MERIT pre-installation review: Preliminary conclusions. Fabich. Follow-up: Safety Review of mercury system. http://edms.cern.ch/document/754444/ Draft answer: http://cern.ch/merit/doc/HgSafetyReviewAnswer.htm Hot issues: Item 11: LEXAN cover on sump tank and as lid

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MERIT pre-installation review: Preliminary conclusions' - krysta


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Merit pre installation review preliminary conclusions

MERIT pre-installation review:Preliminary conclusions

Fabich


Follow up safety review of mercury system
Follow-up:Safety Review of mercury system

http://edms.cern.ch/document/754444/

Draft answer: http://cern.ch/merit/doc/HgSafetyReviewAnswer.htm

Hot issues:

  • Item 11: LEXAN cover on sump tank and as lid

  • Latest documentation on used materials and procedures is currently looked at.


Follow up cryogenics and solenoid review
Follow-up:Cryogenics and solenoid review

https://edms.cern.ch/file/710659/1/memorandum.pdf

  • Item 2: User’s notice. Yet now written procedures on installation and operation of the solenoid&cryogenics have been provided.

    • Cryogenics part by AT/ECR

  • Item 5: Results of non-destructive test (x-rays of welds)

  • Item 8: formal answer by collaboration is required.


Pre installation review
Pre-installation review

  • Installation in TT2A during PS2 run with beam possible.

  • Personnel radiation dose plan and access procedures need to be written.

  • The use of PU foam is currently investigated.

  • Safety valves of cryostat and vacuum jacket.

  • Maximum operating pressure of cryostat limited to 10 bar. Resolves a lot of issues.

  • A lot is dependent on the surface tests at build 180: leak test (warm and cold), condensation.