1 / 23

ILIAS WP3 activities report and ET organization

This report discusses the activities and organizational changes in the ILIAS.WP3 project from 2004 to 2008. The focus shifted from technical issues to ideas and plans for a 3rd generation observatory, with the main effort in the last year being the preparations for the ET Design study. The report outlines the tasks, deliverables, and timeline for the project.

kwaldon
Download Presentation

ILIAS WP3 activities report and ET organization

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ILIAS WP3 activities report and ET organization Harald Lück

  2. From 2004 to 2008 WG3 activities changed from technical issues and planning of 1.5 and 2nd generation detectors… … to ideas and plans for a 3rd generation observatory Main effort in the last year: ET Design study preparations

  3. YEAR 1 YEAR 2 YEAR3 YEAR 4 YEAR 5 Tasks and Deliverables Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 WP 3: A European strategy for future antennas Tasks: Working group and WEB site set-up Elaboration of short term improvement plan Presentation of short term plan to institutions Elaboration of ‘White book’ Presentation of ‘White book’ to institutions Writing of final report Deliverables: Annual Report WG3: A EuropeanStrategy for Future Antennas Transparency from 2005 (R. Flaminio) • Objectives and Delivearbles • - Determine objectives attainable trough short-term improvements • Draft a plan for an European network of GW detectors at the 2010 horizon • - Short term plan after 18 months • Long term plan: ‘White book’ defining the GW community objectives over 10 years period WG chaired by H. Lueck (MPI Hannover) and M.Punturo (INFN Perugia)

  4. ‚white book‘ -> ASPERA roadmap (Sept. 2007) • Permanent and postdocs • Construction and analysis • No distinction between engineers and physicists • Only the agents belonging to ASPERA or affiliated to it. • running experiments’ operation personnel included • PHDs excluded! This causes a non negligible error in estimating the financial impact. • Investment (R&D+ Construction + Commissioning +Operation costs) • No labour included, unless it is externalised labour (eg hire people to excavate a large cavity, prepare a large series of detectors etc) • Mostly money demanded from the agencies affiliated to ASPERA or EU • LISA not included • E.T. construction largely external costs

  5. Meetings 2004 2006 2005 2008 2007

  6. GraWiToN proposal • Initial Training Network under the Marie Curie actions • Training of young scientists on GW theory and experiments • Submitted in Sept08 • It involves: France, Italy, Germany, UK, Poland and Spain • 3M€ overall “typical” budget, 300k€ could be for EGO • Past the threshold but negligible chances of funding STAC Nov2008

  7. First call for proposals closing in spring 2007 Transparency from early 2007 • Fordesign studies,preparatory phase, and support actions • design studies:35 M€ • Support actions:28 M€(budget 2007-2008) • Indicative budget for preparatory phase: • 34 projects (budget 2007-2008) • Closure: 2nd May 2007 • First contracts to come into force before end 2007

  8. ET: Einstein Telescope • A European 3rd Generation Gravitational Wave Observatory • Conceptual design study started May 2008 • Money available from Sept. 2008 on (3M€ in total)

  9. Need for new infrastructure • Existing facilities subject to high, unshieldable environmental noise levels (seismic, gravity gradient noise) • Data taking with advanced detectors incompatible with installation of third generation techniques in same envelope (requires long comissioning times)

  10. 1st generation 2nd generation 3rd generation -19 10 -20 10 -21 10 -22 10 -23 10 -24 10 -25 10 1 10 100 1000 10000 From the 2nd to the 3rd generation

  11. 1st generation 2nd generation 3rd generation -19 10 -20 10 -21 10 -22 10 -23 10 -24 10 -25 10 1 10 100 1000 10000 3 main noise sources Seismic Shot Noise Thermal Noise

  12. ET: Working groups J. Colas M. Punturo H. Lück A. Freise J. v.d. Brand F. Ricci B. S. Sathyaprakash

  13. WG4: Astrophysics Issues Deduce relative speed of light and GW’s to ~ 1 sec / 3x109 yrs ~ 10-17 Determinemassofthe Graviton Measure Hubble Constant fromamplitudeofinspiralsthatare also seen in EM radiation

  14. WG1: Site & Infrastructure • Issues: • Scientific • Security • Costs • Legal • … Figure: M.Lorenzini

  15. WG2: Thermal Noise, Suspension, Cryogenics Coatingless Mirrors Thermo-Optic Noise Cryogenics Cryo-Materials

  16. WG3: Optical Configuration High power laser (1064nm, 1550nm) Squeezed Light Non-Gaussian beams

  17. WP5: Management Administrative Coordination (Jacques Colas) The Project coordinator chairs the Governing Council and the Executive board. He is responsible for the correct funds distribution within the contractors of the consortium. • Scientific Coordination (Michele Punturo, Harald Lück) • Verify and promote the achievement of the scientific targets of the project. • His duties are: • Trace the planning of the overall activities in accordance with the progresses and milestones reached in the different working packages • Facilitate information exchange between WPs • Chair the technical sessions during the project general meetings • Collect and merge single WPs contribution to the bi-annual and annual reports • Secretary VirginieBornes) • Support Project coordinator and Scientific coordinator. • Responsible for official web site containing • Documentation of WP progress • Documentation of meeting activity.

  18. Project Executive board Governing Council Science Team Institutions Scientific community Project Decision Information Flow

  19. Overall effort (proposal numbers) y 18 people for 3 years

  20. WP5: Management Executive board J. Colas Jo v.d. Brand F. Ricci Sathyaprakash A. Freise Michele Punturo Harald Lück R. Flaminio

  21. WP5: Management Science team • Participation open to all scientists of the GW community willing to contribute to this project through their expertise and networking ability. • Co-chaired (first 6 months) by GEO spokesperson and by Virgo-EGO Scientific Forum coordinator The Science Team is to keep continuous contact between the scientists working in the project with the larger GW scientific community and to allocate resources (man power and know-how) available outside the project for all the activities in the project that need external support

  22. You are here Timelines Virgo+ Advanced Virgo GEO HF Hanford Advanced LIGO E-LIGO Livingston Launch Transfer data data Site Prep. DS PCP Construction Comm. 3rd Gen. 1st Generation 2nd Generation

More Related