Explore the implementation of green infrastructure practices at the University of North Carolina at Chapel Hill, focusing on both the main campus and the Carolina North satellite campus. Learn about the regulatory framework, best management practices, lessons learned, and opportunities for future sustainability.

jdooley
Download Presentation

Green Infrastructure at UNC Chapel Hill: Campus and Watershed Scale

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Green Infrastructure at the Campus and Watershed Scale at theUniversity of North Carolina at Chapel Hill Carolyn Elfland, UNC Chapel HillSharon Myers, UNC Chapel HillTed Brown, Biohabitats, Inc.Sally Hoyt, Biohabitats, Inc.

  2. Carolina North Main Campus Mason Farm

  3. Overview • Background • Regulatory Framework • Central Campus BMP Implementation • Lessons Learned • Carolina North Opportunities

  4. Background Central Campus • 740 acres • 13.4 million square feet in 2000 • 7.5 million square feet to be added by 2010 • Stormwater Issues • Flooding and pipe surcharging increasing in frequency and severity • Need to improve water quality leaving the campus

  5. Background Satellite Campus – Carolina North • 1000 acres • Undeveloped except for small general aviation airport • Plan to develop 250 acres in 50 years • Aggressive sustainability goals, including stormwater

  6. Regulatory Framework Town of Chapel Hill Zoning • 85% TSS removal for first 1 inch of preciptation • Volume leaving site post-development shall not exceed volume pre-development for the 2 year 24 hour storm event (3.60 inches) • Rate leaving site post-development shall not exceed rate pre-development for the • 1 year storm – 3.0 inches • 2 year – 3.60 inches • 25 year – 6.41 inches • 50 year – 7.21 inches

  7. Regulatory Framework Jordan Lake TMDL • Existing development or redevelopment • 35% total nitrogen reduction • 5% total phosphorus reduction • New development • 2.2 lbs/acre/year unit loading rate target for total nitrogen • 0.82 lbs/acre/year unit loading rate target for total phosphorus

  8. Watersheds Bolin (lavender) Battle (gray) Chapel (blue) Meeting of the Waters (pink) Morgan (beige)

  9. Campus Best Management Practices

  10. Best Management Practices Phillips Hall/ Memorial Hall

  11. Best Management Practices Estes Storage Lot

  12. Best Management Practices Friday Center Lot

  13. Best Management Practices Carrington Hall

  14. Best Management Practices Hooker Fields

  15. Best Management Practices Rams Head Center

  16. Best Management Practices cisterns plastic storage modules Rams Head Center

  17. Best Management Practices Rams Head Center

  18. Best Management Practices Rams Head Center

  19. Best Management Practices Rams Head Center

  20. Best Management Practices Fed-Ex Global Education

  21. Land Cover

  22. Central Campus Lessons Learned • Don’t put cisterns on roofs • Cistern water is not free • Make careful plant selections for green roofs • Porous paving design makes a difference • High quality fill material is important • Education is critical

  23. Carolina NorthApplying Central Campus Lessons in an Integrated, Sustainable and Holistic Manner

  24. Carolina North • Up to 250 acres of a 1,000 acre parcel to be developed sustainably (energy, landscape, water, transportation, buildings) over next 50 years. • Currently small regional airstrip surrounded by mixed hardwood and pine forest. • Site also contains an inactive municipal landfill, a chemical waste site currently undergoing remediation and old municipal public works and bus depot yards

  25. Phase 1 – First 15 Years

  26. Phase 1 Principles • Respect the ecology of the site • Focus on transit-oriented development • Create a sense of identity and place • Provide appropriate local connections for bike, pedestrian, transit & roadways • Design for efficient land use with appropriate density

  27. Stormwater Strategies • Develop a water budget for the site that mimics the natural, undisturbed infiltration capacity of the land using practices and techniques that emphasize vegetative filtering and uptake and/or infiltration. • Provide water quality treatment for all impervious areas using practices that emphasize vegetative filtering and uptake and/or infiltration. • Provide treatment as close to the generating source as possible. Horace Williams - Carolina North

  28. Existing Land Cover for Phase 1at Carolina North

  29. Proposed Land Cover for Phase 1at Carolina North

  30. Summary of Existing and Proposed Conditions Peak Discharge and Runoff Volume Assumes no water quality or water quantity controls in place.

  31. Summary of Peak Discharge and Runoff Volume with Application of Green Infrastructure Assumes half of impervious surface (~34 acres) is converted to either green roofs or porous pavement. Still requires ~8 acre-feet of storage to provide peak flow attenuation.

  32. New Development Nutrient Loading Pre- and Post-development Jordan lake unit loading criteria (2.2 lbs/ac/yr and 0.82 lbs/ac/yr for TN and TP, respectively) are required for 20 acres of new development. Computations based on Tar Pamlico unit loading spreadsheet.

  33. Nutrient Export with Application of Green Infrastructure Components Half the rooftops to be green roofs, the other half served by cisterns. Half of the transportation area porous, and half of the managed turf area converted to forest. Green roofs behave like managed pervious areas. Area draining to cisterns removed from the total area (total area is reduced from 20 acres to 16.7 acres). Area consumed by porous pavement has same loading as managed pervious area. BMPs removal as 35% and 45% for total nitrogen and total phosphorus, respectively.

  34. Conclusion • UNC has committed to wide-scale implementation of green infrastructure elements across its campus, using an adaptive management approach. • Campus is evolving towards a whole systems approach that considers the benefits and treatment capabilities of soils, vegetation, and topography as well as the beneficial uses achieved through rainwater harvesting and water conservation. • Carolina North will be an example of UNC holistically applying green infrastructure principles in a fully integrated and multi-functional manner. • The intended outcome of UNC’s green infrastructure efforts is to maintain the sense of place that defines the campus community by creating and enhancing connections and linkages between human and natural systems in a manner that promotes education, stewardship, and participation.

  35. Questions?