1 / 15

BTW 2012 Network Changes – 3 month rolling plan

BTW Planned Engineering Works 90 day overview April 2013 to July 2013 These dates are indicative dates only and not to be used for any forecasting purposes as they are all subject to change. Please ensure that you wait for formal notifications from IRAMS.

kyle-jensen
Download Presentation

BTW 2012 Network Changes – 3 month rolling plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BTW Planned Engineering Works 90 day overviewApril 2013 to July 2013These dates are indicative dates only and not to be used for any forecasting purposes as they are all subject to change. Please ensure that you wait for formal notifications from IRAMS. The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT). Please treat it accordingly and do not forward, republish or permit unauthorized access. BT reserves the right to make changes to the information in this Presentation at any time without further notice.

  2. BTW 2012 Network Changes – 3 month rolling plan • Whilst BTW has continually worked to enhance its network, we are currently undergoing an exceptional level of change driven by four main drivers:- • Stability – to improve the reliability of the network, BTW is targeting certain network elements with hardware and software improvements. • Capacity – the need for additional capacity is driven by an increase in the number of broadband users on the 21C network (through migration from 20C and growth) and also by the ever-increasing bandwidth demands of those users. • Resilience –to improve the resilience of the network , BTW is actively removing single points of failure from the network • New Functionality – to meet the needs of the market BTW needs to enhance its network to deliver the services its customers require. • This presentation outlines the key upgrade programmes, their drivers, customer impact and the number of upgrades per programme per week. • BTW is keen to deliver all the required improvements as quickly as possible whilst actively managing the risk to customers. For this reason a range of run-rates against each programme has been outlined. The actual run-rates achieved will be determined by this ongoing live analysis of risk. • Customer outage times for the PEWs start between 00:01 and 02:00 with the aim of completing customer impacting work by 04:00. This allows 2 hours for roll-back should the PEW be unsuccessful. • Business as usual capacity upgrades and upgrades to resilient structures have not been listed here.

  3. Customer Service / BTID Network Change - Executive Summary 21c BRAS Upgrades Programme No 37 • SE800 11.1.2.5p8 Software upgrade - status update • Endorsed plan to progress SEOS software upgrades from 6.1.3.10 p10 to 11.1.2.5 p8 on all 255 Ericsson SE800 BRASs in the 21C BB estate 5 nights per week, so change program could be completed by mid June 13 and provide a stability period before BT Sport Launch Aug 13. • SEOS 11.1.2.5 p8 moves BT from bespoke software to standard releases & in so doing fixes numerous bugs including a memory leak issue which has caused 7 BRASs to crash over the last 9 months. Additionally, it supports IPv6. • The following dashboard provides overall status of the upgrade program with projected completion 14 Jun 13:

  4. Customer Service / BTID Network Change - Executive Summary Deployment Priorities Feb – Apr 2013 39 40 41 42 45

  5. Ongoing 21C Upgrades SVLAN moves - these moves offload SVLAN’s (bundles of Broadband traffic) from one BRAS to another. This is carried out to alleviate capacity issues mplet 6 EEA – EES 7750 Lag Migration - This change provides increased scalability . 24 Software upgrade to increase platform stability. 31 Software upgrade to support BTR 40G Product requirements 35

  6. Ongoing 21C Upgrades Cont’d SVLAN moves - these moves offload SVLAN’s (bundles of Broadband traffic) from one BRAS to another. This is carried out to alleviate capacity issues mplet 37 HT-BEA- Capacity requirement for bigger switch. 13 slot device replacing 9 slot device Capacity – Software upgrade to replace software which is going out of vendor support. 22 38

  7. Ongoing 20C Upgrades Cont’d 36

  8. Completed 20C Upgrades 1 14 2

  9. Completed 21C Upgrades 15 16 3 17 28

  10. Completed 21C Upgrades 16 3 17 28 11

  11. Completed 21C Upgrades 22 26 27 30 23

  12. Broadband Services on 21CN 2 14 29 1 36 44 11 40 35 22 4 20 34 32 45 9 27 37 6 45 28 26 45 39 45 23 38 31 34 11

  13. Ethernet Service on 21CN

  14. Descriptions

  15. Management of risk

More Related