1 / 21

Main Injector Upgrades

Main Injector Upgrades. Ioanis Kourbanis March 15 , 2005. Decay Pipe. MI in 2005.  ’s to Soudan. NuMI extraction line. Outline. Introduction Power Supplies RF systems Large Aperture Quads Gammat-Jump Collimators. Introduction.

Download Presentation

Main Injector Upgrades

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Main Injector Upgrades Ioanis Kourbanis March 15 , 2005

  2. Decay Pipe MI in 2005 ’s to Soudan NuMI extraction line Kourbanis-Proton Driver Director's Review

  3. Outline • Introduction • Power Supplies • RF systems • Large Aperture Quads • Gammat-Jump • Collimators Kourbanis-Proton Driver Director's Review

  4. Introduction • Main Injector is currently delivering beam to the pbar target and to NuMI on the same cycle with a 0.5 Hz rep rate. • The total MI beam intensity can be as high as 3.5E13p/cycle and is expected to increase to about 5.5-6E13p/cycle with the implementation of beam stacking for NuMI. • For the Proton Driver MI is expected to deliver up to 1.5E14p/cycle with 0.67 Hz rep. rate. Kourbanis-Proton Driver Director's Review

  5. Power Supplies • At present the max. accelerating rate is 205GeV/sec. • The power supplies can support a max accelerating rate of 280 GeV/sec. With this the MI cycle time can be reduced to 1.5 sec (assuming a Linac as Injector). • To reduce the MI cycle time further down to 1 sec the max. accelerating rate has to increase to 325GeV/sec. • We will need some power supply upgrades to achieve this accelerating rate. Kourbanis-Proton Driver Director's Review

  6. Present Power Supply Capability Minimum Cycle Ramp 1.75sec Present MI Ramp 1.87sec Time for Sync. Injection Kourbanis-Proton Driver Director's Review

  7. Picture of Current MI Ramp MI Bend Current MI Bend Voltage Sync. Injection Time Time (sec) Kourbanis-Proton Driver Director's Review

  8. MI 1 Sec Ramp with Linac Injection Kourbanis-Proton Driver Director's Review

  9. MI Power Supplies Mod. For 1 Sec Ramp • Upgrade four more Quad Supplies to higher voltage (1200Vdc) • Add three more Bend Supplies. • Add one more 345kV Transformer and Harmonic Filters. • Total cost is estimated to be around $6M. Kourbanis-Proton Driver Director's Review

  10. MI RF System • The existing MI rf system does not have enough voltage or power to accelerate the beam intensity required. • We can increase the rf power available by adding another power tube to each cavity. The cavities have an extra port available. See John Reid’s talk. • We can add more cavities to increase the rf voltage needed for faster ramps (we have 3 spare cavities). • A design for a new rf system has been developed. See Dave Wildman’s talk. Kourbanis-Proton Driver Director's Review

  11. MI Cavity Kourbanis-Proton Driver Director's Review

  12. MI RF Power Calculation (18 Cavities) • Cavity Q=4700 (at max ramp rate), R=4.9E5Ω, V(gap)=240KV • 18 Cavities, each delivering 350KW for a total of 6.3MW • Min bucket area 1.24eV-sec(280 Gev/sec), 0.66eV-sec (325 GeV/sec) Kourbanis-Proton Driver Director's Review

  13. MI RF Power Calculations (20 Cavities) • Cavity Q=4700 (at max ramp rate), R=4.9E5Ω, V(gap)=240KV • 20 Cavities, each delivering 350KW for a total of 7.0MW • Min bucket area 1.77eV-sec(280 Gev/sec), 1.13eV-sec (325 GeV/sec) Kourbanis-Proton Driver Director's Review

  14. Wide Aperture Quads (WQB) • In all of the MI extraction areas the quadrupoles upstream of the Lambertson magnets limit the physical aperture leading to beam loss. • We plan to replace these quadrupoles with larger aperture ones (4in instead of 3.3in). • The first of these quadrupoles will ready for magnetic testing in early May. • We expect to have 4-7 of the WQB magnets ready for installation during this year’s shutdown. Kourbanis-Proton Driver Director's Review

  15. Beam Profiles with the old and WQB quads Old Lambertson Location Proposed Lambertson Location Kourbanis-Proton Driver Director's Review

  16. WQB Cross Sections Kourbanis-Proton Driver Director's Review

  17. WQB Laminations Kourbanis-Proton Driver Director's Review

  18. Coils of the first WQB magnet Kourbanis-Proton Driver Director's Review

  19. Gamma-t jump system • A gamma-t jump system is needed in MI to reduce the longitudinal emittance growth during transition crossing and prevent beam loss. • We have a conceptual design of a first order gamma-t system consisting of 8 sets of pulsed quadrupole triplets. It provides a Δγτfrom 1 to -1 within 0.5 ms. • The only big issue is to find the free space for the component installation. Kourbanis-Proton Driver Director's Review

  20. MI Collimation System • The combination of a very high amount of beam power injected into the MI (~0.13 MW), tight MI aperture defined by the extraction and injection Lambertsons, imposes serious constraints on beam losses. • An MI collimation system that gets rid of beam not captured during slip stacking will be needed in the immediate future. Kourbanis-Proton Driver Director's Review

  21. CONCLUSIONS • A series of upgrades is required for MI to run at Proton Driver Intensities and rep rates. • Most of the technical issues have been understood. • The large aperture quads and the MI collimation system will be in place before the Proton Driver since they are needed for the current MI operation. • An rf R&D program should start ASAP. Kourbanis-Proton Driver Director's Review

More Related