950 likes | 1.16k Views
Outline. IntroductionProject History White Pass AssessmentConversion ConsiderationsConstruction DetailsFeasibility Closing. Introduction. House Bill 241 proposes the extension of the Alaska Railroad from Fairbanks to Whitehorse, YukonAt Whitehorse, the proposed railroad would join the existin
E N D
1. White Pass Standard Gauge Conversion Mark Taylor
University of Alaska Fairbanks
Spring 2002
2. Outline Introduction
Project History
White Pass Assessment
Conversion Considerations
Construction Details
Feasibility
Closing
3. Introduction House Bill 241 proposes the extension of the Alaska Railroad from Fairbanks to Whitehorse, Yukon
At Whitehorse, the proposed railroad would join the existing White Pass and Yukon Route Railroad
White Pass track gauge is non-standard and requires conversion
The process and feasibility of such standardization are presented.
5. Introduction The conversion of an active railroad has never taken place in modern times
It is difficult to compare historical practices against today’s technology
6. Introduction Working knowledge of railroad operations, maintenance, and construction
Worked seasonally as track surveyor, bridge inspector, conductor/engineer, work train foreman, project engineer
Authored White Pass manual of maintenance and construction standards
7. Project History Railroad development into Alaska and northern Canada has a long history
First development was Alaska Railroad in 1923
Further exploration prior to WWII
State interest in 1970, 1980 produced route surveys and environmental studies (HB 47)
Recent increase in interest over last decade; notably HB 241 and Sen. Murkowski’s “Rails to Resources”
8. Project History The White Pass is included as an integral component of proposed trans-Canada railroad
Provide a tidewater access 110 miles from Whitehorse, YT
9. HB 241 Testimony White Pass could be converted ahead of the proposed corridor and serve as a supply route
A route simply from Fairbanks to Skagway via Whitehorse would prove sufficiently valuable in and of itself in addition to serving as a building block to further southward expansion
10. White Pass Built in 1898 as a transportation response to the Klondike gold rush
Key transporter of freight and passengers to and from the Yukon and Northern B.C.
Leased by the U.S. Army in WWII, valuable construction supply route for the Alaska Hwy
11. White Pass Major transporter of ore from the Yukon
Following mine closures, unable to compete against recently opened hwy traffic
Shutdown in the fall of 1982
Reopened the spring of 1988
Seasonal passenger operations moving over 300 000 / yr
12. White Pass White Pass was designed for narrow gauge but constructed to standard gauge specifications
Current maintenance and construction meets standard gauge operational requirements
13. White Pass Current Track Maintenance
Upgrading to heavy rail
Installation of 8 ft. ties
Higher capacity switches
Standard ballast
Wider clearances
Higher load ratings bridges and docks
Uniformity of heavy passenger trucks
14. Conversion White Pass’s current maintenance program is intended to ensure safe, reliable passenger operations however such efforts greatly enhance the efficiency of future conversion
The active passenger corridor receives the heaviest maintenance and upgrades
16. Conversion Traffic interruption
Revenue is generated through summer tourist trains
To limit or restrict passenger operations is unnecessary
Much of the railroad is unused and substantial work can be accomplished without hindrance to passenger operations
17. Construction Outline Construction is expected to last two years
Work performed through seven phases
Starting in early January of ‘Year One’
Ending mid-September of ‘Year Two’
18. Construction Outline Year One
Phase 1; Construction of rail-barge facility
Phase 2; Upgrading of bridges
Phase 3; Grade stabilization from Carcross to Whitehorse
Phase 4, 5; Gauge widening from Carcross to Bennett to Skagway
Phase 6; Equipment conversion
19. Construction Outline Year Two
Phase 6 (continued); Equipment Conversion
Phase 7; Gauge widening from Carcross to Whitehorse
22. Phase One; Rail Barge Facility Begins January of Year One
Ends May of Year One
Allow for construction material to be loaded by the manufacturer and shipped directly via barge
Be the leading end of Skagway’s rail-barge connection
23. Phase One; Rail Barge Facility Construction must be completed prior to the cruise ship season
Wintertime port construction is common in Skagway
All docks in Skagway have been designed or adapted to accommodate passenger traffic
24. Phase One; Rail Barge Facility Two are immediately suitable for a rail barge ramp construction
All are deepwater docks
Skagway has 25 ft tides and the appropriate ramp design would allow for four loading/offloading windows per day at the 16 ft stage
26. Phase One; Rail Barge Facility “Railroad Dock”
designed and built to standard gauge rail capacity
A third rail runs throughout its length
No additional rail crossings would be required
Additional rail traffic accessing the pier would pose no significant threat increase to pedestrian traffic
28. Phase One; Rail Barge Facility “Ore Dock”
The former ideal location for such a facility
Alaska Marine Line operates a ramp here
Land leases have severely restricted any potential foot print for freight operations
Track geometry in the confined quarters would be a design problem
Rail access would require additional grade crossings through Skagway tourism district
30. Phase One; Rail Barge Facility The City of Skagway exists in a confined valley
Waterfront land is leased by White Pass from the City
Much land has been subdivided and remaining portions are not adequate for staging of railroad freight
31. Phase One; Rail Barge Facility The best means of marshalling barge borne freight is to remove it directly from the barge and stage it north of town near railroad milepost 3
34. Phase Two; Bridges, Tunnels, and Clearances 23 Bridges over entire route
14 bridges within Alaska
3 bridges within British Columbia
6 bridges within Yukon
35. Phase Two; Bridges, Tunnels, and Clearances To handle the increase in axle loads from standard gauge equipment, many bridges require upgrading
The simplest method is the installation of intermediate pony trusses at bridge mid-spans
36. Phase Two; Bridges, Tunnels, and Clearances Alaska Subdivision (MP 0.0 – 20.4)
5 bridges have been recently rebuilt to steel, standard gauge capacity
4 require intermediate bents
Both short and shallow
2 require extensive upgrading
3 are adequate
37. Phase Two; Bridges, Tunnels, and Clearances British Columbia Subdivision (MP 20.4 – 53.2)
2 have recently been rebuilt to steel, standard gauge capacity
One is due for rebuild by 2003
38. Phase Two; Bridges, Tunnels, and Clearances Yukon Subdivision (MP 53.2 – 110.0)
3 recently reconstructed to standard gauge capacity
3 require extensive reconstruction
All short and shallow
39. Phase Two; Bridges, Tunnels, and Clearances Only two tunnels exist along the railroad
Both in the Alaska Subdivision
40. Phase Two; Bridges, Tunnels, and Clearances MP 16 Tunnel
Constructed in the winter of 1899
300 ft long
Requires no upgrading
Current dimensions allow for standard rail traffic
43. Phase Two; Bridges, Tunnels, and Clearances MP 18 Tunnel
Built in 1969 to replace a bridge
700 ft long
Built to American Railway Engineer Assoc Standards (AREA)
However, the portals limit the interior dimensions of the tunnel
45. Phase Two; Bridges, Tunnels, and Clearances Clearances
No additional right-of-way widening is necessary
An intensive maintenance program has actively removed close clearances, widened cuts, deepened shoulders, and removed rocky outcrops
46. Phase Two; Bridges, Tunnels, and Clearances Clearances
Historically, White Pass has transported excess dimension freight
White Pass transported 80 ft lengths of 60 in diameter pipe in proof of concept test for Foothills Pipeline
White Pass operates with some standard gauge equipment
50. Phase Three;Right-of-Way Stabilization Carcross (MP 65.7) to Whitehorse (MP 110.0)
Little maintenance has occurred over this northernmost section since 1982
A dedicated crew will work six months beginning May 1 of Year One
The crew will be comprised of one work train and supporting heavy equipment
51. Phase Three;Right-of-Way Stabilization Primary focus of crew:
Restoring shoulder width
Replacing wooden culverts with aluminum
Widening cuts
52. Phase Three;Right-of-Way Stabilization It is expected that over 200 000 yds of material will be removed or distributed along the right-of-way
All of the material required is available from natural sources within designated railroad land rights
53. Phase Three;Right-of-Way Stabilization Existing track:
Much of the subgrade is a mixture of sand and silt
Cleaned ballast was placed during 1960 overhaul throughout much of this section
Rail, ties, and accompanying track hardware is inadequate for standard gauge traffic and will be addressed during Year Two
54. Phase Three;Right-of-Way Stabilization No rail operations are underway over this track portion and construction crews can operate unimpeded
Access to the track is available via the Klondike Highway
57. Phase Four;Gauge Widening Carcross to Bennett Carcross (MP 67.7) to Bennett (MP 40)
This section of track follows the shore of Bennett Lake passing light grades through fine soil terrain near Carcross becoming rock near Bennett
No operations are underway over this section
58. Phase Four;Gauge Widening Carcross to Bennett Heavy reconstruction has taken place within the past six years
Shore stabilization
100% long tie renewal
Extensive surfacing
Ballasting
Much of the rail is new 100 lb/yd and adequate for standard gauge traffic
59. Phase Four;Gauge Widening Carcross to Bennett Track and right-of-way is in condition suitable for straightforward gauge widening
No operations take place over this section
Two crews, totaling thirty people, would be required
Work will closely resemble the process of a rail relay
60. Phase Four;Gauge Widening Carcross to Bennett Two people will precede crew one removing spikes and anchors on the west rail
The east rail will remain in place serving as a gauge rail
The crew will proceed with a hydraulic gauging machine moving the unspiked rail 10.25 in. and gauge spike
61. Phase Four;Gauge Widening Carcross to Bennett The next crew, in the same fashion, will move the east rail 10.25. in and gauge spike
The bulk of the crew will complete all spiking, anchoring, leveling, and lining
Standard gauge production rail laying equipment will be used
The crew will leave behind standard gauge track
62. Phase Four;Gauge Widening Carcross to Bennett The primary crews will ignore track discontinuities to maintain momentum
Ie: grade crossings, turnouts, yards
A follow up crew will address these potentially time consuming tasks
64. Phase Five;Gauge Widening Bennett to Skagway Bennett (MP 40.4) to Skagway (0.0)
At Bennett, crews will be entering the active passenger corridor
Timing is important
The construction crew should arrive Bennett near the time Bennett Service is suspended
Expected around mid-August
66. Phase Five;Gauge Widening Bennett to Skagway From Bennett, construction can proceed toward Fraser
Crews should arrive Fraser near the time Fraser service is suspended
Expected around mid-September
68. Phase Five;Gauge Widening Bennett to Skagway From Fraser, construction can proceed toward the summit
Crews should arrive at the summit near the time total passenger services are suspended near late September
After this date, crews have total access to the passenger corridor
70. Phase Five;Gauge Widening Bennett to Skagway In Skagway Yard, a crew of eight to ten will be at work converting switches, road crossings, and some short lengths of three-rail track
At the end of the summer of Year One, the essential portions of the Skagway Yard will be ready to accommodate standard gauge stock
71. Phase Five;Gauge Widening Bennett to Skagway By the Fall of Year One, the railroad will be standard gauge from Skagway to Carcross
73. Phase Six; Equipment Conversion The Skagway Facility can dedicate itself to equipment conversion after the suspension of passenger service
Nearly all of White Pass’ equipment in service is historical passenger equipment
The process would proceed through the winter ending before start of season Year Two
74. Phase Six; Equipment Conversion Only passenger equipment will be focused on for conversion
Freight and work equipment can be easily replaced with more efficient leased or purchased standard gauge equipment brought in by barge
75. Phase Six; Equipment Conversion Nearly all of the passenger fleet has been transitioned to a uniform, steel truck design which can be easily converted to standard gauge
A stockpile of standard gauge components can be on hand early via barge
76. Phase Six; Equipment Conversion The conversion of equipment would be a straightforward:
The car enters the shop
Is jacked up
Narrow gauge trucks and brake rigging removed
Standard gauge trucks and rigging installed
77. Phase Six; Equipment Conversion White Pass locomotives are wholly obsolete with their technology dating back to the 1950’s
One modern, standard gauge locomotive would easily replace four existing White Pass locomotives
New locomotives could be purchased and/or leased for a significantly lower cost
79. Phase Seven; Gauge Widening Carcross to Whitehorse Carcross (MP 67.5) to Whitehorse (MP 110.0)
The existing track over this section would be converted during the spring and summer of Year Two
80. Phase Seven; Gauge Widening Carcross to Whitehorse All new track supplies could be brought to Skagway via barge and taken directly to Carcross on standard gauge cars
This will provide the most striking metamorphosis
This will also be the most management intensive part of construction
81. Phase Seven; Gauge Widening Carcross to Whitehorse All new track supplies would be brought to Skagway via barge and taken directly to Carcross on standard gauge cars
First, a crew working north will widen gauge as previously outlined
The track will be temporarily spiked on the existing narrow gauge ties
82. Phase Seven; Gauge Widening Carcross to Whitehorse Second, a standard gauge work train will proceed north distributing new, 115 lb/yd rail and ties at night
During the day, a crew will lay the new rail and gauge spike, still using narrow ties
83. Phase Seven; Gauge Widening Carcross to Whitehorse Third, a crew using standard gauge production equipment will insert new ties and complete the conversion
This is concluded with a ballast train and surfacing crew
Work will progress at 3 miles per week
Work is to be completed by mid-September
84. Cost This cost assessment is a broad scope analysis of projected costs
85. Cost: Phase One
86. Cost: Phase Two
87. Cost: Phase Three
88. Cost: Phase Four
89. Cost: Phase Five
90. Cost: Phase Six
91. Cost: Phase Seven
92. Summary
95. Questions