Metals Homework #4

Metals Homework #4. Frank Schornagle. RS Means. 05 12 23.77 0201 New Material Cost: 100%*$2250 + $2250 = $4500 05 12 23.77 5399 New Labor Cost: 100% * $273 + $273 = $546. 7 -1 Walk Through - Part A. Weight of beam: 40 lb/ft x 20 ft = 800 lb

kyna
Download Presentation

Metals Homework #4

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MetalsHomework #4 Frank Schornagle

  2. RS Means • 05 12 23.77 0201New Material Cost: 100%*$2250 + $2250 = $4500 • 05 12 23.77 5399New Labor Cost: 100% * $273 + $273 = $546

  3. 7-1 Walk Through - Part A • Weight of beam: 40 lb/ft x 20 ft = 800 lb • Conversion lb -> tons: 800lb / 2000 lb = 0.4 tons • Sales Tax: 6% x $1800 = $108 • O&P: 15% x $2226.8 = $334.02 • Material Cost: $4500 x 0.4 = $1800 • Equipment Cost: $251 x 0.4 = $100.40 • Labor Cost: $546 x 0.4 = 218.40

  4. 7-1 Full Solution

  5. 7-5, 7-6, 7-7

  6. Beam Measurements http://www.flangebar.com/?content=barinfo&pdata=d_flangesizes

  7. Materials List W12 x 35 C1 -> C2 : 300” –8.06” – (11.94”/2) = 285.97” Conversion: 285.97 in * 1ft/12in = 23.831 ft W12 x 35 C1 -> C2 : 300” –(6.535”/2) – (8.005”/2) = 292.73” Conversion: 292.73 in * 1ft/12in = 24.394 ft

  8. 7-6, 7-7 24.311' long W12 x 72 Beam 24.311 ft x 72lb/ft = 1750.392 lb

  9. RS Means • 05 12 23.77 0201New Material Cost: 50%*$2250 + $2250 = $3375 • 05 12 23.77 5396New Labor Cost: 25% * $273 + $273 = $341.25

  10. 7-5, 7-6, 7-7 Full Solution • Conversion lb -> tons: 32787.353lb / 2000 lb = 16.394 tons • Sales Tax: 6% x $55328.66 = $3319.72 • Labor Tax: 28% x $5594.34 = $1566.42 • O&P: 22% x $69923.95 = $15383.27 • Material Cost: $3375 x 16.394 tons = $55328.66 • Equipment Cost: $251 x 16.394 tons = $4114.81 • Labor Cost: $341.25 x 16.394 tons = $5594.34

  11. Weight of beams

  12. Thanx for your attention!