An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BPSS and Service PanelsSanta Cruz, CA E Anderssen LBNL E. Anderssen LBNL

  2. Service Structures and Beampipe Support • Package design of Insertable Pixel System • Pixel system is integrated into train of services • Service Supports and Beampipe supports integrated together in Forward Region • Joined together to Form “PACKAGE” • Assembly of Package on surface is largely European responsibility • Key Cost Points • Beampipe Supports are a new Pixel responsibility—not fully approved by US Atlas, but fully accepted as absolutely required—NO WBS in Pixel estimate • Only limited Service Panel Prototyping occurred in FY03—shift mockup/system testing to ‘04 • Design changes increased cost of service structures and integration responsibilities are increased(ing) • UNCOSTED: Environmental cooling/sensors; 1/8-Barrel System test in ’04 (completely ignored this) • Assumptions • MT Staffing for BP and Service Supports is Shared with PST, will ramp up when Sectors finish • BP support budget will come from US Atlas—does not come from current pixel budget E. Anderssen LBNL

  3. Patch Panel 0 TRT Forward TRT Forward SCT Barrel Service Panels Service Panels Pixel Detector Side C Side A E. Anderssen LBNL

  4. “Package” Beam Pipe Support Structure Pixel Detector Not Shown Beam Pipe Beam Pipe Support Structure Service Panels E. Anderssen LBNL

  5. Service Panel with PP0 and PP1 Quarter panel • Cooling connections • Electrical Connections • Opto cards, fibers and fiber connections • Service Support along PST • Regenerative Heat Exchanger integrated in service quarter panel (SQP) • Supports PP1 during assembly E. Anderssen LBNL

  6. Inner Panel not installed, but need to know far enough in advance to ‘adjust’ lengths of B-Layer and Disk Type 0 Cables Service Quarter Panel Structure—Back Bone and Arms shown 2 Hit Service Quarter Panel Back Bone Tube Support Arms E. Anderssen LBNL

  7. Disk/B-Layer not assembled (Inner Panel) Support condition not changed—last armature supports end of Outer Panel Inner panel supported on tabs placed on BPSS Assembly PP0 2-Hit installed on BPSS E. Anderssen LBNL

  8. BPSS Supports Service Panels • Primary interface to BPSS is ‘Longeron’ • Adequate clearance for beampipe wire given by cooling tubes • BPSS Adjustor fits through PP1 QP, which is integrated with SQP • Interface blocks along longeron for SQP ribs Mate with Tube Support Arms • Mount tabs on Barrel Cruciform support Inner service panel E. Anderssen LBNL

  9. PP1 Part of SQP Assembly—tight interface with BPSS • Routing of tubes through PP1 set to minimize variety of tubes (same bend profile) • Sets of Tubes shared per octant • BPSS Adjustor, and support strut align with SQP during assembly • Gap between tubes (anti-clocked with adjustors) allows for access to Opto connector(s) • SQP Backbone not shown—sits in ‘rail cutout’ E. Anderssen LBNL

  10. PP0—Interface to Detector Services • PP0 is detector end of SQP Assembly • 2 hit system has ~6 less PP0 flexes per octant which is number of flexes on inner panel • Inner panel carries Disk and B-layer services (nominally) • Can be ‘de-scoped’ but requires decision deadline prior to fabrication of type 0 cables for disk and b-layer, or deciding now to fabricate these ‘long’ E. Anderssen LBNL

  11. Service Panel Numerology E. Anderssen LBNL

  12. Cooling Tubes • Heat Exchanger integrated into Service Panel • Requires close-coupling of inlet and outlet (supply/exhaust) tubing within the panel • Design and routing requires ~5 different bend profiles—these are combined in various ways to get all combinations of tubes • Cost of Bending tubes in SQP assy estimate—tubing and fittings in cooling tube estimate E. Anderssen LBNL

  13. Tube units are pre-assembled into Heat Exchangers Tube units are held in service panel support structure Blue unit is for Barrel Red unit is for Disk Units are loaded as required by service modularity Heat Exchanger Units (Type 1 Tubing run) E. Anderssen LBNL

  14. PPO Electrical/Structural Prototype E. Anderssen LBNL

  15. Beampipe Support Frame Wire Adjustors 2 Frames – 1 A Side, 1 C Side Single Frame Shown Here 4 Support Wires, 1 Support Plane Longerons Service panel Attachment points Reinforcing Longerons, Attach Points to PP1 Fixed Adjustors (no spring) Top and Side Wires at Z=-848,+848 Sprung Adjustors Side and bottom (tension limiters) Cruciform supports E. Anderssen LBNL

  16. Beam Pipe Collars Aerogel Insulation Wire Anchor Point Kapton Heater Split Conical Ring Allows Free Placement in Z No longer delivered—saves ~$25k E. Anderssen LBNL

  17. Adjustor/Tension Limiter Wire Guide Preload Adjustor Barrel Wire Wire Adjustor Nut Tension Limiter Plunger Wire Collet & Nut Limiter Spring Wire Adjustor Screw E. Anderssen LBNL

  18. Schedule • Delivery for Beampipe Support and Service panels follows roughly the delivery of the frame components • Delivery January ‘05 • Delivery of Beampipe supports may be requested earlier—need to define actual date in conjunction with Beampipe group • PRR for BPSS complete in FY ’03, production design complete • EDIA in ’04 is for fixture ‘adjustments’, mfg procedure definition, and production oversight. • Service Panels may be required earlier subject to testing requirements as yet undefined • Prototype Service panel(s) required for System Test in 2nd QTR FY03 Left in from last year—shifted to 2nd QTR ’04 • Service Panel PRR in Dec ‘03 E. Anderssen LBNL

  19. Costs for Service Panels/Supports • ETC03 to ETC04 Increase of ~$84k • Due to Schedule Delay and increased Complexity • Production moved from FY03 to FY04—materials purchased ‘03 • Prototyping (mockup) still required, shifted to ’04, may still happen in ’03 (24k+15k) • Labor is .8 FTE in ’04 • Did not estimate ‘auxilliary cooling/env sensors/opto-cooling E. Anderssen LBNL

  20. Costs for Beampipe Support • Added responsibility to Pixel Project—budget to come from Lissaeur’s integration WBS • Renamed ‘prototype’ to first production unit, built 1-d prototype for April FDR • EDIA is less than initial Estimate • No Foreseen cost impact to finalized design • Production delayed, engineering accelerated—no cost increase, but shift of all production cost to ‘04 • Contingency would require Second ‘production’ structure to be fabricated • Labor in ’04 is ~0.6FTE • Some of this cost ‘decrease’ is a shift of cost to ‘Insertion’ E. Anderssen LBNL

  21. Manpower Needs over Mechanics ‘04 • Manpower Requirements over all of Mechanics • PST ~0.6FTE • Service Panels ~0.8FTE • BPSS ~0.6FTE • Insertion ~0.1FTE • Sectors assumed ‘half an FTE’ in ’04 • Manpower is ~2.6FTE • Seems that this is possible with manpower available, but neglects inefficiency of task switching, PHASING • Also, assumes that all tasks completed in FY’04, some can trickle into 1st QTR FY’05 • Does not include Manpower for PP1, Frame Assy, Installation/Dry fit E. Anderssen LBNL