An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RON EZEKIEL Fasken Martineau Tel: 604 631 4708 Email: rezekiel@fasken.com With the assistance of: Brenden Hunter, Calgary Raziel Zisman, Toronto 2008 Quebec Forum on Electricity:Business Opportunities in the Rest of Canada

  2. Outline • Markets • Participants • Structure • Opportunities • Challenges • Transmission • NIMBYism • First Nations

  3. Markets: Participants • BC • BC Hydro managed most of BC’s generation, transmission and distribution • In 2002 (and subsequent) energy plans and 2003 Transmission Corporation Act: • BC Hydro’s role in new generation is limited, with most new generation to come from IPPs. • BC Hydro’s transmission role transferred to new Crown corporation, British Columbia Transmission Corporation

  4. Markets: Participants • Alberta • Historically, no one dominant vertically integrated utility, but a variety with an integrated transmission network (ATCO, TransAlta, EPCOR) • 1995 Electricity Utilities Act established: • independent entity, Power Pool, to administer hourly wholesale market • Transmission Administrator role to operate Tx system

  5. Markets: Participants • Alberta • New 2003 Electricity Utilities Act consolidated Power Pool and Transmission Administrator functions into AESO

  6. Markets: Participants • Ontario • Ontario Hydro managed most of Ontario’s generation, transmission and distribution • In 1998 Electricity Act, Ontario Hydro’s role was divided up: • Generation: OPG and IPPs • Transmission: Hydro One • Distribution: Hydro One and other D COs. • Market: IESO

  7. Markets: Participants • Ontario • System Planning left to market, resulted in demand supply gap in 2002 • Electricity Restructuring Act of 2004 created the OPA, responsible for ensuring long term supply, including through planning and DSM/conservation

  8. Markets: Participants Summary

  9. Markets: Structure • BC • No real wholesale market • BC Hydro predominant buyer • In 2005, BCUC approved BC Hydro tariff permitting industrials to purchase electricity from third parties, but stepped rates and uncertainty over assured supply limit attractiveness • Export opportunities limited; limited availability on interties; Powerex an option

  10. Markets: Structure • Alberta • Pool system • One hour bids for rolling 7 day periods • AESO develops a merit order, taking into account congestion and constraints • Scheduling is day-ahead • Pool price is weighted average marginal price over the hour – all sellers receive and all buyers pay the pool price

  11. Markets: Structure • Ontario • Pool System - similar to Alberta • IESO balances supply and demand and dispatches generation accordingly • Pool price is weighted average marginal price over the hour – all sellers receive and all buyers pay the pool price • Where pool price less than PPA price, there may be a top up from OPA to seller

  12. Markets: Opportunities • BC • 2007 Energy Plan • Energy self-sufficiency, through Special Direction No. 10, directs BCUC to regulate BC Hydro to achieve electricity self-sufficiency by 2016 and each year thereafter

  13. Markets: Opportunities • BC • Bill 15, Utilities Commission Amendment Act, 2008 • BCUC must consider the “government’s energy objectives” in assessing long term resource plans • reduce greenhouse gas emissions • demand-side management • produce, generate and acquire electricity from clean or renewable sources

  14. Markets: Opportunities • BC • Bill 31, Greenhouse Gas Reduction (Emission Standards) Statutes Amendment Act, 2008 requires: • CCS of GHG emissions at least equal to emissions of prescribed GHGs attributable to use of coal for generation • Net zero GHG emissions from natural gas-fired generation facilities; existing facilities given until 2016 to comply

  15. Markets: Opportunities From BC Hydro LTAP Workshop materials, April 25, 2008 at http://www.bchydro.com/rx_files/info/info55971.pdf

  16. Markets: Opportunities From BC Hydro LTAP Workshop materials, April 25, 2008 at http://www.bchydro.com/rx_files/info/info55971.pdf

  17. Markets: Opportunities • BC • Bioenergy Call • Phase I for projects immediately vaiable; Phase II for projects requiring new tenure • Standing Offer Program • Clean or high efficiency cogen; proven technologies; 0.05MW<Capacity<10MW • Clean Power Call • Clean power; 5000 GWh/year; COD by 2016; Buyout option

  18. Markets: Opportunities • Alberta Proposed Generation (2007-2016) Type Capacity (MW) Gas 2073 Wind 3687 Cogeneration 2356 Coal 1873 Biomass 17 Hydro 100 Interconnection 300 Total Proposed Generation10,406

  19. Markets: Opportunities • Alberta • Load growth forecast at 3.1%/year to 2027 From AESO Future Demand and Energy Outlook 2007

  20. Markets: Opportunities • Alberta • AESO generation forecast (AMEC 2005) • 2300MW new generation by 2011, and 4100MW by 2016 • Comprised of 1600MW cogen; largely oil sands behind the fence • Small additions of aggregating 1100MW • Leaves 500-1500MW; forecast to be met with new coal or cogen

  21. Markets: Opportunities • Alberta • Bioenergy Plan • 9 point plan aimed at developing and expanding biodiesel, biogas and ethanol • Wind • 2006 cap of 900MW eliminated

  22. Markets: Opportunities • Ontario • Government’s 2006 Supply Mix Directive • 6300 MW peak reduction through DSM by 2025 • 10,402 MW of renewables by 2010, and 15,700 MW by 2025 • Limit nuclear to 14000 MW • Phase-out coal ASAP • Gas for peak, high value applications • Build transmission

  23. Markets: Opportunities • Ontario • OPA filed Integrated Power System Plan in 2007 to implement Directive • OEB Issue List decision March 2008 • Review expected to commence mid-2008

  24. Markets: Opportunities

  25. Markets: Opportunities

  26. Markets: Opportunities • Ontario • OPA is responsible for procurement of supply, but PPAs only provide for a revenue floor -- set to stimulate investment, but not to prop up or subsidize uneconomic generation • Generators, distributors, wholesale customers and retailers sell and buy energy through the IESO market

  27. Markets: Opportunities • Ontario • OPA procurement activities, largely competitive (RFP, RFQ, etc.) • Standard Offer Program • Wind, hydro, solar, biomass • Capacity<10MW • 20 year EPA • Solar @ $0.42/kWh; others @ $0.11/kWh (20% indexed for inflation) + $0.0352/kWh for reliable peak deliveries

  28. Challenges: Transmission BC

  29. Challenges: Transmission • BC • 10 yr $5.1B capital plan • One goal is integration of new clean and renewable energy • Northwest Transmission Line • BC to CA line From BCTC

  30. Challenges: Transmission • Alberta • The high cost of suboptimal generation being developed in response to transmission constraints is a substantial burden to customers that can be avoided if congestion is eliminated

  31. Challenges: Transmission • Alberta • Examples • Restricted development of low-cost cogen potential in the Fort McMurray because of lack of transmission infrastructure • Development of uneconomic TMR and other Southern AB generation because of constraints on the north-south system Source:http://www.crhnet.ca/casestudies/blackout/ alberta_restructuring.pdf

  32. Challenges: Transmission • Alberta • Examples • Exhaustion of existing system capacity under normal conditions in Southern Alberta; RAS relied on to support the operation of existing generation; market has expressed strong interest in developing wind generation in this region, but no further generation development until the transmission system is expanded Source:http://www.crhnet.ca/casestudies/blackout/ alberta_restructuring.pdf

  33. Challenges: Transmission Ontario From OPA

  34. Challenges: Transmission Ontario From OPA

  35. Challenges: NIMBYism Not In My Back Yard (NIMBY) Build Absolutely Nothing Anywhere Near Anything (BANANA)

  36. Challenges: NIMBYism • Examples • The Edmonton-Calgary 500kV • In May 2004 AESO submitted 13 “concepts” for a new tx line between Edm and Cgy • In April 2005 EUB approved the need for AESO's preferred 500 kV line • After the decision was issued, NIMBY opposition groups were formed, including LAVESTA Area Group and 566 Corridor Group

  37. Challenges: NIMBYism • Examples • The Edmonton-Calgary 500kV • Because the NIMBY groups did not participate in the proceeding, the EUB granted their application for a review and variance (R&V) hearing to consider issues like land density and agricultural impacts • On December 6, 2005, the R&V Panel affirmed the earlier decision

  38. Challenges: NIMBYism • Examples • The Edmonton-Calgary 500kV • In April 2006, the hearing for AltaLink’s facilities application commenced, but was postponed due to security concerns • On June 18, 2007, the EUB admitted hiring four private investigators to spy on landowners during the facilities application

  39. Challenges: NIMBYism • Examples • The Edmonton-Calgary 500kV • On September 30, 2007, on its own motion, EUB voided all previous decisions related to the proposed 500 kV line • On November 20, 2007, after approximately 3.5 years of regulatory proceedings and despite EUB’s September 30th decision, the Court of Appeal quashed all prior EUB decisions relating to 500 kV line on the basis of reasonable apprehension of bias

  40. Challenges: NIMBYism • Examples • Upper Pitt River IPP, BC • Required change of boundaries of provincial park to accommodate Tx line • Local government (Squamish) voted against project, but insufficient – local governments lost control over IPP approvals in 2006 through legislative amendment responding to blocking of Ashlu project • Minister refused park boundary adjustment

  41. First Nations • First Nations • Sparrow (SCC 1990) • Aboriginal rights still exist – constitutionally protected under section 35 • Aboriginal rights are not absolute – can be infringed by government • Government must be able to justify infringement – duty to consult

  42. First Nations • First Nations • Badger (SCC 1996) • Treaty rights also constitutionally protected • Government must also justify infringement of treaty rights

  43. First Nations • First Nations • Haida (SCC 2004) • Crown may have to consult (and accommodate) prior to rights being formally established • No independent duty on industry but can be delegated certain aspects • Content of duty depends on circumstances

  44. First Nations • First Nations • Haida (SCC 2004) • Crown may have to consult (and accommodate) prior to rights being formally established • No independent duty on industry but can be delegated certain aspects • Content of duty depends on circumstances

  45. First Nations • First Nations • Many different paths to take in the building a relationship with First Nations • Various agreements may be used in the course of relationship-building and which, in some cases, can be relied on by the Crown to assist in fulfilling its consultation and accommodation obligations

  46. Conclusion • Considerable need for new supply • Renewables preferred, but challenges including transmission, ability to serve base load and ability to meet demand • May leave opportunities for other generation

  47. Questions? Ron Ezekiel