Construction Report. Your Bond Funds at Work. 2005 PE Facilities: Kuehnle, Mittelstadt, & Roth. RWS Stephens Construction original contractor Frost Construction replacement contractor $2,618,000 Kuehnle, Roth & Mittelstadt are open. 2005 Miscellaneous Projects. Clinic Renovations

I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.

Download Presentation

Your Bond Funds at Work

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Construction projects powerpoint

Construction Report

Your Bond Funds at Work


2005 pe facilities kuehnle mittelstadt roth

2005 PE Facilities: Kuehnle, Mittelstadt, & Roth

  • RWS

  • Stephens Construction original contractor

  • Frost Construction replacement contractor

  • $2,618,000

  • Kuehnle, Roth & Mittelstadt are open


2005 miscellaneous projects

2005 Miscellaneous Projects

  • Clinic Renovations

    • Northampton, Brill, Haude, Greenwood Forest, Nitsch, & Schultz

  • Athletics

  • Science Labs

    • Hildebrandt & Wunderlich

  • Paving

  • SHW

  • SA Construction

  • $3,413,200

  • Complete


Mold remediation schools

Mold Remediation Schools

  • SHW

  • Purcell Construction

  • $5,328,000

  • Complete


Klein hs auditorium

Klein HS Auditorium

  • Price Consulting, Inc.

  • KBR

  • $ 448,888

  • Complete


Benignus elementary

Benignus Elementary

  • SPA

  • Durotech

  • $10,778,535

  • Complete


Vistas hs of choice facility

Vistas HS of Choice Facility

Before

  • RWS

  • ICI Construction

  • $2,721,959

  • Complete

After


2006 pe facilities schultz hassler klenk eiland

2006 PE Facilities: Schultz, Hassler, Klenk, & Eiland

  • RWS

  • ICI Construction

  • $3,948,000

  • Spring ‘07


Summer 2006 projects

Labs & Clinics

SHW

Brothers Construction

$935,000

Intermediate Science Labs

Strack & Doerre

Elementary Art/Science

Greenwood Forest, Haude & Northampton

Roth Clinic

Complete

Miscellaneous Facility Assessment Projects

Joiner Architects

ICI Construction

$1,477,502

Maintenance Center Remodel

Athletics

Paving

Terrazzo

Hildebrandt Driveway

Carpet

Complete

Summer 2006 Projects


2006 summer projects

HVAC – Roth, KIC, Theiss, Hildebrandt, Maintenance, Kaiser, Klein Intermediate, Haude, Lemm, Strack & KHS

CHPA

Way Engineering

1,698,500

Complete

Roofing – KHS, Doerre, Ehrhardt & Theiss

PCI

Premium Roofing

$855,600

Complete

Energy Conservation – Roth, Eiland & Kuehnle

Carter Burgess

Trio Electric

$480,175

Complete

2006 Summer Projects


Hail damage roofs

Hail Damage Roofs

  • Schools with Damage

    • Theiss, Ehrhardt, Doerre, Mittelstadt, Brill, Hassler, Kaiser, Kuehnle, Strack, Wunderlich, Krahn & Kleb – work is complete

    • Klein High School, Annex and Klein High Athletic Buildings – work is in progress


Klein forest hs

Klein Forest HS

  • RWS

  • Marshall Construction

  • $12,712,585

  • Opened in Jan ’07


Krimmel intermediate

Krimmel Intermediate

  • SPA

  • Durotech

  • $21,346,403

  • May ‘07


Frank elementary

Frank Elementary

  • SPA

  • Durotech

  • $11,213,000

  • July ‘07


Summer 2007 projects

Labs, Food Service, & Addition

SHW

Purcell Construction

$4,087,665

Elementary Art/Science

Benfer, Theiss, Epps Island, Kaiser, Lemm, Brill

Benfer classroom addition

Food Service

Benfer & Epps Island

Miscellaneous Facility Assessment Projects

SPA

M. Scott Construction

$498,413

Athletics

Site Work

Wunderlich Farm RR

Ansul Systems

Greenhouse renovations at KHS & KFHS

Summer 2007 Projects


2007 summer projects

HVAC

CHPA

Kilgore

$450,120 bond funds

$6,545,000 super pennies

2006 Fire Alarms

KOHS, Northampton, Krahn & KFHSCareer Center

Carter Burgess

LECS, Ltd.

$1,192,057

Roofing & Wall Repair

Haude, Epps Island, KIC, KOHS, Kuehnle

PCI

Reliable

$609,614

Energy Conservation& Misc. Lighting

Krahn, Mittelstadt, Lemm, Klenk, Doerre, Klein Int., Kleb, Strack, KFHS

RH George

Trio Electric

$427,650

2007 Summer Projects


Other facilities

Network Operations Center

Corgan + PBA

Durotech

$3,650,118

Police Facility

Joiner Partnership, Inc.

Purcell Construction

$2,883,094

Other Facilities

  • Wunderlich Fine Arts Addition

    • RWS

    • Frost Construction

    • $2,137,500 budget


What s ahead

What’s Ahead

  • PASA Demographic Report

    • Forecast district growth

    • Determine when and where schools are needed

  • 2008 Bond Referendum

    • New Schools

    • Renovations/Remodel Facilities

    • Other Needed Facilities

    • Technology

    • Safety/Security