An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Week @ SLAC LCLS Project Management Update M. Reichanadter / SLAC

  2. LCLS Project Status – 1 LCLS currently at CD-2A (Authorized for PED and LLP Approved) CD-0 Approve Mission Need – Jun01 CD-1 Approve Preliminary Baseline Range – Oct02 CD-2A Approve Long-Lead Procurement Budget – Jul04 CD-2B Approve Performance Baseline – Continue to work with OECM for validation of baseline CD-3A Approve Start of Long-Lead Procurement – Dec04 CD-3B Approve Start of Construction – Scheduled for Oct05 Start of LCLS Construction – Mar06 First Light – May08 CD-4 Approve Start of Operations – Scheduled for Apr09 Recent Project Reviews External Independent Review – Jun04 Cost, Schedule and Organization reasonable, contingency adequate to cover risks. Recently OECM has requested additional documentation on LCLS hazards. DOE “Lehman” Review – Aug04 Concern expressed on budget/schedule, particularly wrt FY05 CR Conventional facilities contingency and overall budget Organizational staffing, particularly in procurements Requested revised cost and schedule estimate w/contingency & organizational structure DOE “Lee/Hoy” Mini-Review – Dec04 LCLS Submitted a revised C&S estimate TPC = $379M, TEC = $315M with a CD-4 of Apr09 Committee found C&S and organizational changes reasonable and can be successful DOE “Lehman” Review – May 10-12, 2005 Full Technical, Cost, Schedule and Management Review Includes a early conceptual review of the LCLS Instruments (MIE) and LCLS Operations

  3. LCLS Project Status – 2 The LCLS is in the Design/Procure/Construct phase. The LCLS P3 resource-loaded database is the single source of approved scope, cost and schedule. LCLS performance and progress is based on the resource-loaded schedule. Changes to the “plan” are approved through change control. Earned-Value measured against resource-loaded schedule. Emphasis on meeting schedules/milestones … cost will follow closely. LCLS people-power resource allocation Identify core group of scientists, engineers and managers. LCLS Division established @ SLAC, LCLS Groups @ ANL / LLNL Additional staff and infrastructure supports LCLS via matrix from the 3 collaborating labs. At CD-4 (Project Completion) we transition into LCLS start-up operations/research.

  4. LCLS Total Project Cost (Oct04) Based upon recommendations from the DOE “Lehman” Review, LCLS has submitted a Revised Cost Estimate $315M TEC $379M TPC ~35.2% contingency on work remaining ~37% comp on PED ~4% comp on TPC • LCLS is organized into fully integrated (design through commissioning) decoupled systems. • Decoupling allows each system to go as fast as technically possible. • Allows phased commissioning • Global systems (i.e., controls, alignment) are embedded in the technical systems.

  5. TEC Obligations vs Funding • Cum TEC = $315M, Cum Cont = $78M • To-date LCLS has been funding-limited • FY05 major step-up in funding • Construction start in FY06 • CD-4 extends LCLS into FY09 • Phase fund CM and CF Constr Staffing, LLP and CM/GC are key in FY05

  6. LCLS (TEC+OPC) Obligations Profile • Inj-Lin start-end early • CF is key to project success (safety, cost and schedule risks) • PM converges into a operations group. • FY09 provides a smooth transition into a ~$50M ops phase

  7. LCLS Summary Schedule – Dec04 • Highlights • 214 days of schedule float (10.5 mos.), • CP through Linac and B.O. for e-beam dump • FY05 Shutdown recently modified to 1 week • FY06 shutdown ~ 4 months Schedule contingency wrt CD-4 ~ 24%

  8. LCLS Project Organization • Increase senior level expertise • Chief Scientist • Construction Safety Professional • Dedicated Procurement Group • E-Beam and X-Ray Systems Managers add a management layer between the WBS System Managers and PO • Laser Group Manager to provide expertise to entire project

  9. LCLS Staffing Update • LCLS ES&H – Interviewing for Lead • Will need additional conventional and tunneling safety staff • LCLS Chief Scientist – Posted Soon • LCLS Procurement Manager @ SLAC – Interviewing for Lead • G. Desaulniers providing interim support • C. Jamison (Tech Lead) & B. Patten (Interim CF Lead) • Dedicated Procurement Support at ANL (J. Ingrafia) and LLNL (LLNL Proc. Mgr.) • LCLS Administrative Aide – P. Dungan • LCLS QA Manager – Posted Next Week • LCLS Design Supervisor – Interviewing • LCLS Documentation/Database Mgr – Posted Soon • LCLS Relational Database Mgr (Cntls) – Posted Soon • E-Beam System Manager – Advertising – Interviewing Soon • LCLS Laser Group Leader – Interviewing • Inj-Lin RF CAM – D. Schultz • Inj-Lin Engr – Advertising – Interviewing Soon • LCLS Undulator Proj Engr – B. Youngman • LCLS ANL Chief Engineer – Posted Soon • LCLS Conventional Facilities Project Engineer – J. Saldivar • LCLS Conventional Facilities Project Engineer – Interviewing Soon • More to follow in XTOD and XES. • Most of SLAC additions will be colocated in B280. • LLNL to ramp-up physicist support in damage optics and laser R&D.

  10. LCLS Peoplepower / System / Lab • LCLS resource usage is derived from resource-loaded schedule. • Staffing @ SLAC will require careful coordination. • Controls ~OK SLAC ESD + few hires • MEz ~OK • RF ~OK D. Schultz +SLAC KD • PO Staff-need senior-level and construction mgmt • Have secured additional offices in B280 to co-locate staff. *FY2009 annualized rate

  11. LCLS Procured Materials and Services / Lab • Lab Procurement efforts are decentralized • SLAC ~$15M/yr • ANL FY06-FY07 Undulators • LLNL modest procurements of mostly commercial items

  12. LCLS is under Configuration Management • Management Control • LCLS Project Management Plan • with Appendices • LCLS Advance Procurement Mgmt Plan • w/ Critical Procurements Appendix • LCLS Quality Implementation Plan • LCLS Risk Management Plan • with Risk Registry Appendix • Technical Control of Scope • Technical Specifications Documents • GRD, PRDs, ESDs, RDSs, ICDs • WBS Dictionary • Cost/Schedule/Resource Control • LCLS P3 Cost & Schedule Database • With Baseline Change Requests • LCLS L1-L2-L3 Milestones • All LCLS Project documentation can be found on the LCLS website (thanks to H.D. Nuhn)

  13. LCLS BCR Thresholds • Change Control Boards (CCBs) act at pre-determined thresholds • Positive / Negative cost & schedule changes and increment / decrement contingency.

  14. LCLS Cost Performance Report – Dec04

  15. PMCS Monthly Status & Reporting Cycle • System Managers will receive draft data ~ one week before Project Office CPR Meeting. Please be prepared to assess the status of your scope of work. • Cost, schedule, milestones, procurements, funding, resources, etc.

  16. Project Management Goals for LCLS Week • Cost and Schedule Performance Breakouts • Earned-Value/Milestones/Critical Path/Float/Contingency • Continue to be sensitive to schedule performance • Marching army costs due to delays ~$2-4M/mo in later years. • Early identification of issues/problems/risks • Risk Management Registry updated monthly • FY05 Planning • Staffing Ramp-up • Schedules, particularly FY05 and FY06 shutdowns • LCLS Procurements • Advance procurements to utilize available funding. • LCLS Finance • Discussion of MOU’s, fund transfers and actual cost tracking. • LCLS Construction Phase • Prepare for Title II • Davis-Bacon Tutorial