The PATH To A NEW Charter Oak INTERNATIONAL ACADEMY. The New CHARTER OAK INTERNATIONAL ACADEMY – Size and Program. A 4 section per grade school with 480 K-5 students Room for 80 PreK students in 5 classrooms Implementation of the full West Hartford Curriculum

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' The PATH To A NEW Charter Oak INTERNATIONAL ACADEMY' - jafari


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

The new charter oak international academy size and program
The New CHARTER OAK INTERNATIONAL ACADEMY – Size and Program

  • A 4 section per grade school with 480 K-5 students

  • Room for 80 PreK students in 5 classrooms

  • Implementation of the full West Hartford Curriculum

  • Implementation of the IB-PYP Curriculum

  • Enhancements unique to Charter Oak – World Language PK-5, Quest 1-5 and Math Quest 1-5


General timeframes
General Timeframes

  • 2013-14 – Design the new school

  • 2014-15 – Start construction

  • 2015-16 – Complete construction

  • 2016-17 – Open the new school


2013 14 timeframes
2013-14 Timeframes

  • Faculty and Student Listening Meetings – Sep 13 and Sep 19

  • Parent and Community Listening Meetings– Oct 3 and Oct 9

  • Concept Design Feedback (end of October/early November 2013)

  • Meet with Faculty and Students

  • Meet with Parents and Community

  • Meet with the Board of Education

  • Review of Schematic Design (December 2013)

  • Approval of Schematic Design (January 2014)

  • Approval of Final Design (June 2014)