RELATED TO AGENDA ITEM W1. NCTD/SANDAG Project Update Capital Improvement Program. Bill Prey, P.E., LOSSAN Corridor Director San Diego Association of Governments. Current Rail Projects. 19 projects now in development 11 funded through construction $ 467 million in funding

Download Presentation

NCTD/SANDAG Project Update Capital Improvement Program

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Nctd sandag project update capital improvement program

RELATED TO AGENDA ITEM W1

NCTD/SANDAG Project UpdateCapital Improvement Program

Bill Prey, P.E., LOSSAN Corridor Director

San Diego Association of Governments


Current rail projects

Current Rail Projects

  • 19 projects now in development

  • 11 funded through construction

  • $467 million in funding

  • $915 million estimate cost at completion

  • Schedule currently funded through 2016


North coast corridor program

North Coast Corridor Program


In design batiquitos lagoon double track

In Design: Batiquitos Lagoon Double Track

Batiquitos Lagoon Double Track

$3 million

Funded through preliminary engineering

2.7 miles of second track

Anticipated to reach 60% design Feb. 2015


In design elvira to morena sd river bridge

In Design: Elvira to Morena & SD River Bridge

Elvira to Morena Double Track

$78.7 million

2 miles of second track in City of San Diego

Construction start 2015

San Diego River Bridge

$9.4 million

Realignment of bridge

0.9 miles of second track

San Diego River Bridge

Elvira to Morena


Nctd sandag project update capital improvement program

Near Construction: Sorrento Valley Double Track

Sorrento Valley Double Track

North of Sorrento Valley Station

$34 million

1 mile of second track

Construction startLate 2013/Early 2014

Sorrento Valley Double Track


Nctd sandag project update capital improvement program

Near Construction: San Onofre Double Track

San Onofre to Pulgas Double Track

Camp Pendleton area

Longest stretch of double track

4.2 miles

$38 million

Construction start Fall 2013


Near construction los pe asquitos lagoon

Near Construction: Los Peñasquitos Lagoon

Los PeñasquitosLagoon Bridge Project

$25 million

Recipient of $14 million TIGER grant from US DOT

4 wooden bridges to be replaced with concrete bridges

Construction begins mid-2014 for one year


Near construction oceanside transit center

Near Construction: Oceanside Transit Center

Platform Improvement Project

$19.5 million

Add third track and new platform

Constructionstart TBD

Level boarding considerations

Oceanside Transit Center


In construction santa margarita river bridge

In Construction: Santa Margarita River Bridge

Santa Margarita River Bridge

North of Oceanside

$41 million

0.8 miles

Deck now replaced

Est. completion April 2014

Sorrento to Miramar 1

Tecolote Crossover


In construction sorrento to miramar phase 1

In Construction: Sorrento to Miramar Phase 1

Sorrento to Miramar Double Track Phase 1

South of Sorrento Valley Station

$44 million

1.4 miles

Estimated completion January 2014


Near completion tecolote washington crossovers

Near Completion: Tecolote/Washington Crossovers

Tecolote/Washington Street Crossovers

Facilitates trains passing north of Downtown San Diego

$11 million

Tecolote: Completed September 2013

Washington: Completion slated in October 2013

Tecolote Crossover

Washington Crossover


Near completion san luis rey transit center

Near Completion: San Luis Rey Transit Center

San Luis Rey Transit Center

New bus transit center

$9 million

SANDAG construction completion October 2013

NCTD communications work through early 2014

Bus operations to begin in February 2014

Santa Margarita River Bridge

Sorrento to Miramar 1


Other sandag initiatives

Other SANDAG Initiatives

  • Station Parking Prioritization Study

  • Santa Fe Depot Study – in support of Convention Center COASTER station

  • Level Boarding Analysis


Nctd sandag project update capital improvement program

LOSSAN Coastal Rail Corridor Capital Improvement Projects

QUESTIONS & ANSWERS

More Information: KeepSanDiegoMoving.com/LOSSAN