T- 489 Status Report 4/5/07. Yesterday:. 10am: access to ESA to retrieve Fe samples and place Ti-alloy samples Irradiation for 3.5hrs 2:00 pm : access to ESA to retrieve downstream Fe samples Continuous gamma spectrometry and dose

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' T- 489 Status Report 4/5/07' - jayme-buckley


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
T 489 status report 4 5 07

T- 489Status Report 4/5/07

Yesterday:

  • 10am: access to ESA to retrieve Fe

  • samples and place Ti-alloy samples

  • Irradiation for 3.5hrs

  • 2:00 pm: access to ESA to retrieve downstream Fe samples

  • Continuous gamma spectrometry and dose

    rate measurements in building 24


Gamma Spectra Measurements

Dose Rate Measurements

B24 Measurements


Dose rates to be measured over a period of 1000 hours (until May 15, 2007)

Short term sample activation levels at ~10 mSv/hr (1mR/hr) on contact

Samples Species:

Cu, Al, Fe, Ti, TiAlV, SS, dirt, concrete, water

B24 Measurements


AB01 Toroids May 15, 2007)


Check of CID Toroid with respect to CID Faraday Cup (10% agreement)

Likely to do a post experiment calibration of AB01 Toro 4140

AB01 Toroids


Schedule for today

Schedule for today: agreement)

  • 10am: take out Ti-Alloy and Steel Reference samples put in Al lateral and downstream and Steel Reference samples

  • Irradiation for 4hrs

  • 2pm: access to ESA to retrieve Al downstream sample

  • Continuous gamma spectrometry and dose rate measurements in

  • building 24

  • Will run through weekend until 7:00 AM Monday (09-May-2007)