London Reprocurement - PowerPoint PPT Presentation


  • 89 Views
  • Uploaded on

London Reprocurement. Existing set up. Janet novated the telecommunications contracts from LMN in October 2010. All customer connections now have the same end date – 29 th March 2014. Customers receive their Janet connectivity – Primary or back up via a Janet PoP.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' London Reprocurement' - josephine-gilbert


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

Existing set up

Existing set up

  • Janet novated the telecommunications contracts from LMN in October 2010.

  • All customer connections now have the same end date – 29th March 2014.

  • Customers receive their Janet connectivity – Primary or back up via a Janet PoP.

  • Current PoP’s are all in central London.


Current pop layout

Current PoP layout

Three current PoP’s:

  • ULCC

  • Imperial College

  • King’s College

  • UCL also provides connectivity for a number of Janet customers.

4x10G

GE

VzB

4x10G

GE

VzB


Requirements gathering

Requirements Gathering

  • Questionnaire via survey monkey – issued 20th November 2012 and closed 31st January 2013.

  • Customer visits – Frances and myself have been visiting HE customers between October and January.

  • Requirements gathering during the RSC London Janet services day.

  • Analysing individual customer bandwidth usage to project forward to Q4 2015 to anticipate growth.


Janet6 london infrastructure

Janet6 - London Infrastructure

Reading

Access to the Janet backbone will be 60Gb initially.

The dark fibre will be delivered by the end of March 2013.

May – July 2013 migration from SJ5 to Janet6.

Imperial College

ULCC

TelecityPowergate

Telehouse West

Duxford


Procurement

Procurement

  • During RNO in sourcing Janet would take the opportunity to refresh the regional network infrastructure.

  • Janet6 has undertaken this element already for London.

  • We are therefore looking for point to point connections to customer premises as before.

  • Janet will use our existing Telecommunications Framework for this procurement.

  • Contract length:

    • 3 years with options to extend for a further 3 years.

    • Price refresh during year 2

    • Technology refresh in year 2


Procurement timetable

Procurement Timetable

11 week process

5 weeks between issuing the SoR and closure for responses.

3 weeks to evaluate the responses.

3 weeks to reach contract signature

The supplier will then have 7 months (144 working days) to deliver the connections.



Gary blake project manager t 44 0 1235 822211 e gary blake@ja net

Gary BlakeProject Managert +44 (0)1235 822211e [email protected]