Building a Legacy Rebuilding Providence Public Schools. 2008 Q2 Report Volume IV. Overview. Required by School Board Resolution. Timely Information to the School Board and Public. Historical Reference for the Program.

Download Presentation

Building a Legacy Rebuilding Providence Public Schools

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Building a LegacyRebuilding Providence Public Schools 2008 Q2 Report Volume IV

  2. Overview • Required by School Board Resolution. • Timely Information to the School Board and Public. • Historical Reference for the Program. • Overall Focus will be on Phase I projects, estimated present value cost - $384MM. • Targeted Focus on Active Projects.

  3. Keys for Review • Strikethrough means outstanding issue has been resolved. • Project comments may be updated and not show comments from previous report. • Checkmark means action has been completed.

  4. Active Projects • Adelaide Avenue High School. • Central High School. • Hanley Vocational School. • Career and Technical Educational Facility. • Free Standing Athletic Complex. • Nathan Bishop Middle School. • West Broadway Elementary School.

  5. Comments Opened on time September 2007 575 students in grades 9-11 Outstanding Issues Access route to the Building still pending. Active ProjectsAdelaide Avenue High School

  6. Comments Estimated Cost of $36MM. Final stages of multi year renovation. Interior and Exterior. Building Codes. Temporary relocation of students. Outstanding Issues Permanent Certificate of Occupancy received. Furnishings in place. Opened for use January 1, 2008. Expected to be fully occupied August 2008. Active ProjectsCentral High School

  7. Comments Estimated cost is $22MM Part of RIDE’s $90 M approval which includes the Hanley facility, CTE and Athletic Complex. Hanley programming - Culinary, Cosmetology, Graphic Arts, Automotive. Outstanding Issues City to Issue Bonds. Project design currently undergoing changes. Awaiting Deed for Land Parcel. Completion Sept. 2009. Active ProjectsHanley Career and Technical School

  8. Comments Estimated cost of $50 MM. Part of RIDE’s $90 M approval which includes the Hanley facility, CTE and Athletic Complex. CTE Programming - Masonry, HVAC, Electrical, Plumbing, Carpentry. Completion in Sept. 2009. Outstanding Issues RIDE approval of project City to sell Bonds. Acquire City Planning Commission pre-approval. Acquire Zoning Board approval. Complete abatement of existing gym prior to demolition (May 2008). Active ProjectsCareer and Technical Education (CTE)

  9. CTE Vision

  10. CTE Vision

  11. Hanley Vocational Progress

  12. CTE/Athletic Complex Progress

  13. Active ProjectsCareer and Technical Education (CTE) Hanley Wing Update • Masonry and Window replacement complete; • Roofing 90% complete; • Installation of mechanical systems 80% complete; • Interior walls complete; • Painting in progress; • Third Floor - finish painting, ceiling grids, light fixtures and floor preparations underway; • Substantially complete by January 2009, but not available for use until September 2009.

  14. Active ProjectsCareer and Technical Education (CTE) CTE - By October 1, 2008 • Foundation completed; • Slabs complete; • Erection of structural steel commenced; • Installation of new underground utilities. CTE - Post November: • Masonry to begin; • Fireproofing of structural steel; • Pouring of elevated decks; • Exterior walls begin.

  15. Comments Estimated Cost of $18 MM. Part of RIDE’s $90 M approval which includes the Hanley facility, CTE and Athletic Complex. Will house track and field and other indoor sports events. Outstanding Issues City awaiting RIDEM approval City to issue bonds. Bidding underway for building, site, foundation and building envelope. Expected to open September 2009. Active ProjectsAthletic Complex

  16. Comments Estimated cost of $35 MM. Program designed with community advisement. First facility proposal approved under State’s revised review process. Outstanding Issues RIDE and Regent Approval. Historical Society review to be scheduled by RIDE. City to sell bonds. General contractor bids due April 14. Completion Sept. 2009. Active ProjectsNathan Bishop Middle School

  17. Active ProjectsNathan Bishop Middle School Nathan Bishop Update • Awarded contract and commenced work as of June 2008. • Abatement work and exterior masonry in progress; • Selective demolition ongoing; • Site utilities and development in progress; • Commenced new interior walls on 1st Floor; • No outstanding issues – Open September 2009.

  18. Comments Students and Faculty relocated to Pell Complex. Options Development Community Group. Work of the Community Group will be submitted to School Board. Outstanding Issues No timetable set for this project to date. Active ProjectsWest Broadway Elementary School

  19. Warm, Safe and Dry Projects • $12.4 million in FY 2006. • $11.5 million in FY 2007 • FY 2008/FY 2009 • $2.0 million for 25 projects completed this past summer at 16 schools; • $750,000 for 5 projects scheduled for this fall at 5 schools.

  20. Phase I Projects

  21. Action StepsApril to October 2008 • School Board Approval • Capital Plan • Phase I Next Steps • RIDE/Board of Regents Approval • Nathan Bishop - Building Trades CTE • Bonds Sold • 2007 Series A, $75MM -2007 Series B, $75MM • Projects Started • Nathan Bishop - Building Trades CTE • Projects Completed • Outstanding Issues at Adelaide resolved

  22. Next Steps – October - January School Board Approval • Capital Plan • Phase I Next Steps