An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMMA STATUS 18th June 2009 EMMA Collaboration Meeting

  2. Magnet construction is complete and magnet measurements to be complete by June 09 40 D-types and 40 F-types delivered Addition measurements required with F-type and D-type magnets together Production Quadrupoles QD QF

  3. In house design of septum magnet and vacuum chamber - complete Wire eroding of laminations - complete Septum magnet components - contact placed with TR Engineering – Delivery due 10th July Septum Design • Lamination Cleaning Fixture - contact placed with Metric Tool and Die – Delivery due 30th June • Cleaning of laminations July 09 • Assembly of septum magnet – 1st -14th August 09 • Magnet measurement coils – design complete and coil manufacture in progress at DL. • Magnet measurements scheduled for 17th -28th August 09 ISO view of septum with vacuum chamber removed

  4. Kicker Magnet Design • Kicker magnet components - contract placed with Brite Precision - completed May 09 • Magnet measurement coils – design complete and coil manufacture in progress at DL. • Magnet measurements scheduled for July 09 • Power supply acceptance testing at APP 24th -26th June. Conductor

  5. Corrector Magnet Design • Contract placed with Tesla Engineering - scheduled delivery early August 09 • 20 vertical corrector magnets • 8 combined vertical/horizontal corrector magnets Vertical corrector magnets Combined vertical/horizontal corrector magnets

  6. Standard Ring Vacuum Chamber • Contract placed with VG Scienta - all 16 chambers now delivered.

  7. Injection/Extraction Ring Vacuum Chambers • Design complete • Contract placed with K J Lesker- Delivery due 24th August 09 Kicker Kicker Septum

  8. RF Cavity Progress Input Coupler construction (Times Microwave) • 16 out of 20 cavities received • Final 4 awaiting input couplers from Times Microwave • 2 input couplers have been delivered • Input couplers • Excessive losses discovered on 2 of the feedthroughs and have been returned to Times Microwave for investigation/repair • In parrallel an order for 2 additional feedthrough’s has been placed with Times Microwave due to leaking/damaged feedthrough’s • Cavity evaluation • Four cavities successfully conditioned • Q0≈20000 achieved • Crosstalk seen on the pick-up probe • Responses to be checked and coupler to be adjusted by 180° Cavity construction Tuning range 0- 25 mm EMMA Review Alan Wheelhouse

  9. Progress on Waveguide Distribution Q-Par Angus • Acceptance tests performed on the 27th May 2009 • Issue with the reflected power coupler directivity • 3dB variation with 180° phase shift • Latest improvements look encouraging • To be reviewed • Need to determine its criticality to the LLRF system • System presently undergoing painting • Delivery anticipated by the 30th June 2009 • Installation late August 2009 • Actions • 3dB hybrid required • No flexible waveguide sections • Straight length of WR650 still to be defined EMMA Review Alan Wheelhouse

  10. HPRF Amplifier Progress CPI VIL409 HPRF Amplifier • Software testing and debugging on-going • System testing and debugging on-going • Preliminary results 19th June 2009 • Estimated acceptance test date 13th July 2009 • Estimated delivery 31st July 2009 • Main issue has been resource issues • Delivery early July 2009 • Installation August 2009 • Commissioning September 2009 EMMA Review Alan Wheelhouse

  11. LLRF System Progress • Performance tests performed with I-Tech Libra system • At 5kW (~150kV) per cavity • Phase: 0.0093º (spec is 0.3º) • Amplitude: 0.006% (spec is 0.3%) • Contract for LLRF system to be awarded by 19th June 2009 • Delivery mid August 2009 • Commissioning October 2009 • Critical issue • Synchronisation of the phase with the arrival of the beam EMMA Review Alan Wheelhouse

  12. INJECTION LINE ALICE to EMMA • Modules 27, 28 and 29 have been assembled, installed, leak tested and RGA scanned. • Module 30 – assembly ready for vacuum pump down ALICE Module 30 Module 28 Module 29 Module 27

  13. Injection Line – Module 30

  14. Ring GirderModule Assembly • 4 out of 7 girders have the quadrupoles installed • One girder with vacuum chambers installed ready for pump down (next slide)

  15. Ring Girder with Vacuum Chambers Installed

  16. DIAGNOSTICS LINE • YAG’s, bellows and beam dumps - Contract placed with - K J Lesker – Delivery in August 09. • BPM Assemblies – Contract placed with VG Scienta – Delivered • Quadrupole and dipole magnets - Contract placed with Scanditronix – Delivery End of June 09 • Corrector magnets - Contract placed with Tesla – delivery August 09 • Vacuum chambers – Design complete. • Girders - Design complete.

  17. Milestones Off line build of modules in progress – Sep 2009 ALICE shutdown 24th Aug – 12th Sep 2009 3 wks Installation in Accelerator Hall Mar – Oct 2009 Test systems in Accelerator Hall May - Nov 2009 Injection line complete 1st Oct 09 ALICE shutdown 1 – 23rd Nov 09 Ring complete 23rd Nov 09 Commission with electrons starting Dec 2009