An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Construction/Installation Planning • Integration • Planning • Planning schedules • Typical Installation plan • Detailed schedules

  2. LCLS Construction/Installation Planning • Integrate all aspects of the LCLS project • Use P3 Schedule tools • Multi-calendar/multi-shift capability • Effort loaded • Official schedule for dates/timelines • Use Planning Schedules • High level schedules to review LCLS systems with SLAC programs

  3. LCLS Construction Planning • Integrated Schedule – P3 • Controlled by PMCS group • Input from System managers • Planning Schedule • Overview of LCLS systems • Conventional Facilities & Technical Systems • Integrate with SLAC programs • Downtimes, FFTB, SSRL, etc. • LCLS installations, “what-if” scenarios

  4. Planning Schedule - 1

  5. Planning Schedule - 2 FFTB shutdown date is subject to review and may move earlier Research yard work is shifted left 1 month relative to P3 for ‘what-if’ planning purposes

  6. Planning Schedule - 3

  7. LCLS Installation Planning • Typical Tech Component Installation • Conventional Construction Schedule – B.O. dates • Cable Plant & Utilties (LCW, I&C, Bus, etc) • Alignment/Survey • Supports & Stands Install • Technical Components Install • Utilities connections to components

  8. LCLS Installation Planning • Typical Tech Component Installation (cont) • Alignment/Survey, final • Test & Checkout, MPS/I&C • PPS Checkout & Verification • Lockdown & Power-On Checks • Commission

  9. LCLS Installation Planning • Subcontract Installation • Subcontracts work extremely well (for SPEAR3) • Prepare scope of work well in advance, be detailed in subcontract description, review with SLAC purchasing early • Prepare installation plan, make it easy for subcontractors to do their work.. Quickly and safely; minimize field change orders • Have system engineer/UTR on site during all subcontractor work; work out issues in a timely manner

  10. Installation Schedules • SLAC October downtime schedule • Input from LCLS • Lists Area and Shop • Shop sort done for all tasks • Integrates all SLAC shop requests • Weekly meetings • Run by Tech Div

  11. LCLS Installation Schedules • SPEAR3 schedule used P3 • 5 calendars • Units in hours • As much detail as needed

  12. RF Gun Load Lock L0-1 & L0-2 3-m SLAC Sections Gun Diagnostics Laser Heater Transverse RF Cavity DL1 Bend Straight Ahead Spectrometer Injector Installation • Injector installation to follow Sector 20 Facility B.O. • October installation: pipe in shield wall • Injector installation starts early ‘06

  13. LCLS Installation Planning • What’s next? • Start Planning process • Begin routine installation meetings • Review work scope & safety aspects • Develop plan & implement process • Daily meetings during installation times • Prepare for October installations • SLAC downtime schedule • Begin August ’06 installation plans • SLAC downtime/P3 detailed schedule • Continue to integrate CF & Technical component installation plans

  14. End of Presentation