Far Experimental Hutches. David Saenz Project Manager. Far Experimental Hall Hutches. Scope Design Status/Deliverables Schedule Estimated Construction Cost Present Status Summary. Scope. Approximately 7,800sf of new facilities for three Hutches, Control Rooms and Common Rooms

Download Presentation

Far Experimental Hutches

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Far experimental hutches

Far Experimental Hutches

David Saenz

Project Manager


Far experimental hall hutches

Far Experimental Hall Hutches

  • Scope

  • Design Status/Deliverables

  • Schedule

  • Estimated Construction Cost

  • Present Status

  • Summary


Scope

Scope

  • Approximately 7,800sf of new facilities for three Hutches, Control Rooms and Common Rooms

  • Current approved specifications are well defined and present no major challenges


Scope cont d

Scope – Cont’d

1 ton capacity cranes

Radiation protection

Standard door sizes

Existing common floor

Standard wall/ceiling finishes

No acoustic requirements

  • Utilities (MEP)

    • Process chilled water

    • Chilled water

    • Compressed air @ 100psi

    • HVAC 72°± 1 °F

    • RH 45% ± 10%

    • 24” cable trays

    • Standard lighting

    • Surface mounted conduits

    • Standard 110V and 208V outlets


Engineering specification documents

Engineering Specification Documents

  • LCLS ESD’s approved by key stake-holders.

    • ESD 1.9-112

      • Hutch 4

    • ESD 1.9-113

      • Hutch 5

    • ESD 1.9-114

      • CXI Room

    • ESD 1.9-115

      • XCS Room

    • ESD 1.9-116

      • Common Room

    • ESD 1.9-117


Access tunnel looking south

Access Tunnel (looking south)


Feh looking west

FEH (looking west)

Existing utility systems in place


Feh floor plan section by dga

FEH Floor Plan/Section by DGA

Floor Plan

Building Section


Hvac floor plan by dga

HVAC Floor Plan by DGA


Design status

Design Status

  • Design was awarded Oct 10, 08

  • Title I completed on Nov 6, 08

    • Internal design review currently in process and will be completed on 11/13/2008

  • Title II 60% scheduled for Jan 15, 09

  • Title II 90% scheduled for Feb 25, 09

  • Title II 100% scheduled for Mar 4, 09


Design deliverables

Design Deliverables

√ Existing Conditions Report

√ 30% Design Review

√ Structural Design Review

√ Preliminary Cost Estimate

60% Design Review

Detailed Cost Estimate

90% Design Review

Engineering Coordination Presentation

Updated Cost Estimate

100% Design Review

Final Cost Estimate

Issue of Issue For Construction (IFC) documents

Value Engineering

  • All deliverables are expected to be provided on time!

  • Sufficient quantity of deliverables are established to manage progress and complete development


Construction schedule

Construction Schedule

  • 9 months including pre-construction activities to commence Mar 09 and complete Dec 09

  • Need to revise schedule to reflect construction award Mar 09 for major packages


Estimated construction cost

Estimated Construction Cost

  • Initial estimate provided by AE valued at $3.6M

    • Includes direct and in-direct cost and escalation

  • Strategy for construction delivery method is consistent with expectations

    • Design → Bid → Build

  • Current WBS (1.9.3.14.2) budget is $4.1M (including contingency)


Summary

Summary

  • Design parameters are clearly defined

  • Sufficient quantity of deliverables are in process

  • Title I complete

  • Title II in process

  • AE firm has provided alternatives solutions for higher priced items i.e. structural steel


End of presentation

end of presentation