Basin-Specific Feasibility Studies, ECP Basins Evaluation of Alternatives. STA-3/4. Presentation to STA Design Review Staff. August 21, 2002. STA 3/4. Includes S-7/S-2 and S-8/S-3 Basins Additional Inflows from C-139 Basin South Shore Drainage District S-236 Basin Lake Okeechobee.

lena
Download Presentation

Basin-Specific Feasibility Studies, ECP Basins Evaluation of Alternatives

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Basin-Specific Feasibility Studies, ECP Basins Evaluation of Alternatives STA-3/4 Presentation to STA Design Review Staff August 21, 2002

  2. STA 3/4 • Includes S-7/S-2 and S-8/S-3 Basins • Additional Inflows from • C-139 Basin • South Shore Drainage District • S-236 Basin • Lake Okeechobee

  3. STA-3/4 • Present Design Approx. 16,543 Acres in 3 Parallel Flow Paths • Emergent Macrophyte Marsh Current Design Basis • Under Construction, Scheduled Completion Late 2003 Legend: Existing SAV Existing Spillway Existing Pump Station Existing Control Structure Existing Seepage Pump Station

  4. Baseline Conditions • Current Design, Present Inflows Through 2014 • Current Design, Inflows Modified To Reflect Full CERP Implementation (EAA Storage Reservoirs, Phase 1 and 2) After 2014 • Only Phase 1 Authorized by WRDA 2000 • Not a CERP-sanctioned simulation, assumptions made for the BSFS which may or may not coincide with the final conceptual design for the EAA Reservoirs • Inflow TP Loads Reflect 50% Reduction Due To BMPs In EAA

  5. Baseline 2015-2056 • Hydrologic Data and inflow TP loads taken from District-furnished files • Outflows of long-term average flow-weighted mean TP concentrations estimated by method presented in Phosphorus Removal by Urban Runoff Detention Basins, W.W. Walker, Ph.D. • Preliminary In Nature • Subject to Review and Possible Substantial Modification During Design of EAA Reservoirs

  6. Baseline 2015-2056 • EAA Reservoir Modeled in 4 Components, 3 Hydraulically Linked to STA-3/4 • A1 - Runoff from NNR & Miami Canal Basins • A2 - Overflows from A1, & L.O.R.R. • B - Overflows from A2, and L.O.R.R.

  7. Baseline 2015-2056 • Component A1 • Reservoir Area = 20,400 acres • Average Inlet Concentration = 95 ppb • Average Outlet Concentration = 65 ppb Estimated Long-Term Average Outflow Concentration, Compartment A1

  8. Baseline 2015-2056 • Component A2 • Reservoir Area = 20,400 acres • Average Inlet Concentration = 72 ppb • Average Outlet Concentration = 59 ppb Estimated Long-Term Average Outflow Concentration, Compartment A2

  9. Baseline 2015-2056 • Component B • Reservoir Area = 10,240 acres • Average Inlet Concentration = 71 ppb • Average Outlet Concentration = 59 ppb Estimated Long-Term Average Outflow Concentration, Compartment B

  10. STA-3/4 Baseline • Average Annual Inflows • 2007-2014; 660,889 ac-ft at Mean TP Conc. Of 88 ppb • 2015-2056; 628,502 ac-ft at Mean TP Conc. Of 76 ppb • Average Annual Outflows • 2007-2014; 623,700 ac-ft at FW Conc. Of 36 ppb, Geo. Mean Conc. Of 36 ppb • 2015-2056; 588,100 ac-ft at FW Conc. Of 32 ppb, Geo. Mean Conc. Of 30 ppb

  11. Alternative 1 P • Current Design, Present Inflows Through 2014 • STA-3/4 modified to optimize its performance--in place by 2014 • Conversion of Cells 1B, 2B, & downstream Portion of Cell 3 from emergent to Submerged Aquatic Vegetation (SAV_C4) • Future (With CERP) Inflows 2015-2056 Legend: Conversion to SAV New Control Structures New Small Forward New Levee Pumping Station

  12. Alt. 1 Physical Works • 3.3 Miles of Interior Levee Subdividing Cell 3 • Includes Additional Water Control Structures • Also Includes 3.6 Miles Additional Power Line • Forward Pumping Stations (3 total, capacities range from 24 to 54 cfs) • Pump From Emergent Cells During Drought To Maintain Stages in SAV Cells • Herbicide treatment of Cells 1B, 2B, and (new) 3B

  13. Alternative 2 • STA-3/4 modified to optimize its performance--in place by 2006 • Other Than Implementation Schedule, Identical to Alternative 1 • Existing Condition Inflows Through 2014 • Future (With CERP) Inflows 2015-2056

  14. STA-3/4 Summary of Alternatives * Computed Value Less than Calibration Range, Reported at Lowest Sustainable Concentration ** 2015 - 2056

  15. Sensitivity To SAV Performance * Computed Value Less than Calibration Range, Reported at Lowest Sustainable Concentration

  16. Sensitivity To BMP Performance * Computed Value Less than Calibration Range, Reported at Lowest Sustainable Concentration

  17. General Sensitivity * Computed Value Less than Calibration Range, Reported at Lowest Sustainable Concentration