An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Carthago Herzlich Willkommen! . . . mit Carthago in die Zukunft

  2. CASE: Carthago Proizvodnja avtodomov d.o.o. • Total planned investment: 3.032.000,00 Eur • State subsidy funds: 1.217.000,00 Eur • Nr. Of new employment: 150 • Production of Chic C line model

  3. Die Chic Familie

  4. Goals and benefits for Carthago • Odranci, Slovenia = Carthago’s 3rd production site • To increase the market share by creating production capacities for a new compact product line • one of few, increasingoutput during recession • Reduction ofmanufacturing costs • Access to a large pool of highly skilled and educated manpower • Benefit on local community support • Potential forfurther development • high manpower potential • available land

  5. Investment implementation • Challenges: • Fulfillment of the obligation to employ 150 persons in 3 years after receiving the subsidy (as the result of late start with production) • Support • National cost sharing grant scheme – Ministry of the Economy • Local community support • Regional development agency Mura • Employment service Murska Sobota

  6. Important elementsfor successful launch • Preparation of the project (CARTHAGO’s case: 1 year) • Selection of highly motivated initial employees • Preparation and training of employees • 25 employees were trained at the HQ, Germany • Surveillance and support for employees in the first days of their start-up • Selection of the employees to follow • criteria: experience and labor discipline

  7. Present stand of operation • Production of 700 vehicles planned for 2010 • 35 % of total production output of Carthago Group • 150 employees reached • Enlargement in planning phase

  8. Increasing production / output tendency

  9. Local Payroll

  10. Payroll – CARTHAGO Group Today the Carthago Group has more than 430 employees at 3 sites

  11. Benefits for the Pomurje region • 150 new employments • Development of sub-contracting activity in the region • Higher added value: product development done by local engineers • Synergies with the local community

  12. What’s next? Project 2 = Second investment project – new vehicle model Goal: to double again the production capacity • Total planned investment: 2.800.000,00 Eur • Building • Equipment, machines • State subsidy: 30% • Carthago will run on two calls for grant funds exploiting • the new Law of POMURJE: • Employment subvention, tax exemption • foreign investment incentives • State co-financing

  13. Project 2: objectives • Increase the output rhythm to 24 vehicles a week by the end of 2010 • Increase the production rhythm to 45 by 2012 • Increase total employment on 260