An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The South Carolina Design-Build ExperiencePresented by: Rocque L. Kneece, P.E.

  2. Southern Connector $ 206 million COMPLETE I-95 Honda Interchange $ 8 million COMPLETE Wateree River $ 8 million COMPLETE Conway Bypass $ 386 million COMPLETE Carolina Bays Parkway (2) $ 54 million ACTIVE Brockman-McClimon Interchange $ 52 million SELECTION Reedy & Enoree Bridge* $ 3 million COMPLETE Carolina Bays Parkway (1) $232 million COMPLETE Cooper River Bridge $ 531 million ACTIVE DESIGN-BUILD PROJECTS SC 170 Widening $80 million ACTIVE

  3. Carolina Bays Parkway Horry County, SC New Location Freeway 22 miles in Length Includes Right of Way Acquisition $232 million

  4. Carolina Bays Parkway - The Quality Challenge -

  5. Quality • Materials - Procedures

  6. Carolina Bays Parkway

  7. Carolina Bays Parkway

  8. QA/QC RESPONSIBILITY • QA/QC Testing by Contractor • Job Control Testing Used for Acceptance • Independent Assurance Testing by DOT • Discrepancies in Test Results resolved by third party testing

  9. Additional Measures by DOT • Assigned Resident Construction Engineer • Hired Consultant for Monitoring and Testing • DOT sets 10% Independent Test Ratio

  10. QA/QC COMMITMENT PROJECT DOT CONTRACTOR QA/QC QA/QC 1 3+ ENOREE/REEDY R. BRS. WATEREE R. BRIDGE SC 170 WIDENING CAROLINA BAYS PKWY COOPER RIVER BRIDGE 1 5+ 5+ 9+ 9 12+

  11. Cooper River Bridge Charleston, SC $532 million

  12. Existing Bridges

  13. Project Location New location

  14. Project Statistics • Length (Hwy 17) – 3.5 miles • Drilled Shafts - 427 • Concrete – 308,000 CY (poured in place) • Rebar – 53,000 tons • Structural Steel – 43,000 tons • Concrete Girders – 717 • Bridge Deck – 2 million sq. ft. (28 lane-miles) • ONLY 4.92 acres of environmental impacts!

  15. QA/QC BASIC STRUCTURE • QC Testing by Contractor • Acceptance Testing by DOT • DOT Test Rate Equals 20% of QC Testing • Independent Assurance Testing by DOT

  16. DESIGN-BUILD CONTRACTS QA/QC PERSONNEL PROJECT DOT CONTRACTOR QA/QC QA/QC 1 3+ ENOREE/REEDY R. BRS. WATEREE R. BRIDGE SC 170 WIDENING CAROLINA BAYS PKWY-1 COOPER RIVER BRIDGE 1 5+ 5+ 9+ 9 + 12+ 18+20+ Contract Responsibility Not a Contract Responsibility

  17. The Environmental Challenge • Sediment and Erosion Control • Construction Access • Hazardous Materials • Turtle Lighting • Community Impacts

  18. The Environmental Challenge • Joint Environmental Inspections • Contractor and DOT Contractor has a full time environmental inspector on the project • Full Time SCDOT Environmental Consultant • Together, the team of environmental professionals functions to ensure environmental compliance and to expedite the environmental process.

  19. Sediment & Erosion Control • Approximately 2 miles of silt fence, 10 temporary sediment basins, and several check dams among other control measures are installed on the project. • Contractor and SCDOT have strict inspection processes in place to monitor erosion control measures. • Inspections weekly and after every .50” rain

  20. Temporary Sediment Basin

  21. Construction Access • A total of 3 temporary construction trestles were erected for the project. • Greatly minimized impacts to wetlands while still allowing construction access.

  22. Hazardous Materials • SCDOT has remediated five UST’s, disposed of more than 100 cubic yards of contaminated material, and abated lead based paint and asbestos from structures ranging from houses to bridge. • During the construction of the CRB, SCDOT has spent an additional half million dollars for handling of hazardous materials/waste encountered during construction.

  23. Pumping material from an abandoned UST encountered in the Charleston Interchange.

  24. Potential Turtle Impacts • Concerns raised that bridge lights may disturb loggerhead hatchlings • Aesthetic Lighting Modified • Lights are controlled by timer • Lights may be dimmed • Lights may be turned off

  25. Community Impacts • Nine homes within the project ROW were relocated for affordable housing. • The homes were placed on new foundations at various sites in the community and are being renovated through a partnership between SCDOT and the City of Charleston.

  26. Lessons Learned • Include the Draft Contract with the RFP • Include Schedule of Values in Contract • QC/QA - Trust but verify • Independent Assurance by DOT • Be sensitive to the community concerns • Make Partnering a Key Element • Establish Lines of Communication • Time really is money – make decisions quickly

  27. LAST LESSON LEARNED

  28. BE CAREFUL OUT THERE… You never know what you might find.