An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AMO Instrument StatusWBS# 1.6.6 & 1.6.7 Jose Chan Cost Account Manager May 14, 2009

  2. AMO Team • Mechanical Engineering • Jean Charles Castanga (operation engineer) • Michael Holmes • Mechanical Installation Manager • Richard Atkinson • Cable Installation Manager • Ponciano Rodrigues • Manufacturing • SLAC MFD • LBNL • LLNL • Ohio University

  3. Atomic, Molecular and Optical Science beam

  4. Hutch 1 Layout

  5. Instruments • Pulse Picker • Slit System • Refocus Optics (LBNL) • Optic mirror coating (LLNL) • High Field Physics • Diagnostics • Magnetic Bottle (Ohio State University) • Energy Monitor (LLNL)

  6. Electrical/Mechanical Devices • 30 pumps • 27 Gauges • 62 Motors • 26 Pneumatic Solenoids • 16 Video Cameras • 12 Detectors & Spectrometers • 53 Other Electrical Devices (sensors, coils, metering devices, …)

  7. Pulse Picker Status • All purchased parts have been received • Assembly is more than 50% complete • No major issue with this assembly • Ready for installation on June 2nd

  8. Pulse Picker Assy

  9. SLIT System Status • Design is complete • All materials on order • MFD fabricating supports and chamber • Schedule to complete assembly by June 2nd • No major issue with the assembly

  10. Refocus Optics Status • Design complete • Vacuum chamber and supports are in fabrication • Optic Substrates being coated at LLNL expect to complete by June 1st • Assembly will begin in late June • Test, tune and align in July • Ready for installation by August Beam

  11. Refocus Optics Parts in Fabrication Chamber

  12. High Field Physics Status • Design is complete • Temporally fixed vertical stages are being used, will replace with movable vertical jacks when available • All purchased parts are in except ITOF detectors and manipulators. These parts are scheduled to be delivered this week • Assemblies are being assembled in a clean room • Complete assembly by the end of May and start installation by June 2nd beam

  13. High Field Physics Assy

  14. Time of Flight Assy ITOF ETOF

  15. Diagnostics Status • Design is complete • Temporally fixed vertical stages are being used, will replace with movable vertical jacks when available • Received all purchased parts • Magnetic Bottle and Energy Monitor assemblies will be field installed beam

  16. Diagnostics Chambers Assy

  17. Magnetic Bottle Status • Design is complete • Parts are in fabrication and procurement • Photonis detector is on critical list, expect delivery on June 16th • Complete assembling and testing by mid July • Installation by end of July

  18. Energy Monitor Parts Internal Parts, Flight-tube Cage, Shielding Mounts, Detector Flange Pole Magnet Mounting Detector Chamber Main Flight-tube Chamber

  19. Energy Monitor Status • Design is complete • Parts are in fabrication and procurement • Schedule to complete assembly and bakeout by June 23rd • Ship to SLAC on 7/7 • Install, leak check and pump down by mid July 2009

  20. Storage Chamber Status • Completed assembly and vacuum processing • Ready for storage of detectors • Available for installation

  21. CF Installations

  22. Hardware Installations

  23. Budget Summary

  24. Variance Explanations • WBS 1.6.6 • Installation of stoppers have been delayed due to wall 2 installation schedule slip • WBS 1.6.7 • AMO design was behind schedule, additional designers were added to expedite design schedule. This was significantly underestimated in the baseline plan • Additional engineering design and fabrication cost were incurred due to SLAC disqualification of ADC supplier for vertical adjustment stages

  25. 6- Months Look Ahead • Complete assemblies in May • Complete mechanical instrument installations by June 30th • Can start AMO commissioning in July (w/o Refocus System & Magnetic Bottle) • Install Refocus Optics by the end of July • Start phase 7 cable installations for Near Hall, X-ray transport Hall and Far Hall in August • Update all red-lined drawings and release to document control • Plan for users experiments