STRATEGIC MANAGEMENT TOWARDS COAL SECURITY FOR NSPCL BHILAI AMIDST COAL CRISIS

STRATEGIC MANAGEMENT TOWARDS COAL SECURITY FOR NSPCL BHILAI AMIDST COAL CRISIS. STRATEGIC MANAGEMENT TOWARDS COAL SECURITY FOR NSPCL BHILAI AMIDST COAL CRISIS. Presented By: V.K. Agrawal and Renuka Isaran. Introduction.

johnsjames
Download Presentation

STRATEGIC MANAGEMENT TOWARDS COAL SECURITY FOR NSPCL BHILAI AMIDST COAL CRISIS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STRATEGIC MANAGEMENT TOWARDS COAL SECURITY FOR NSPCL BHILAI AMIDST COAL CRISIS STRATEGIC MANAGEMENT TOWARDS COAL SECURITY FOR NSPCL BHILAI AMIDST COAL CRISIS Presented By: V.K. Agrawal and RenukaIsaran

  2. Introduction Availability of coal in required quantity in a cost effective manner is the most important aspect for operation of a coal based power plant. The present coal stock at NSPCL Bhilai has gone down to super critical level and we are striving hard to keep the generation on as per schedule. In this presentation, coal requirement for Bhilai 2x250 MW units is analyzed and tried to find some additional sources to arrange coal for it. NSPCL BHILAI

  3. Coal Crisis and Power Sector Coal Stock at NSPCL Bhilai TPS NSPCL BHILAI

  4. Coal crisis Analysis Some of the possible reasons for present coal crisis are: Enormous capacity addition in coal based power stations Embargo on Import Coal Loss of wind, hydro and nuclear power Capacity addition NSPCL BHILAI

  5. Coal security for NSPCL Bhilai NSPCL BHILAI

  6. Coal Supply Statistics for NSPCL Bhilai SECL SCCL .5 MMTPA MOU signed on “best effort basis” for FY17-18 ACQ OF 2.408MMTunder FSA (24.09.13) Trigger level is 75% of ACQ 20% materialization achieved from SCCL The detail of coal receipt (in Tons) from different sources NSPCL BHILAI

  7. Generation losses incurred due to coal shortage at NSPCL Bhilai Generation losses due to Coal at NSPCL Bhilai: 234MU during FY14-15, 18MU during FY12-13 253 MU during FY 11-12 There was 4 Lakhs Ton Coal Stock during Feb’15 and March’15. FY16-17, recorded highest ever station performance. Again coal crisis emerged during 17-18 and coal stock dropped down, carpet coal used occasionally to avoid unit S/D.Coal stock is presently at super critical level (<3 days) at NSPCL Bhilai NSPCL BHILAI

  8. Alternatives To Improve Coal Supply 1. Implementation of Flexi scheme NSPCL BHILAI

  9. 2. Through e-auction by Rail mode NSPCL BHILAI

  10. 3. Coal transportation by Road Cum Rail Mode: Feedback from NTPC units NSPCL BHILAI

  11. Landed coal cost statistics for Bhilai NSPCL BHILAI

  12. Conclusion Linkage coal are the most economical source, to keep ECR at lowest possible level. Effort should be made to enhance materialisation under flexi scheme as per rolling plan / coal supply matrix Looking into present coal scenario and offer from SECL, NSPCL may need to resort to lift small % of linkage coal by RCR mode on trial basis Option to procure small % of coal through E-auction may also be kept ready. NSPCL BHILAI

  13. Limitation • Availability of coal and related offer is prerogative of coal supplier, any dispute to be dealt with as per FSA provision. • Scope of work and terms and conditions related with proper monitoring of coal dispatch by RCR mode to be looked after as per site requirement. • The prices in the estimates are indicative only, actual prices may very.

  14. Thank You NSPCL BHILAI