Shifted gradients begin at a time other than between periods 1& 2. Must use multiple factors to find P in year 0. Arithmetic. Shifted Gradients. (a)$101 (b)$295 (c)$370 (d)$397. Example : John Deere expects the cost of a

Download Presentation

Shifted gradients begin at a time other than between periods 1& 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Shifted gradients begin at a time other than between periods 1& 2 Must use multiple factors to find P in year 0 Arithmetic Shifted Gradients

  2. (a)$101 (b)$295 (c)$370 (d)$397 Example : John Deere expects the cost of a certain tractor part to increase by $5 /yr beginning 4 years from now. If the cost in years 1-3 is $60, the present worth of the cost thru year 10 at an interest rate of 12%/yr is closest to:

  3. Example : John Deere expects the cost of a certain tractor part to increase by $5 /yr beginning 4 years from now. If the cost in years 1-3 is $60, the present worth of the cost thru year 10 at an interest rate of 12%/yr is closest to: 1 10 3 0 2 4 5 60 60 60 65 70 (a)$101 (b)$295 (c)$370 (d)$397 95 Cash Flow Diagram i=12% The cash flow diagram is as follows:

  4. Example : John Deere expects the cost of a certain tractor part to increase by $5 /yr beginning 4 years from now. If the cost in years 1-3 is $60, the present worth of the cost thru year 10 at an interest rate of 12%/yr is closest to: P2=? 1 10 3 0 2 4 5 0 1 2 3 8 60 60 60 65 70 (a)$101 (b)$295 (c)$370 (d)$397 95 P2 = 60(P/A,12%,8) + 5(P/G,12%,8) = $370.41 i=12% The cash flow diagram is as follows: First find P2 for the gradient ($5) and its base amount ($60) in year 2:

  5. Example : John Deere expects the cost of a certain tractor part to increase by $5 /yr beginning 4 years from now. If the cost in years 1-3 is $60, the present worth of the cost thru year 10 at an interest rate of 12%/yr is closest to: P0=? 1 10 3 0 2 4 5 0 1 2 3 8 60 60 60 65 70 (a)$101 (b)$295 (c)$370 (d)$397 95 P0 = P2(P/F,12%,2) = $295.29 i=12% The cash flow diagram is as follows: First find P2 for the base amount ($60) & gradient ($5) in year 2: P2 = 60(P/A,12%,8) + 5(P/G,12%,8) = $370.41 Next, move P2 back to year 0:

  6. (a)$101 (b)$295 (c)$370 (d)$397 PA= 60(P/A,12%,2) = $101.41 Example : John Deere expects the cost of a certain tractor part to increase by $5 /yr beginning 4 years from now. If the cost in years 1-3 is $60, the present worth of the cost thru year 10 at an interest rate of 12%/yr is closest to: PA=? i=12% 1 10 3 0 2 4 5 60 60 60 65 70 95 The cash flow diagram is as follows: First find P2 for the base amount ($60) & gradient ($5) in year 2: P2 = 60(P/A,12%,8) + 5(P/G,12%,8) = $370.41 Next, move P2 back to year 0: P0 = P2(P/F,12%,2) = $295.29 Next, find PA for the $60 amounts of years 1 & 2:

  7. PT= ? 1 10 3 0 2 4 5 Example : John Deere expects the cost of a certain tractor part to increase by $5 /yr beginning 4 years from now. If the cost in years 1-3 is $60, the present worth of the cost thru year 10 at an interest rate of 12%/yr is closest to: 60 60 60 65 70 (a)$101 (b)$295 (c)$370 (d)$397 95 PT= P0 + PA = $396.70 i=12% The cash flow diagram is as follows: First find P2 for the base amount ($60) & gradient ($5) in year 2: P2 = 60(P/A,12%,8) + 5(P/G,12%,8) = $370.41 Next, move P2 back to year 0: P0 = P2(P/F,12%,2) = $295.29 Next, find PA for the $60 amounts of years 1 & 2: PA= 60(P/A,12%,2) = $101.41 Finally, add P0 & PA to get PT in year 0: Answer is (d)

  8. Shifted gradients begin at a time other than between periods 1& 2 Equation yields P for allcash flow(i.e. base amt is included) For negative gradient, change signs in front of both g’s P=A{1-[(1+g)/(1+i)]n/(i-g)} Geometric Shifted Gradients