An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jun 14th 2019 BNB Canopy Update 09:00 Meeting

  2. Revised Schedule • Steel Canopy installation MI12 Service Building Completed section Week of June 24th Asphalt installation: Week of June 17th Final Grading: Week of June 17th HDPE liner installation: Week of June 24th Project Completion: Week of July 1st Week of July 8th Presenter | Presentation Title or Meeting Title

  3. BNB Canopy

  4. C. Gattuso| AD Shutdown Manager

  5. Cons Gattuso 09:00 Meeting 2019 Summer Shutdown Planning 6/14/19

  6. Shutdown Planning Guidance • Intensity Reduce needed for the Shutdown work: None (at this time) • Start Date • July 8th Monday (in the tunnel) • HEP Beam off • July 6th at 0800 hrs. (Saturday) • Booster Studies may impact when beam goes off….. • July 7th Configuration control/rad surveys/convert to shutdown key sets • Following Enclosures Areas will be Re-cored for the duration of the shutdown: (at this time) • Booster, Main Injector,8 GeV Line, NuMI-65, target/pre-target, Muon Campus, F-sector, Transfer Hall, Enc B • Duration • ~12 weeks • Turning on Week of September 23rd • 1-2 Week of Start up/ Commissioning • During the Shutdown our 09:00 meetings will be held Tuesdays and Fridays. 17 Work days until the shutdown Presenter | Presentation Title or Meeting Title

  7. Planning Stages • We will meet Once every two weeks • Between January - June • Planning Milestones • Kick off meeting -Completed • Set Major Jobs (end of Feb.)- Completed • Get T&M/Fixed price packets out by April ~95% Complete • Issues have already come up • Set Maintience tasks (end of May) ~95% complete • Determine Man Power Needs (mid may) ~95% complete • Set Service Building Outages (early June) ~65% complete • Completed by the Engineering building site prep • This also impacts our Controls work in the Computer Room • Resource leveled schedule – ~95% Complete C. Gattuso

  8. Mech Crew • Initial Meeting Crews to outline work flow (process has started) • Crews will be reviewing/optimizing • Job Dose workplan • Job HA • And other permits that may be required • Electrical • Burn • Ect. • Review and optimizing • Preparing equipment needed • Staging equipment if needed and possible C. Gattuso| AD Shutdown Manager

  9. Finalizing our schedule • Hand full of jobs that still need to be scheduled • Main Injector/Recycler • Be7 issues • Understanding what will need to be able to work in some of these areas. • Water leak on MI202 Quad Completed • CUB work • Muon Campus Heat exchanger change out (2) • Effluent tank replacement • Updating the schedule with any work that may have been completed – In Progress • Power outage schedule impacts • Should be small impact C. Gattuso| AD Shutdown Manager