Flowgate Selection for Economic Simulations

Learn about the impact and criteria for selecting flowgates in economic simulations. Manage economic dispatch and ensure a reasonable economic solution. Get insights from flowgate simulation data and understand the effect of adding flowgates. Next steps for flowgate selection.

lbyers
Download Presentation

Flowgate Selection for Economic Simulations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ITP20 Flowgate Selection Introduction Timothy Miller July 21st, 2010 TWG Teleconference

  2. Flowgate Simulation Impact • In the economic simulations flowgates are the only flow control mechanism • Line limits are not heeded by default • Penalties associated with an overload provide control • Manage the economic dispatch • Key to a reasonable economic solution

  3. Selecting Reasonable Flowgates • Staff is developing flowgates based upon the ITP 20 Year Assessment Scope document • Preferred outcomes • Spreadsheet listing the flowgates • Charts summarizing the simulated data • Maps showing congestion

  4. Flowgate Selection Criteria

  5. Flowgate Selection Criteria • Starting Point • NERC Book of Flowgates • Additional criteria • 345 kV Contingencies • 115+ kV Monitored Elements • Evaluate 8,760 hours

  6. Flowgate Selection Criteria • Additional criteria • SPP devices and tie-lines • 60 hour threshold • Rate A & Rate B unchanged • Three iterations

  7. Unique Operational Flowgates

  8. Unique Operational Flowgates • SPP-SPS interfaces • Staff recommends redefining flowgate as individual OTDF flowgates due to extensive upgrades in place by 2030.

  9. Unique Operational Flowgates • GGS Stability Interface • Staff recommends continued use of this interface

  10. Example Flowgate Simulation Data

  11. Flowgate Example Results • Violations avoided by flowgate definition • Before & After • By Area • By month

  12. Effect of Adding Flowgates

  13. Flowgate Example Results • Flowgate congestion • Limit is respected • Prices change

  14. Congestion by Shadow Price Impact

  15. Next Steps • Staff to provide TWG draft results: • Top 10 congested flowgate summary • Exhaustive flowgate spreadsheet • Hours Congested & Avg. Shadow Price • Results of contingency scans • Requesting TWG endorsement of flowgates in August teleconference

  16. Timothy MillerPlanning Engineer 501-614-3357tmiller@spp.org