BLM NEPA HANDBOOK Overview and Major Clarifications

BLM NEPA HANDBOOK Overview and Major Clarifications. PLA NEPA Permitting Seminar Denver, Colorado June 11-12 , 2008 Contact: Brian St. George at (303) 239-3709 or Brian_St_George@blm.gov. Topics. Purpose and Need Affected Environment and Environmental Consequences Cumulative effects

lewis-chase
Download Presentation

BLM NEPA HANDBOOK Overview and Major Clarifications

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BLM NEPA HANDBOOKOverview and Major Clarifications PLA NEPA Permitting Seminar Denver, Colorado June 11-12, 2008 Contact: Brian St. George at (303) 239-3709 or Brian_St_George@blm.gov

  2. Topics • Purpose and Need • Affected Environment and Environmental Consequences • Cumulative effects • Contracting NEPA analysis • Categorical Exclusions – especially 390 CXs • Adaptive Management

  3. Why a New NEPA Handbook • Generally to tie the NEPA guidance more directly to CEQ regulations, BLM Planning regulations, Departmental guidance, and evolving case law • A more detailed procedural guide for BLM specialists and the public • Supplementing • Federal Register Notices • Public notification and involvement • Filing with EPA

  4. Purpose and Need • Treats the purpose and need separately • Need can be framed as underlying issue, conflict or problem that requires resolution • Purpose is the objective or solution to problem identified in the Need • Collectively the P&N establish: • why here, why now, why this action • the range of reasonable alternatives • the basis for selecting the preferred alternative • Should be specific but not arbitrarily narrow • Should relate to achieving the goals/objectives of the RMP

  5. Purpose and Need • “Need” tells the reader the problem to overcome or opportunity available • Need is essentially the lack of something wanted, or presence of something unwanted. • “Purpose” identifies criteria the decision maker will consider when choosing the alternative that best meets the need • In essences – the goals to be meet while carrying out the action

  6. Affected Environment and Environmental Consequences • Elimination of critical elements • Emphasizes the“hard look” at effects and impacts – a reasoned analysis containing quantitative or detailed qualitative information • Significance hinges on context and intensity of the impact • Highlights the 10 CEQ considerations for evaluating intensity

  7. Affected Environment and Environmental Consequences • Effects and impacts analysis – the heart of a NEPA document • Emphasizes analysis that tracks with the Alternatives and allows for side-by-side comparisons • Reader should be able to discern a difference in impact • Emphasizes the identification of mitigation measures • Specific practices that reduce, avoid or eliminate effects of the proposed action or alternative • Distinct from design measures included in the proposed action

  8. Connected Actions • Connected Actions are those which • Automatically trigger other actions that require NEPA • Can not or will not proceed without other actions • Limited to actions that are currently proposed • Analysis of Connected Actions • If both are Federal actions, they should be analyzed in a single NEPA document • If non-Federal, we must demonstrate at a minimum that it has been considered as a connected action in the analysis

  9. Cumulative Effects • Emphasizes full accounting of cumulative effects • Geographic scope, Timeframe, Extent • Context, Intensity, and methodology • Reasonably foreseeable actions • Is there an existing proposal? • Is there a commitment of resources, funding? • Has the NEPA process begun?

  10. Cumulative Effects • Cumulative Effects Analysis • Analyze direct and indirect effects of each cumulative issue • Separate analysis for each alternative • Describe the incremental difference in cumulative effect as a result of the proposed action

  11. Contracting NEPA Analysis • Contracting may be used in part or in whole • Contracting does not eliminate BLM’s active role • BLM is responsible for scope and content • BLM should independently review the analysis and decisions • BLM should prepare all decision records • Contractor is chosen or approved by BLM • Recommend including a conflict of interest disclaimer • Recommend using an MOU • MOU must: • Establish roles and responsibilities • Specify that all costs of using a contractor in development of the NEPA document will be borne by the applicant

  12. Categorical Exclusions – Section 390 • BLM must provide justification in case file why a CX applies and ensure compliance with the RMP • 390 CX does not require review for extraordinary circumstances. • BLM must still provide for the same mitigation and BMPs necessary to ensure insignificant impacts • Other procedural steps still apply such as ESA Consultation and National Historic Preservation Act. • Specific guidance provided in IM-2005-247