D0 Trigger Status. 7 MHz input rate Data. Brief discussion of each project Great progress all systems Significant delays Manpower Shortages Technical Difficulties Delivery. Framework. Data Log. L1 4.2 m s. L2 100 m s. L3 48+ ms. 50 Hz. 7 kHz.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' D0 Trigger Status' - leanna


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
d0 trigger status
D0 Trigger Status

7 MHz input rate Data

  • Brief discussion of each project
  • Great progress all systems
  • Significant delays
    • Manpower Shortages
    • Technical Difficulties
    • Delivery

Framework

Data Log

L1

4.2 ms

L2

100ms

L3

48+ms

50 Hz

7 kHz

1000 Hz

48 nodes

128 terms

128 terms

framework status
Framework Status
  • Components(MSU)
    • Operational
  • Commissioning/Schedule
    • Support detector commissioning
    • Complete readout to L3 by 1/11
    • Integrating with L2
    • L2 trigger mask and pseudo-terms deferred?
  • Firmware
    • Need to complete pseudo-terms
    • Commission run-control
  • Personnel
    • Loss of senior engineer, Steve Gross
    • Loss of engineer, Kirsten Moore
    • Replacement uncertain

Good progress, on time

detector l1 l2 components

L1CAL

Detector/L1/L2 Components

L1

LUM

LUM

L2Cal

CAL

L1

FPS

FPS

L2PS

CFT/

CPS

Global

L2

L1

CTP

L2CFT

L2STT

SMT

L2

Muon

L1

Muon

Muon

L2FW:Combined

objects (e, m, j)

L1FPD

FPD

L1FW: towers, tracks, correlations

luminosity monitor status
Luminosity Monitor Status
  • Components(Brown)
    • Scintillator(48) Complete
    • Electronics
      • CAFÉ boards(175) on hand
      • Completing ADC(~12) board layout, ordering parts
      • Vertex board, FPGA 75% complete, layout commencing.
    • Procuring signal cables(~60) soon
    • Crate/PS on hand
  • Commissioning/Schedule
      • Installed Scintillator 4/00
      • Cabling awaits FPS.
      • February 1, Electronics Installed
      • March 1, Luminosity Monitoring
      • March-April, and/or terms.
  • Software
      • Working on embedded software
      • Download currently underway.
      • Database under development

Good progress, on time

l1ctp fps fpd

CTT Organization showing links to the L1 TM, L2

PreProcessors and L3

AFE

MIX

DB/DBTC

COL

BC

TM

L3

OCT 1

CFT

L1CFT

Ax.

/CPS

Ax.

L3

75

L3

OCT 2

L3

OCT 3

L2CFT

·

Q 1

L3

L2PS

OCT 4

L2CFT

·

Q 2

L3

L2PS

OCT 5

L2CFT

Q 3

·

40

L3

L2PS

OCT 6

L2CFT

·

Q 4

L3

·

L2PS

OCT 7

CPS

·

L3

Ax.

·

m

OCT 8

L1

TM

5

OLR 1

L2STT

SEXT 1

L3

OLR 2

L2STT

SEXT 2

L3

OLR 3

L2STT

SEXT 3

L3

OLR 4

L2STT

SEXT 4

L3

OLR 5

L2STT

SEXT 5

L3

CFT

OLR 6

Stereo.

L2STT

SEXT 6

75

L3

L2PS

N U

L3

5

L2PS

N V

L3

CPS

L2PS

Stereo

S U

L3

10

L2PS

S V

L3

L2FPS

N U

L3

L2FPS

N V

L3

FPS

L1FPS

16

L3

L2FPS

32

S U

L3

L2FPS

S V

L3

LEGEND

Analog Boards

FSC LINK

LVDS LINK

the inset shows

CFT

LVDS LINK

the number of

G LINK

Stereo.

each type

3

TRANSITION

CARDS

DAUGHTER

CARDS

Each color

Each filling

corresponds to a

corresponds to a

Created by Manuel I. Martin

different flavor

different flavor

May. 6, 99

L1CTP/FPS/FPD
l1 ctp fps fpd status
L1 CTP/FPS/FPD Status
  • Components
    • Analog(Fermilab-D0)
      • AFE-8MCM (CFTax): At vendor, full order complete 1/18/00
      • AFE-12MCM (FPS):
        • motherboard prototype this month
        • daughter prototype board order 1/01
      • Crates/Cables on hand
      • Power supplies delayed until new year (partial).
    • Mixer(Fermilab-CD)
      • Super-sector (1/5th) 11/15
      • Full Mixer 1/01
    • Digital(Fermilab-D0)
      • Motherboard here
      • Transition module 1/11
      • CTP daughter boards 11/15
      • FPS daughter board order out, parts on order
      • Crates/Cables/PS here
  • Firmware
      • AFE & Mixer complete
      • DFE 50%
      • Collector/Broadcaster 50%
      • No diagnostics
l1 ctp fps fpd status1
L1 CTP/FPS/FPD Status
  • Commissioning/Schedule
      • Assembling test stands for digital/VHDL
      • Installing cables/crates on platform
      • Crates/Cables installed in MCH.
      • Analog
        • 10 AFE8 installed, operating 12/00
        • Balance at FNAL by 1/18/01
        • AFE12 unknown (in prototype)
        • Supplies as arrive
      • Digital
        • Sufficient hardware for commissioning
        • Balance Installed by 12/00
  • Personnel
      • Recently lost Kin Yip (FNAL postdoc) & Juan Lizarazo (FNAL Co-op) both on VHDL
      • A position has been available but not yet filled & a new student arrived.
      • Reduced engineering (John Anderson) has delayed AFE12.
      • Have redirected Jamieson Olsen to assist with VHDL, Fermilab arranging technical help to assist reorganization and installation.

Good progress on all fronts

AFE12, VHDL concerns

l1 cal status
L1 CAL Status
  • Components
    • Analog pick-offs (320) to accommodate changed BW prototyped. 1FTE month to production
    • Quadrant hardware (40) circuit/firmware designed
    • L2/L3 Readout complete
  • Commissioning/Schedule
    • Inactive until framework complete 11/00. Within a month progress should resume
    • Start w/ analog pick-offs
    • L2 & L3 readout 11/00
  • Firmware
    • All exists, not all tested
  • Personnel
    • Same as framework

Late but well before 3/01

l1 muon status
L1 MUON Status
  • Components
    • L1MuTrigger (4 crates) Prod Beginning(UAz)
      • Motherboard: starting production/fabrication
      • Scintillator daughter board: preproduction in assembly
      • Wire daughter board: production board in design
      • Crate Manager: testing production card, balance to be assembled
      • Trigger Manager daughter-board: starting prod/fab now
      • Serial Link Transmitters complete
      • Serial Link Receivers production testing
    • MCEN (5 crates) in Preprod Testing(BU)
      • MCEN: preproduction testing underway
      • Centroid Daughter Board: preprod, testing underway
      • Crate manager: preprod layout.
    • Crates/Backplanes complete
    • Power Supplies on order.
l1 muon status1
L1 Muon Status
  • Software
      • Download Infrastructure in place
      • Preproduction versions of all firmware exist.
      • No alarms, monitoring
  • Personnel
      • Arizona down to zero from two postdocs. Advertising for one replacement
      • Boston post doc hired, visa difficulties
      • Discussing Ken Johns buy-out.
      • Need help w/ assembly/test of PSupplies
  • Commissioning/Schedule
      • One trigger, one manager crate in operation and readout.
      • Next providing L1CTPT Manager Crate.
      • Two Octants triggering by 11/00
      • L1 Muon full crate assembled 1/01
      • MCEN full crate assembled 3/01

L1Muon before 3/01

Some concern MCEN, manpower

l2 component status
L2 Component Status
  • Alpha serial processors (MSU,UM,UIC):
    • Production Status
      • 3 preproduction worked “out-of-the-box”
      • ADCO, same vendor that produced CDF TDCs
      • About 25 stuffed or nearly stuffed
      • Parts for another 15 in reserve
      • Many key components obsolete
    • Diagnostics @ UM
      • Four boards
      • To our knowledge none work
    • Diagnostics @ UIC
      • 10 boards
      • 2 incorrectly mounted components 8 have partial functionality
      • Rapid learning curve
    • Considering a range of options
      • Repair sufficient boards for March 1, 2001
      • Build new boards with larger vias and reserve parts
      • Build new boards with larger vias. Recover components and build full complement.
      • Re-layout board and/or find new vendor
      • Complete redesign
    • Hope to decide before November 1, leaning towards full press: repair, new boards, and redesign
    • Complicating commissioning.
l2 components cont
L2 Components Cont.
  • MBT I/O Cards(U-Maryland):
      • 6 production cards received. 3 pass specs. 3 under test now
      • Firmware functionality 90% done.
      • Remaining 25 boards built, parts on hand
      • Balance by December.
  • FIC L1/L2 Interface(SACLAY):
      • Boards complete
      • Final firmware adjustments October 16-20.
  • SLIC Parallel Proc.(NIU,Columbia):
      • Boards complete
      • First results from DSP Central algorithm meet speed/efficiency requirements
  • CIC, SFO Muon/L2 Interface (U-Neb):
      • Prototypes pass battery of tests but not up to standard design practices (two layers, unconventional shielding planes, unequal traces on differential signals...)
      • Have solicited advice from Fermilab engineers but process delayed by illness. Restarting now.
      • Delivery December?
l2 status cont
L2 Status Cont.
  • Software
    • C++ Framework exists
    • Preprocessor algorithms well developed, global needs attention.
  • Commissioning/Testing:
    • MCH and test stand racks and crates 85% done. Cabling 65% done
    • Commissioning sequence under discussion.
    • Essentially on hold until alpha, CIC, SFO issues resolved.
    • Once alpha’s MBTs are on hand the L2CAL, L2CTT, L2PS can be assembled <1 month.
  • Personnel
    • Recently lost one key postdoc from UIC and one from Maryland, will lose another UIC postdoc at the end of the year
    • One UIC postdoc has been replaced and new ones added from MSU and Columbia
    • Lack of on-site coordinator has slowed progress. Discussing Nikos Varelas buy-out.
    • Lack of project engineer has slowed progress. However, Rich Kwarciany (CD Electronics System Engineer) has been a great help as an on-call consultant. Fermilab looking into this.

MBT, SLIC, FIC ready before 3/01

Alpha, CIC/SFO, manpower concerns

slide14
STT
  • Motherboard & communication daughter board
    • First prototypes in hand or being built
    • November
  • Fiber Road & Track Fit daughter boards
    • Parts in hand
    • prototypes coming (Feb/ Dec)
    • VHDL and simulation in progress
  • STC(hit filter, cluster finder)
    • VHDL design/coding in progress
    • Not easy to fit into real estate
      • May change Altera to Xilinx?
      • Or fancier Altera?
  • VME CPU: purchase in progress
  • Schedule
    • Schedule in mid-update
    • Attempt integration in Feb 2001 with first prototypes, not 2nd
    • Scheduled Complete Feb 2002
daq l3

Digitizing Crates

(2 of 16 groups)

Data

pathway

o o o

Receiver

Collector

(1 of 8)

o o o

VBDs

Fiber Path

(8 total)

Event Tag

Generator

Levels 1,2

Trigger data

o o o

o o o

Event tag

path

o o o

o o o

Segment

Bridge

Processor

Nodes

(4 groups of 16)

DAQ/L3
  • Evolved to a single multipurpose card used in VRC, SB, processor nodes (~100)
  • VHDL code specific to VRC, SB, Node complete
  • ETG is one of a kind.
l3 daq status
L3/DAQ Status
  • Components(Brown)
      • Layout done for 6 wks, parts procurement difficult.
      • 25 board order placed with vendor
      • Layout @ board houses. Bids received. Production complete < 2 weeks.
      • Procuring parts now w/ Fermilab assistance
      • 5 days to stuff & check
  • Software(Brown,Washington)
      • Framework up and running
      • Nodes also operational
  • Commissioning/Installation
      • Maintaining emulators for commissioning, no schedule delay for other systems.
      • Cable plant is minimal - reuses infrastructure, MCH 50% done, remainder under discussion.
  • Schedule (full chain by Jan 1)
      • After receipt of board 1-2 week at Brown, then install 4 VRCs @ DAB
      • 2 wks install 1 SB, fiber between VRC-SB
      • 2 wks install multiple node adapters, fiber between SB-node.
      • ETG January

Software in good shape

Watching delivery closely

filtering database
Filtering/Database
  • Components(Various Institutions)
    • Operational version of ScriptRunner
    • Unpacking code for cal, smt and muon
    • electron, muon, jet, missing et, and tau tools
    • Database and interface in design.
  • Installation/Commissioning
    • Participating in online tests of PDTs, CFT.
    • Participating in 10% SiDet Test
    • Milestone: readout/filtering muon system!
  • Personnel
    • Impending departure of Charles Leggett (LBL) infra-structure (unpack,tool template,offline verification)
    • Carmem Silva (LAFEX) database, currently only 1FTE on database
    • Insufficient support for NT release & porting.
    • Too few tool authors!
  • Schedule
    • 11/00 standard running including ScriptRunner in Mark & Pass mode
    • 1/01 monitor displays available
    • 3/01 operational versions of all physics tools ported and available

Filtering operable, needs personpower

reportable milestones
Reportable Milestones

Priorities:

(1) FWK, L1mu, L1CAL, L3

(2) L2Global, L2CAL

(3) L1&L2 CTPT, FPS

personnel increases
Personnel Increases?
  • To free engineers for VHDL preparation a senior technician to assist CTPT construction. Could also help with L1Muon, L2 installation. Fermilab investigating.
  • An engineer to assist L2 debugging & integration. This could be considered an escalation of the already valuable on-call arrangement. Fermilab investigating
  • Trying to arrange full-time contributions from
    • Ken Johns L1Muon
    • Nikos Varelas L2
  • Looking fortwo programmers for
    • L3 infrastructure/release (Fermilab/LBL?)
    • Database (Collaboration?)
  • Other needs:
    • Examines
    • L2 tools & verification
    • L3 tools & verification!
closing comments
Closing Comments
  • Trigger making excellent progress in all areas. (Didn’t mention TrigSim but will be a release Nov 1.)
  • Responding to delays by adding people to construction and commissioning efforts.
  • Will make L2alpha decision soon & trying to accelerate L3 component delivery.
  • First priority FMWK, L1CAL, L1Muon, L3. Then will add systems as components come available.
  • Now’s the time to help: tools, filtering, database, commissioning.