construction & maintenance purposes. • It consists of supports and a working platform for workers and Materials. • Scaffolding • Method of construction of scaffolds is called scaffolding.

  33. Single Scaffolds It consists of • Standards (v posts)(10 cm) • Putlogs (7.5 x 7.5) • Ledgers ( • Wooden boards • Braces Used for ordinary buildings 1.2 m

  34. The distance in between two standards is generally kept within 2.4 to 3 m. These standards are connected to each by a longitudinal horizontal member (named as Ledgers). Ledgers are tied with standards at every rise of 120 cm to150 cm (i.e. 4 ft to 5 ft). Rope lashing is used to tie the standard with ledgers. The putlogs (or transverse horizontal members) are placed at a horizontal spacing of 120 cm such that one end is supported on the ledgers and the other end is held in the holes made in the wall. Rope lashing is used to fasten the putlogs with ledgers. If the height of the scaffolding is very high, to maintain its stability, sometimes diagonal members (named as Braces) are provided. Braces are cross diagonally fitted with the standards using rope lashing.

  35. Double Scaffolds • It consists of • Two rows of standards. • 15 cm, 1.5 m • Shores are provided. • Used for superior works

  36. This type of scaffolding is commonly used in case of stone masonry. It is stronger than brick layer’s scaffolding. • The primary differences between brick layer’s scaffolding and mason’s scaffolding are as follow: • In case of brick layer’s scaffolding single row of standard is fixed into the ground. But in case of mason’s scaffolding two rows of standards are fixed into the ground. • First row of standards is fixed close to the wall and second row of standard is fixed at a distance of 1.5 m from the first row. This is why it is named as double scaffolding. • In case of brick layer’s scaffolding one end of putlog is fixed with wall. But in double scaffolding, putlogs are not fixed with the wall. Put logs are supported at both ends on ledgers. Therefore mason’s scaffolding is completely independent of the wall surface. And there is no need to make any hole on the wall surface. • Sometime raking shores are provided to prevent the slipping of scaffolding away from the wall.

  37. Ladder Scaffolds • It consists of • Brackets for Plate form.

  38. Cantilever Scaffolds • It consists of • Cantilever • Struts • Standards • Putlogs • Plate forms • It is used above ground level

  39. Needle scaffolding or cantilever scaffolding is required in the following cases • When it is not possible to fix standard into the ground • When construction is done on the side of a busy street • When construction work is carried out at very high level in case of tall building • In this type of scaffolding instead of fixing the standard into the ground, it is placed at some height above the ground level. The platform on which stands are placed is called needle. A needle is a cantilever structure, made of timber, projected out from the holes in wall.

  40. Suspended Scaffolds • It consists of • Ropes • Working platforms Ropes can be raised Manually or mechanically Used for light construction and finishing works of multistory buildings.

  41. Steel or Tubular Scaffolds • It consists of • Steel tubes (1-1/2” – 2-1/2” diameter) • Coupler or Clamps (to hold pipes in different positions) • Prop nuts (to hold single pipes) • Bolts, Nuts & washers • Wedge & Clip

  42. Scaffold pipes

  43. Coupler or Clamps

  44. Scaffold fittings • Double Coupler • It joins ledgers and standards. • Swivel Coupler • Composed of two single couplers and used to join two scaffolds at any angle. • Putlog Coupler • Used to join putlogs with transom. • Base Plate • Used at the base of the standards. • Split joint Pin • It’s a connection fitting used to join scaffold tubes. • Reveal Pin • It fit in to the end of a tube to form an adjustable strut. • Putlog end • A flat plate used at the end of a scaffold to convert it in to a putlog.