Minnesota pollution control agency npdes overview
Download
1 / 38

Minnesota Pollution Control Agency: NPDES Overview - PowerPoint PPT Presentation


  • 136 Views
  • Uploaded on

Minnesota Pollution Control Agency: NPDES Overview. Samantha Adams MPCA. Presentation Outline. Feedlot Permitting Thresholds Permit Types Application Process Other Considerations. I. Feedlot Permitting Thresholds: State Animal Units and Federal Animal Numbers. Thresholds

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Minnesota Pollution Control Agency: NPDES Overview' - lel


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Minnesota pollution control agency npdes overview

Minnesota Pollution Control Agency: NPDES Overview

Samantha Adams

MPCA


Presentation outline
Presentation Outline

  • Feedlot Permitting Thresholds

  • Permit Types

  • Application Process

  • Other Considerations


I feedlot permitting thresholds state animal units and federal animal numbers
I. Feedlot Permitting Thresholds:State Animal Units and Federal Animal Numbers

  • Thresholds

    • State Animal Unit Thresholds

    • Federal Animal Number Thresholds

  • These thresholds are critical to determining which type of permit is required for a facility.


I feedlot permitting thresholds animal units
I. Feedlot Permitting Thresholds:Animal Units

  • State of MN use AUs to determine permit types, environmental review, manure management requirements, etc.

    • Local units of governments may do the same

  • It is an important number to accurately represent before applying for a permit on Feedlot Registration Forms, County documents, etc.



I feedlot permitting thresholds animal units1
I. Feedlot Permitting Thresholds:Animal Units

  • Animal Unit (AU) – Unit of measure used to compare difference in the production of animal manure for an animal feedlot or manure storage area.

  • Total Animal Units – Multiply the number of animals of each type by their factor and add the values.


What is the correct answer to the following question; if I had 2489 sows, how many animal units is that?

  • 988.2

  • 862

  • 1002.4

  • 995.6


I feedlot permitting thresholds animal units2
I. Feedlot Permitting Thresholds: had 2489 sows, how many animal units is that?Animal Units

  • Be sure you are using the correct AU for each animal

    • Note: The AU is based on the size and weight of the animal at the time they leave your site


I am at a beef site that feeds them out to market weight, which animal unit should I use for these animals?

  • Beef Feeder Cattle

  • Beef Calves

  • Beef Slaughter Steer or Stock Cow

  • All of the Above


I feedlot permitting thresholds important animal unit thresholds
I. Feedlot Permitting Thresholds: which animal unit should I use for these animals?Important Animal Unit Thresholds

Permitting Thresholds

  • 300 AUs or greater

    • Construction or expansion over 300 AUs requires a state permit

      • Permit may be issued by Delegated County

  • 1,000 AUs or greater

    • Construction or expansion this amount requires a state and/or federal permit

Other Requirements Based on AUs

  • 100 AUs or greater

    • Land application of manure record keeping, nutrient sampling

  • 300 AUs or greater

    • Manure management plan required


I. Feedlot Permitting Thresholds: which animal unit should I use for these animals?US-EPA Large CAFO Animal Number Thresholds


I. Feedlot Permitting Thresholds: which animal unit should I use for these animals?US-EPA Large CAFO and MN State Thresholds


Would the county or state be responsible for permitting a brand new site proposing to house 2,800 head of finishing swine 55-300 lbs?

  • County

  • State


I feedlot permitting thresholds state animal units and federal animal numbers1
I. Feedlot Permitting Thresholds: brand new site proposing to house 2,800 head of finishing swine 55-300 State Animal Units and Federal Animal Numbers

  • If the facility meets one or both of the thresholds (EPA Large CAFO and MN 1,000 AUs), then the facility is required to have a state or federal permit to construct, expand and operate your feedlot.


Presentation outline1
Presentation Outline brand new site proposing to house 2,800 head of finishing swine 55-300

  • Feedlot Permitting Thresholds

  • Permit Types

  • Application Process

  • Other Considerations


II. Feedlot Permit Types: NPDES/SDS brand new site proposing to house 2,800 head of finishing swine 55-300

  • Feedlots that fall into either US-EPA Large CAFO definition and/or MN 1,000 AU Threshold must have:

    • Joint National Pollution Discharge Elimination System/State Disposal System Permit (NPDES/SDS)

      • General

      • Individual

    • Or, State Disposal System Permit (SDS)

      • General

      • Individual

    • Or, for Large CAFOs that are zero discharge, NPDES/SDS and SDS permits are optional


II. Feedlot Permit Types: NPDES/SDS brand new site proposing to house 2,800 head of finishing swine 55-300

What does “zero discharge” mean?

No discharge is where nopollutants from manure or process wastewater generated in a barn, open lot, manure or feed storage area enter a water of the US.

Exception: When overflow occurs from a feedlot designed, constructed, operated, and maintained to contain all manure and process wastewater, and runoff from a 25 yr. - 24 hr. rain fall event.

Operation & Maintenance Practices are verified by:

  • Routine visual inspections

  • Use of depth markers for liquid impoundments

  • Mortality handling

  • Recordkeeping


Ii feedlot permit types npdes sds
II. Feedlot Permit Types: NPDES/SDS brand new site proposing to house 2,800 head of finishing swine 55-300

  • National Pollutant Discharge Elimination System (NPDES)/State Disposal System (SDS) permit

    • Combination of Federal and State requirements

    • Provides protections under Clean Water Act

    • Current permit will expire on 1/31/2016

    • Needed when proposing a new or expanding an existing facility, or to operate an existing feedlot that:

      • Meets or exceeds the US-EPAs Large CAFO threshold; and

      • Discharges to waters of the US; or

      • Elects to have coverage


Ii permitting npdes sds permit
II. Permitting – NPDES/SDS Permit brand new site proposing to house 2,800 head of finishing swine 55-300

  • Two Types of NPDES/SDS Permits

    • General

    • Individual


II. Permitting – NPDES/SDS Permit brand new site proposing to house 2,800 head of finishing swine 55-300

  • Two Types of NPDES/SDS Permits

    • General

    • Individual


Ii permitting sds permits
II. Permitting – SDS Permits brand new site proposing to house 2,800 head of finishing swine 55-300

  • State Disposal System (SDS) Permits

    • General

    • Individual

    • Construction under these permits may also require a Construction Stormwater Permit

    • Not available at this time, permits being drafted and more information will be forthcoming


What do i need to remember about sds and npdes permits
What do I need to remember about SDS and NPDES Permits? brand new site proposing to house 2,800 head of finishing swine 55-300

  • I need to know when to permit with an SDS or NPDES

  • I need to know when a site exceeds the CAFO threshold or 1000 AU and refer to MPCA


Presentation outline2
Presentation Outline brand new site proposing to house 2,800 head of finishing swine 55-300

  • Feedlot Permitting Thresholds

  • Permit Types

  • Application Process

  • Other Considerations


Iii permitting application process
III. Permitting – Application Process brand new site proposing to house 2,800 head of finishing swine 55-300

  • MPCA must review your application within 15-business days

  • NPDES/SDS permits require a 30-day Public Notice

  • We make great efforts to issue your permit correctly and timely


Presentation outline3
Presentation Outline brand new site proposing to house 2,800 head of finishing swine 55-300

  • Feedlot Permitting Thresholds

  • Permit Types

  • Application Process

  • Other Considerations


VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Environmental Review

  • Project Thresholds for Environmental Assessment Worksheet (EAW)

    • Mandatory

      • Environmental Review Required for Project.

    • Discretionary

      • Environmental Review may be done for Project.

    • Exempt

      • Environmental Review may not be done for the Project.


Mandatory

VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Environmental Review

Mandatory

Mandatory EAW Thresholds

Sensitive Areas

  • Construction of a new AFO with a capacity of 1,000 AU.

  • Expansion of an existing AFO by 1,000 or more AU.

  • Construction of a new AFO by 500 or more AU in a sensitive location.

  • Expansion of an existing AFO by 500 or more animal units in a sensitive location

  • Shoreland

  • Delineated flood plain

  • Designated wild and scenic river district

  • Delineated DWSMA

  • Within 1,000 feet of a known sinkhole, cave, resurgent spring, disappearing spring, Karst window, blind valley, or dry valley.


VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Environmental Review

Discretionary

Petitions

  • A governmental unit with jurisdiction may order the preparation of an EAW for any project that does not exceed mandatory thresholds … and when the project is not exempted.

  • An EAW may be required with a Petition that:

    • Is signed by at least 100 individuals

    • Is submitted before the project has received final approval by the appropriate governmental units

    • Demonstrates that there may be potential for significant environmental effects


Exempt

VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Environmental Review

Exempt

  • The expansion of an existing feedlot by less than 100 AUs, not in a sensitive location.

  • The construction of a new, or expansion of an existing feedlot by 50 AUs regardless of location.

  • Feedlots outside sensitive areas are exempt when:

    • New feedlot has a capacity less than 1,000 AUs, or the feedlot has a total capacity of less than 1,000 AUs after expansion; and

    • County board holds a public meeting for citizen input 10 business days before the feedlot permit is issued, unless another public meeting for citizen input has been held with regard to the feedlot to be permitted.


Do i need to even worry about eaws
Do I need to even worry about EAWs? brand new site proposing to house 2,800 head of finishing swine 55-300

  • No, MPCA takes care of these

  • Counties never see these

  • Yes, counties can be responsible for being the RGUor forwarding to MPCA


Phased actions

VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Environmental Review

Phased Actions

Phased Action Requirements

Additional Information

  • Two or more projects to be undertaken by the same proposer that:

    • Environmentally impact the same geographic area; and

    • Are undertaken sequentially over a limited period of time.

  • “Limited Period of Time” is three years between start of construction of one project and the date of application for the next project.

  • “Same Geographic Area” is:

    • Determined on a case by case basis with the following considerations:

      • Potential impacts to air quality.

      • Potential impacts to water quality.

      • Land application sites.

      • Watersheds.


VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Multi-Site Permitting

  • Determine if feedlots are separate or combined

  • Multiple sites (and AUs) are combined when:

    • There is Common Ownership; and

    • The Sites Adjoin; or

    • The sites use common areas or system for disposal of wastes

      • Land application acres or comingling of manure


Common ownership

VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Multi-Site Permitting

Common Ownership

  • Definition of owner from Minn. R. 7020.0300

    • MPCA considers husband and wife as a single owner

    • MPCA considers minor children as a single and common owner

  • Subpart 17: "Owner" means all persons having possession, control, or title to an animal feedlot or manure storage area.


Adjoining production s ites

VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Multi-Site Permitting

Adjoining Production Sites

Production sites adjoin if:

  • within ¼ mile of each other

    • Measured from barns, open lot, or storage areas

    • Road, ditch or fence, do not constitute “separation” (if within ¼ mile)


Common areas or system for land application

VI. Other Considerations: brand new site proposing to house 2,800 head of finishing swine 55-300

Multi-Site Permitting

Common areas or system for land application

  • Duplicate acreages noted in the manure management plan, or

  • Commingling in a shared manure handling system

    • Not common system just because same third party takes the manure

    • Not common system if using same equipment and never mixing manure sources


In conclusion
In conclusion… brand new site proposing to house 2,800 head of finishing swine 55-300

  • Many considerations to make as a producer expands their operation

  • Long-term plans for expansion should include future permit requirements

  • MPCA and CFOs can assist in planning for your expansion, navigating state and federal requirements and completing an application

    • MPCA and CFO commonly meet together with a producer to address these needs at one time.


Questions
Questions brand new site proposing to house 2,800 head of finishing swine 55-300