Reliability and Safety Analysis

Reliability and Safety Analysis. RCD Laser System Corey Lane, Ryan Scott, Danny Barjum. Microcontroller. λ p = (C 1 π T + C 2 π T ) π Q π L = 2.36 failures/10^6 hours MTTF = 1/ λ p = .4237e6 hours to failure. Bluetooth Modem.

Download Presentation

Reliability and Safety Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reliability and Safety Analysis RCD Laser System Corey Lane, Ryan Scott, Danny Barjum

  2. Microcontroller λp = (C1πT + C2πT) πQ πL = 2.36 failures/10^6 hours MTTF = 1/ λ p = .4237e6 hours to failure

  3. Bluetooth Modem λ p = (C1πT + C2πT) πQ πL = 2.45 failures/10^6 hours MTTF = 1/ λ p = .4082e6 hours to failure

  4. RF Reciever λ p = (C1πT + C2πT) πQ πL = 1.226 failures/10^6 hours MTTF = 1/ λ p = .8157e6 hours to failure

  5. Voltage Regulator λ p = λ pπTπSπCπQπE = .3744 failures/10^6 hours MTTF = 1/ λ p = 2.6709e6 hours to failure

  6. Failure Modes – μC Subsystem

  7. Failure Modes – Battery Subsystem

  8. Criticality Definitions • Low Criticality – Inconvenience to the user or failure of system. λp = 10^6 failures/hours • High Criticality – Potential to harm user. λp = 10^9 failures/hour Potential Improvements • Independent monitoring of the battery voltage as a fail safe for the charger. • Robust battery enclosure to reduce critically of battery overcharging. • Monitor voltage regulator and shutdown system if out of range. • Monitor charging power supply voltage and current. • If RF data connection fails, always draw instead of never draw.