Topic-14. Production Activity Control. Production Activity Control (PAC). Objectives of PAC: 1. Meeting job due-dates 2. Controlling work-in-process inventory level 3. Reducing shop congestion and leadtimes 4. Controlling the queues at each work center

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Topic-14' - keiji


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Topic 14 l.jpg

Topic-14

Production Activity Control


Production activity control pac l.jpg
Production Activity Control (PAC)

  • Objectives of PAC:

    1. Meeting job due-dates

    2. Controlling work-in-process inventory level

    3. Reducing shop congestion and leadtimes

    4. Controlling the queues at each work center

    5. Preventing bottleneck machines in advance.

    6. Increasing shop utilization


Production activity control ii l.jpg
Production Activity Control (II)

  • Five major data files in PAC:

  • Item master file

  • Job routing file

  • Work center master file

  • Shop order master file

  • Shop order status file


Data requirements l.jpg
Data Requirements

The Files generally required For a PAC System Are:

Planning Files Control Files



Function of production activity control i l.jpg
Function of Production Activity Control (I)

The major function of an efficient productions activity control system consists of the following:

  • Releasing orders to the production on schedule having verified material, tool. Equipment and personnel available.

  • Preparing shop packet (shop order, drawing, pick list, route sheet, tool request form, labor ticket, move ticket, etc.)

  • Establishing scheduled start and completion dates of steps in the production process as well as the schedules completion date of the order, as milestones to measure progress


Function of production activity control ii l.jpg
Function of Production Activity Control (II)

  • Comparing future workload with planned capacity to allow for a determination of appropriate action for balancing work

  • Ranking orders in desired priority sequence by work center and issuing a dispatch list

  • Tracking the current status of each order in process

  • Providing timely and accurate feedback on activities not proceeding according to plan

  • Revising order priorities on the basis of performance and changing conditions

  • Monitoring and controlling lead time, work center queue and work in process

  • Providing exception and performance evaluation reports (scrap, rework, late order, and work center efficiency analysis reports)


Slide8 l.jpg

The large number of logs in the river at the same time creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

To increase the flow of the logs the saw mill down river, the number of logs placed in the river at one time must oftentimes be reduced.


Shop work load control load l.jpg
Shop Work Load Control Load creates a “log jam” which restricts the overall flow of the logs to their saw mill destination


Production control overview l.jpg
Production Control Overview creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

Four Major functions of production control:


Process focused manufacturing l.jpg
Process-Focused Manufacturing creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • Process-focused factories are often called job shops

  • A job shop’s work centers are organized around similar types of equipment or operations

  • Workers and machines are flexible and can be assigned to and reassigned to many different orders

  • Job shops are complex to schedule


Process focused manufacturing12 l.jpg
Process-Focused Manufacturing creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • The production department controls and monitors order progress through the shop by:

  • Assigns priority to orders

  • Issues dispatching lists

  • Tracks WIP and keeps systems updated

  • Controls input-output between work centers

  • Measures efficiency utilization and productivity

    of shop.


Job dispatching sequencing rules l.jpg
Job Dispatching (Sequencing) Rules creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • Dispatching rule: determine which job will be processed next among the jobs waiting in queue.

  • Common dispatching rules:

  • FCFS (first-come, first served)

  • SPT (shortest processing time—job first)

  • LPT ( longest processing time—job first)

  • EDD (earliest due-date—job first)

  • MRO ( most remaining operations—job first)

  • CR ( critical ratio: smallest CR job first)


Job dispatching rules ii l.jpg
Job Dispatching Rules (II) creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • CR=(due date – current time) / total remaining operation time

    If CR=1, this order is in critical

    If CR<1, this order is late already

    If CR>1, this order has some slack time

  • Most dispatching rules are heuristic in nature

  • Different rules perform differently under different measures.


Example of evaluation criteria for production scheduling l.jpg
Example of Evaluation Criteria for Production Scheduling creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • Minimize average lateness for completed jobs

  • Minimize average flow time for completed jobs

  • Minimize maximum lateness for completed jobs

  • Minimize maximum flow time for completed jobs

  • Maximize machine utilization in facility

  • Minimize average value of work-in-process

  • Maximize worker utilization

  • Balance workload assigned to each worker/machine

  • Maximize volume of work completed in each time period


Job dispatching example l.jpg
Job Dispatching Example creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • There are three jobs waiting for machine 1. their processing time requirement and due-dates are given below:

Dispatching jobs by SPT, LPT and EDD. Comparing

the average job flow time and the the number of

jobs late


Job dispatching example17 l.jpg
Job Dispatching Example creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

There are three jobs waiting for Machine 1.

Their processing time requirement and due-dates are given below:

Dispatching jobs by SPT, LPT, and EDD. Comparing the Average

Job Flow Time and the Number of Jobs Late


Job dispatching example18 l.jpg
Job Dispatching Example creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

a) SPT

0

2

5

14

Average Job Flow Time = (2+5+14)/3=21/3=7

No. of Jobs Late = 1 (3)


Slide19 l.jpg

Job Dispatching Example creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

b) LPT

0

9

12

14

Average Job Flow Time = (9+12+14)/3=35/3=11.67

No. of Jobs Late = 1 (7)


Slide20 l.jpg

Job Dispatching Example creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

c) EDD

2

0

11

14

Average Job Flow Time = (2+11+14)/3=27/3=9

No. of Jobs Late = 0


Exercise job dispatching problem l.jpg
Exercise: Job Dispatching Problem creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

  • There are eight jobs waiting in the queue for processing on machine 1. The jobs are arranged in order of their arrival with A, B, C,… G,H.

  • Use FCTS (First come first serve) dispatching rule. Compute Total Job Completion Time, Average Job Flow, and Average Job Lateness.

  • Use SPT (Shortest Processing Time) dispatching rule. Compute Total Job Completion Time, Average Job Flow Time, and Average Job Lateness.


Exercise job dispatching problem22 l.jpg
Exercise: Job Dispatching Problem creates a “log jam” which restricts the overall flow of the logs to their saw mill destination

There are eight jobs waiting in the queue for processing on machine1. The jobs are arranged in the order of their arrival with A, B, C, … G, H.

  • Use FCFS (first-come-first-serve) dispatching rule. Compute total job completion time, average job flow time, and average job lateness.

  • Use SPT (shortest processing time) dispatching rule. Compute total job completion time, average job flow time, and average job lateness


Slide23 l.jpg

By creates a “log jam” which restricts the overall flow of the logs to their saw mill destinationFCFS Rule

A

27

27

32

-5

14

B

33

41

8

C

7

31

48

17

31

D

79

40

39

E

9

88

28

60

27

115

52

63

F

3

G

9

109

118

H

1

95

139

44

400

655

( )

Total

( )

Average Job Flow Time= (Total Flow-Time)/Number of Jobs

= 655/8=82

Average Lateness= (Total Lateness)/Number of Jobs

= 400/8=50


By spt rule l.jpg
By creates a “log jam” which restricts the overall flow of the logs to their saw mill destinationSPT Rule

G

3

3

9

-6

17

C

7

10

-7

E

-9

9

19

28

33

33

B

14

0

54

44

H

21

10

81

32

A

27

49

108

52

F

27

56

139

40

D

31

99

192

Total

( )

447

( )

Average Job Flow Time= (Total Flow-Time)/Number of Jobs

= 447/8=56

< 82

Average Lateness= (Total Lateness)/Number of Jobs

= 192/8=24

< 50




Job sequencing problems l.jpg
Job-Sequencing Problems Problems on

  • We want to determine the sequence in which we will process a group of waiting orders at a work center.

  • Many different sequencing rules can be followed in setting the priorities among orders.

  • There are numerous criteria for evaluating the effectiveness of the sequencing rules.


Job sequencing problems ii l.jpg
Job-Sequencing Problems (II) Problems on

General performance:

1.First come first served: poor performance and fair play.

2.Shortest processing time: good performance and may continuously push the long processing time orders back.

3.Critical ratio: good performance and focuses too much on jobs that cannot be completed on time.


Product focused production line scheduling l.jpg
Product-Focused (Production Line) Scheduling Problems on

  • Scheduling decisions:

  • If products are produced in batches on the same production lines:

    --how large should production lot size be for each product?

    --when should machine changeovers be scheduled?

  • If products are produced to a delivery schedule:

    --at any point in time how many products should have passed each operation if time deliveries are to be on schedule?


Product focused scheduling l.jpg
Product-Focused Scheduling Problems on

  • Computerized scheduling:

  • Develops detailed schedules for each work center indicating starting and ending times

  • Develops departmental schedules

  • Generates modified schedules as orders move

  • Many packages available select one most appropriate for your business


Scheduling in service operations l.jpg
Scheduling in Service Operations Problems on

  • Major characteristics of scheduling in service operations:

  • Large demand fluctuation due to customer involvement

  • Intangible output can not be inventoried, capacity flexibility is critical

  • Capacity is labor-intensive in customer-contact operations


Scheduling in service operations ii l.jpg
Scheduling in Service Operations (II) Problems on

  • Two major scheduling issues:

  • Worker shift construction: how many shifts per working day?

  • Staffing for each shift: how many workers will be assigned to each shift?

  • Major scheduling techniques in service operations:

  • Optimization analytical models

  • Practical-oriented scheduling heuristics

  • Queuing models

  • Computer simulation search algorithms

  • ………………


Scheduling in service operations i l.jpg
Scheduling in Service Operations- I Problems on

  • Scheduling customer demand

    • Appointments

    • Reservations

    • Backlogs

  • Scheduling the workforce

    • Translates the staffing plan into specific schedules of work for each employee

    • Must satisfy workforce requirements

    • Must reallocate employees if requirements change

  • Major Scheduling Constraints

    • Technical constraints

    • Legal and behavioral considerations

    • Schedule types fixed and rotating


Scheduling in service operations ii34 l.jpg
Scheduling in Service Operations- II Problems on

  • Computerized workforce scheduling systems

    • Useful in coping with complex systems

    • 24/7 schedules and the need for great flexibility add significantly to the complexity of scheduling

  • Scheduling across the organization

    • Schedule involves an enormous amount of detail and affect every process in the firm

    • Product, services, and employees schedule determine specific cash flow requirements, trigger the billing process, and may initiate requirements for employee training processes

    • Good scheduling processes can decrease costs and improve responsiveness to supply-chain dynamics

    • The scheduling process, whether it is in manufacturing or services, can provide any firm with a capability useful in competing successfully


Service operations planning and scheduling l.jpg
Service Operations: Planning and Scheduling Problems on

  • Service are operations with:

  • Intangible outputs that ordinarily cannot be inventoried

  • Close customer contact and short lead time

  • High labor costs relative to capital costs

  • Subjectively determined quality

  • Need better planning controlling and management to stay competitive


Service operations planning and scheduling ii l.jpg
Service Operations: Planning and Scheduling (II) Problems on

  • Positioning strategies contain two elements:

  • Type of service design

    --Standard or custom

    --amount of customer contact

    --mix of physical goods and intangible services


Service operations planning and scheduling iii l.jpg
Service Operations: Planning and Scheduling (III) Problems on

  • Type of production process:

    --quasi-manufacturing: production occurs much as manufacturing physical goods dominant over intangible services

    --customer as participant: high degree of customer involvement physical goods may or may not be significant service either standard or custom

    --customer as product: service performed on customer usually custom


Service operations planning and scheduling iv l.jpg
Service Operations: Planning and Scheduling (IV) Problems on

  • Scheduling challenges in services: planning and controlling day-to-day activities difficult due to:

    --service produced and delivered by people

    --pattern of demand for services is non-uniform


Work shift scheduling in service operations l.jpg
Work Shift Scheduling in Service Operations Problems on

  • Three difficulties in scheduling services:

    --demand variability

    --service time variability

    --availability of personnel when needed

  • Managers use two tactics:

    --use full-time employees exclusively

    --use some full-time employees as base and fill in peak demand part-time employees


Work shift scheduling in service operations ii l.jpg
Work Shift Scheduling in Service Operations (II) Problems on

  • Scheduling customer-as-participant services

  • Must provide customer ease of use/access features lighting walkways, etc.

  • Layouts must focus on merchandising and attractive display of products

  • Employee performance crucial to customer satisfaction

  • Waiting times used extensively to level demand variation


Waiting line in service examples l.jpg
Waiting Line in Service: Examples Problems on

  • Computer printing jobs waiting for printing

  • Workers waiting to punch a time clock

  • Customers in line at a driven-up window

  • Drivers waiting to pay a highway toll

  • Skiers waiting for chair lift

  • Airplanes waiting to take off


Waiting line in service ii l.jpg
Waiting Line in Service (II) Problems on

  • Waiting line analysis: assists managers in determining:

  • How many servers to use

  • Likelihood a customer will have to wait

  • Average number of customer will wait

  • Waiting line space needed

  • Percentage of time all servers are idle


Waiting line in service iii l.jpg
Waiting Line in Service (III) Problems on

  • Scheduling customer as product services

  • Wide range of complexity

  • Every facet designed around the customer

  • Highly trained motivated and effective workforce critical to success

  • Waiting-line analysis can be helpful in determining staffing levels

  • In more complex operations simulation is a helpful tool in scheduling resources.


Waiting line in service iv l.jpg
Waiting Line in Service (IV) Problems on

  • Reasons for simulating operations

  • Experimentation with the real system is impossible impractical or uneconomical

  • System is so complex that mathematical formulas cannot be developed

  • Values of the system’s variables are not known with certainty