Sweetwater Wastewater Treatment Plant Improvements

Sweetwater Wastewater Treatment Plant Improvements. Progress Report. SBR Basin Excavation Begins. Mid-April time frame showing topsoil stockpile in background. SBR Basin Rock Excavation. Mid-May time frame showing beginning of rock removal. SBR Basin Subgrade.

keenan
Download Presentation

Sweetwater Wastewater Treatment Plant Improvements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sweetwater Wastewater Treatment Plant Improvements Progress Report

  2. SBR Basin Excavation Begins Mid-April time frame showing topsoil stockpile in background

  3. SBR Basin Rock Excavation Mid-May time frame showing beginning of rock removal

  4. SBR Basin Subgrade Mid-June showing rock to be removed.

  5. SBR Basin Preparing to Blast Rock Late June time frame loading holes to blast rock in SBR pit.

  6. SBR Basin – Tertiary Filters Mid-August placing concrete slab for tertiary filters in SBR pit.

  7. SBR Basin – Tertiary Filter Late August - Beginning formwork for filter walls.

  8. SBR Basin – Preparing Subgrade Late August – Finishing rock removal and preparing the subgrade for the SBR slab.

  9. Electrical Building – Main Feeder Duct Bank Mid-May time frame – Electrical Building layout

  10. Electrical Building – Rough-In Late May time frame

  11. Electrical Building Late August time frame – Rough-In complete, footing poured

  12. Lab/Operation Building Footing & Rough-In Mid-July time frame

  13. Lab/Operations Building Mid-August, placing floor slab

  14. Lab/Operations Building Late August – Wall framing beginning

  15. UV Disinfection Structure Mid-July, Subgrade Preparation

  16. UV Disinfection – Wall Framing & Reinforcement Mid-August

  17. UV Disinfection Structure Late August