MMS Update for TPTF April 21, 2008 Murray Nixon Sai Moorty

Loading in 2 Seconds...

play fullscreen
1 / 6

MMS Update for TPTF April 21, 2008 Murray Nixon Sai Moorty - PowerPoint PPT Presentation


  • 110 Views
  • Uploaded on

MMS Update for TPTF April 21, 2008 Murray Nixon Sai Moorty. Agenda. MMS release schedule Proposed Deferrals Included in MMS4 MMS4 pre-FAT status MMS4 FAT plans. MMS Release Schedule. Proposed Deferrals Included in MMS4. MMS4 pre-FAT Status.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MMS Update for TPTF April 21, 2008 Murray Nixon Sai Moorty' - kioshi


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
agenda
Agenda
  • MMS release schedule
  • Proposed Deferrals Included in MMS4
  • MMS4 pre-FAT status
  • MMS4 FAT plans

http://nodal.ercot.com 2

mms release schedule
MMS Release Schedule

http://nodal.ercot.com 3

proposed deferrals included in mms4
Proposed Deferrals Included in MMS4

http://nodal.ercot.com 4

mms4 pre fat status
MMS4 pre-FAT Status
  • MMS4 pre-FAT started on 2Apr08 with a targeted completion of 16Apr08
  • 275 structured tests completed with a 94% pass rate
  • New functionality was tested using an updated PSS/E data set created by ERCOT resources from MMS, EDS & INT
  • CIM importer tested using CIM schema v1.8 with data from 29Feb08 that was supplemented with data created by ERCOT resources from MMS, EDS & INT

NOTE: to the extent possible, the same data is being used for EDS4 running MMS3 software

  • Severity 1 defects: 0
  • Severity 2 defects: 3 (one deferred to ERCOT for additional information; one corrected and ready for retest; one S&B retested SPR partially failed and is targeted to be fixed and retested during FAT)
  • Total defects: ~120

http://nodal.ercot.com 5

mms4 fat plans
MMS4 FAT Plans
  • MMS4 FAT is scheduled to start 22Apr08
  • Initial loading and smoke testing in DEV and FAT is estimated to take approximately 1 week
  • Regression testing on the new functionality will take place using the MMS4 pre-FAT PSS/E data set; this is estimated to take approximately 2 weeks
  • With an objective of supporting migration to a common Nodal CIM model and data set, work continues on validating the schema with NMMS & ABB, and with NMMS, INT & EDS on a common set of test data
    • ~1000 MMS4 FAT regression tests will be conducted using the common Nodal CIM schema and CIM data file; detailed re-planning for this activity is underway
  • MMS and Release Management will work with all downstream systems (e.g., INT, iDEV, EDS) to make this release available when feasible for their respective environments