1 / 13

Overhead Distribution Systems

Overhead Distribution Systems. The Example Distribution Circuit. Typical of suburban/rural circuits 10 miles of 3-Phase 13.8 kV Main Feeder 8 single-phase laterals, evenly distributed on the main feeder. Each lateral 3 miles long, and connected to the main feeder through a fuse

judithortiz
Download Presentation

Overhead Distribution Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overhead Distribution Systems

  2. The Example Distribution Circuit • Typical of suburban/rural circuits • 10 miles of 3-Phase 13.8 kV Main Feeder • 8 single-phase laterals, evenly distributed on the main feeder. Each lateral 3 miles long, and connected to the main feeder through a fuse • A total of 1800 customers (8 x 225 customers/lateral) Distribution Substation 10 miles 3 miles 115 kV 13.8 kV

  3. R Improving Distribution Reliability with Reclosers Basic Radial System Case 1 SAIFI: 4.3 int/cust/yr SAIDI: 8.8 hrs/yr MAIFI: 0.0 mom/yr 10 miles Substation Circuit Breaker with No Reclosing Capability Case 2 SAIFI: 1.6 int/cust/yr SAIDI: 3.3 hrs/yr MAIFI: 8.7 mom/yr 10 miles Substation Recloser

  4. R R R Use of Line Reclosers Case 3 SAIFI: 2.6 int/cust/yr SAIDI: 5.4 hrs/yr MAIFI: 2.1 mom/yr Substation 5 miles 5 miles Circuit Breaker with No Reclosing Capability Case 4 SAIFI: 1.2 int/cust/yr SAIDI: 2.6 hrs/yr MAIFI: 6.5 mom/yr Substation 5 miles 5 miles Recloser

  5. R R Loop Configuration with Manual Switch Case 5 Substation 1 5 miles 5 miles SAIFI: 1.2 int/cust/yr SAIDI: 2.3 hrs/yr MAIFI: 6.5 mom/yr Manual Tie Switch Substation 2 • Assumptions • Circuit breakers have reclosing capability • Manual Tie Switch requires 1 hour to switch • Reclosers require 1 minute to switch

  6. R R R Automatic Loop Restoration - 3 Reclosers Case 6 5 miles 5 miles Substation 1 SAIFI: 1.0 int/cust/yr SAIDI: 2.1 hrs/yr MAIFI: 6.8 mom/yr N.C. Recloser N.O. Recloser Substation 2 N.C. Recloser N.C. - Normally-Closed N.O. - Normally-Open • Assumptions • Circuit breakers have reclosing capability • Reclosers require 1 minute to switch

  7. R R R R R Automatic Loop Restoration - 5 Reclosers Case 7 3.3 miles 3.3 miles 3.3 miles Substation 1 N.C. Recloser N.C. Recloser N.O. Recloser Substation 2 N.C. Recloser N.C. Recloser N.C. - Normally-Closed N.O. - Normally-Open SAIFI: 0.8 int/cust/yr SAIDI: 1.7 hrs/yr MAIFI: 6.5 mom/yr • Assumptions • Circuit breakers have reclosing capability • Reclosers require 1 minute to switch

  8. R R R R R R R R R R R R R Summary of Reclosing Benefits Hrs/Yr%* 8.8 ---- Case 1 - No reclosing 3.3 63% Case 2 - Substation reclosing 2.6 70% Case 4 - Line Recloser 2.3 74% Case 5 - Loop with Manual Switch 2.1 76% Case 6 - 3-Recloser Automatic Loop Restoration 1.7 81% Case 7 - 5-Recloser Automatic Loop Restoration *% Improvement as compared to Case 1

  9. R R R Automatic Loop Restoration - 3 Reclosers ***With Single-Pole Reclosing*** 5 miles 5 miles Substation 1 SAIFI: 0.8 int/cust/yr SAIDI: 1.8 hrs/yr MAIFI: 3.1 mom/yr N.C. Recloser N.O. Recloser Substation 2 N.C. Recloser N.C. - Normally-Closed N.O. - Normally-Open • Assumptions • Circuit breakers have reclosing capability • Reclosers require 1 minute to switch

  10. R R R R R Automatic Loop Restoration - 5 Reclosers ***With Single-Pole Reclosing*** 3.3 miles 3.3 miles 3.3 miles Substation 1 N.C. Recloser N.C. Recloser N.O. Recloser Substation 2 N.C. Recloser N.C. Recloser N.C. - Normally-Closed N.O. - Normally-Open SAIFI: 0.6 int/cust/yr SAIDI: 1.4 hrs/yr MAIFI: 2.7 mom/yr • Assumptions • Circuit breakers have reclosing capability • Reclosers require 1 minute to switch

  11. Benefits of Single-Pole Reclosing

  12. Predictive Reliability Analysis ABB Consulting’s Performance AdvantageTM Software Useful for: • Looking at system configuration and design • Placement of protective devices • Impacts of changes in failure rates and restoration times • Analyzing system reliability from a graphical perspectiveand determining the most cost-effective solutions

  13. Improving Distribution Reliability ABB is the ONLY supplier that can do this in all of the above schemes!

More Related