Doug Thiessen, P.E. Managing Director of Engineering

Loading in 2 Seconds...

play fullscreen
1 / 25

Doug Thiessen, P.E. Managing Director of Engineering - PowerPoint PPT Presentation


  • 100 Views
  • Uploaded on

Update on the Port of Long Beach. Doug Thiessen, P.E. Managing Director of Engineering . ACEC LA January 15, 2014. Port of Long Beach Premier gateway for U.S-Asia trade, major Southern California economic engine. Who We Are. 3,500 acres of land 4,600 acres of water

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Doug Thiessen, P.E. Managing Director of Engineering ' - kiora


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Update on the

Port of Long Beach

Doug Thiessen, P.E.

Managing Director of Engineering

ACEC LA

January 15, 2014

slide2

Port of Long Beach

Premier gateway for U.S-Asia trade, major Southern California economic engine

who we are
Who We Are
  • 3,500 acres of land
  • 4,600 acres of water
  • 6 container terminals
  • 66 Ship-to-Shore cranes
  • 76-foot-deep main channel
  • 2nd busiest U.S. container cargo seaport
  • Part of the world’s 9th busiest port complex
slide4

Diverse Cargo

3,500-acre Port moves cars, crude oil, petroleum coke, lumber and container cargoes.

big ship ready
Big Ship Ready

2013

18,000 TEU

2006

15,500 TEU

8,100 TEU

1997

1996

7,100 TEU

slide6

Largest to Call North America

14,000-TEU MSC Corte Real came in October 2013 – too wide to pass through the expanded Panama Canal.

slide7

Investing in the Future

Port has begun a $4 billion upgrade of facilities to stay competitive

slide8

Current Major Programs

  • Pier G Redevelopment
  • Middle Harbor Redevelopment
  • Gerald Desmond Bridge Replacement
  • On-and Near-Dock Rail
  • Shore-to-Ship Power
  • Fire Protection Program
slide9

Middle Harbor

$1.2 billion facility will be one of the most technologically advanced terminals in the world.

slide10

Middle Harbor

Phase 1 Currently Underway

slide11

Phase 2

Phase 1

Phase 2

Phase 1

Middle Harbor Redevelopment

305-acre facility under construction in two phases.

slide12

Middle Harbor Redevelopment

  • Phase 1- $779.3 Million
    • 10 construction projects
    • Third-party utility improvements/relocations
  • Phase 2- $449.7 Million
    • 9 construction projects
    • Third-party utility improvements/relocations
slide13

Gerald Desmond Bridge Replacement

$1.3 billion cable-stay bridge; $650 million

design-build contract awarded to Shimmick,

FCC & Impregilo on July 2012.

slide14

Pre-Construction

Preliminary engineering complete, two-thirds through Right-of-Way work.

slide15

Future Opportunity

Demolition of Existing Bridge

on near dock rail improvements
On & Near Dock Rail Improvements

Pier B

On-Dock Rail Support Facility*

Ocean Blvd. Track Realignment

Pier G South

Rail Yard*

Middle Harbor On-Dock Rail

*Future project

slide17

Shore Power Projects

  • Port is reducing air quality impacts through the Clean Air Action Plan. The state has enacted a regulation requiring shore power in 2014.
slide18

Major Effort

  • Simultaneous construction at all container terminals and 12 berths
slide20

Fire-Protection Program

  • New Fireboats for Station 15 & 20
  • Fireboat Station 15 Replacement Project
  • Fireboat Station 20 Replacement Project
  • (Site Selection Underway)
slide22

Upcoming Consultant Opportunities

  • Construction Management Division:
    • CM Services – Pier G Redevelopment (under evaluation)
    • On-Call, Inspection & Material Testing (under evaluation)
    • As-Needed Hydrographic Services
    • (under evaluation)
    • CM Services – New Fire Stations, 2014
    • On-Call Construction Mgmt. Services, 2014
  • Other Engineering Divisions:
    • On-Call Cost Estimating Services, 2014
slide23

Upcoming Contractor Opportunities

(Next 12 months)

  • Pier C, Upgrade of Water Facilities, 2013
  • Berths F209 Chemoil Facility Improvements, 2013
  • NRG Facilities Relocation/Demolition, 2013
  • Harbor Scenic Water Valve Replacement, 2013
  • Pier F, Cut-off Wall & Pavement Rehab., 2013
  • Edison Avenue Street Improvement, 2014
  • Pier J, Bike & Pedestrian Path, 2014
slide24

The Future is Big

We face big challenges, but we see big opportunities that will bring a promising future to the Port of Long Beach

staying connected
Staying connected

www.polb.com

www.facebook.com/PortofLB

http://twitter.com/portoflongbeach

http://www.youtube.com/portoflongbeach

ad