1 / 26

From 3.5 TeV to 7 TeV: Solution for the interconnect consolidation Francesco Bertinelli CERN – Technology Department – M

CERN Machine Advisory Committee 2nd Meeting – 26 April, 2010. From 3.5 TeV to 7 TeV: Solution for the interconnect consolidation Francesco Bertinelli CERN – Technology Department – MSC Group. Who is studying the solution and how? What does the new design look like?

iain
Download Presentation

From 3.5 TeV to 7 TeV: Solution for the interconnect consolidation Francesco Bertinelli CERN – Technology Department – M

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CERN Machine Advisory Committee 2nd Meeting – 26 April, 2010 From 3.5 TeV to 7 TeV: Solution for the interconnect consolidation Francesco Bertinelli CERN – Technology Department – MSC Group • Who is studying the solution and how? • What does the new design look like? • How will it be implemented? 20 minutes presentation, 10 minutes discussion: 26 slides

  2. Splices Task Force • Mandate November 2009 (35th LMC, 4 Nov. 2009) • To review the status of all superconducting splices in the LHC machine and prepare the necessary consolidation actions for 7 TeV operation. • Time frame: • 6-8 months starting November 2009. Originally to prepare for a shutdown 2010-2011: plans for the main IC splices maintained after Chamonix2010 (→ shutdown 2012). • Participation: 12 members from different CERN groups and departments. P. Limon (Tevatron), K.-H. Mess (Hera), RHIC this week • www.cern.ch/splices F. Bertinelli, N. Catalan Lasheras, P. Fessia, C. Garion, S. Mathot, A. Perin, C. Scheuerlein, S. Sgobba, H. ten Kate, J.-P. Tock, A. Verweij, G. Willering 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  3. Reminder from Chamonix2010 from A. Verweij • by considering unbiased data, ~15% splices would need redoing from R16 ( = copper stabiliser continuity) alone; • but segment measurements cannot identify them precisely enough (for MQ in particular), plus need to open all M sleeves for a given segment, estimate ~90% of sleeves; • if in addition we consider repairs from visual and preference towards systematically adding a shunt/clamp, we conclude: • Open all W interconnects and cut open all M sleeves, make local R16 measurement, redo ~20% splices, add shunt to 100% splices 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  4. The consolidated main IC splice Mechanical clamping (not present in Tevatron and Hera …) For latest update see Splices Task Force meeting no.17: https://espace.cern.ch/lhcsplices/Meeting%2017/default.aspx Sn-Pb solder for shunt but same Sn-Ag solder where we redo splices Insulation and transversal restraint: injection molding in RYTON(PPS) 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  5. Rationale behind the design i/ii • “Flexible” shunts • e.g. Braids or lamellar construction (EMS-DE) • Should adapt to existing defects • Avoid in-situ machining and copper swarf • Stress-free (or as low as possible) Sn-Pb interface: limit risk of potential degradation • Designed for 13 kA. Critical parameters are thickness and unsoldered length (→ difficult to achieve flexibility with 10 mm ...) • Solder 60Sn-40Pb • Lower melting point than Sn-Ag • “classic” solution (Tevatron, Hera) • ... but additional safety requirements: Safety Commission already involved 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  6. Rationale behind the design ii/ii • Mechanical clamp • Shall not depend on solder strength • Designed to survive ramp-down time • Insulation • Combines electrical function and mechanical restraint to bending • Allows efficient cooling from LHe • Ease of assembly • Current question: Include additional insulation? • nQPS • Build-in monitoring of segment resistances in time • Dedicated resistance measurement campaigns scheduled in Operations • General approach: seek redundancy and safety, do not want to intervene again (but no paranoia ...) 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  7. 13 kA IC: 3 directions for development • ~500 splices redone in 2008-09 • Improved process and QC • Further improvements: • loss of solder • avoid cutting spools • Process speed 13 kA interconnect re-development • Shunt geometry • Solder options • Soldering process • Inductive (as for splice) • Resistive oven (“classic”) • “Fast” resistive • Mechanical clamp 13 kA coordination P. Fessia Shunt development • FEA computations • Materials, availability, costs • Design insulation test Insulation development 16 March, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  8. 13 kA splice and process improvements • Simplify mechanics for easier use • verify the minimum force to get a good joint (samples at 3 level of force 50%, 25%, 15%) → avoid cutting spools • Include external water cooling after soldering → faster process • Optimise temperature profile • Thermocouples • Optimise geometry of inductive coils 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  9. Precise measurement of temperature profile • Eight measurement points located on the upper surface of the bus-bar. • Temperature sensors: Thermocouples type K with Inconel sleeve. • Tester: Data logger by ATP Messtechnik (Sampling Time = 10s). • Standard inductive soldering procedure. • Kapton stripes around the interconnection to avoid Sn flow off. 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  10. Optimisation of temperature profile • A simplified 3D magneto-static model of the inductor and of the bus-bar has been done. • The aim of the model is to understand the relationship between the field and temperature profiles along the interconnection, during the soldering plateau. 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  11. Shunt soldering process • Resistive oven • “Fast” resistive process • Inductive soldering (possibly several shunts in parallel) Note: 550 N required 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  12. Other alloys that we will study • Baseline is 60Sn-40Pb, will be fully developed first • Other studies will be performed later, same temperature as 60Sn-40Pb • Verification of theoretical mechanical properties still to be checked 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  13. Insulation studies Max displacement reduced from 0.25 mm to 0.06 mm and displaced out of the connection and far from the shunt 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  14. 13 kA IC Quality Control Shunt contact resistance • Progressing in parallel to IC work • First tests of electrical resistance at warm • Launching feasibility studies with EMPA (CH) and BAM (DE) Ultrasonics test 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  15. FRESCA results and “proof of principle” test See L. Bottura 27 April • Quadrupole busbar, constant current • 2 shunted defects measured (3 mm thick, 6 – 10 mm non-soldered length) Shunted No shunt • Shunts show a large improvement of stability • However, results are not directly applicable to the LHC machine situation: → simulation work 15 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  16. Final Validation Test • In SM18 two special SSS cold masses in series (MQM for Q8 and Q9) • the M1 and M3 busbars are not connected to the magnet, hence no inductance during splice testing • in preparation for July 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  17. Review • Formal reviews will be organised: • for the main IC splice design and process • two stages: before Validation Test and end 2010 • Composition? 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  18. Scenario for implementation • Series experience = real data • Average 30 IC activities per week • Capacity designed for 40 IC activities per week • Plan 2012 intervention to 50 IC activities per week (ambitious goal) • repair ≠ new • once work starts there will be huge pressure, many intervenants, little possibility for adaptations → do not count on learning curve • So many aleas at this stage → resist temptation to “squeeze” planning too much already now • Organise work as a train • Proceed to adjacent sector (→ do not jump), extend over 2-3 sectors • keep General Access mode as long as possible (→ cooldown and power as late as possible) • there will be additional work and surely unexpected work (→ Special Interventions Team) See K. Foraz 27 April 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  19. Series experience: soldering busbars 90% work in 11 wks … … but last 10% work in 9 wks from P. Fessia 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  20. Length of shutdown: estimate @50 IC/week The next sector ends 5 weeks later and so on ... 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  21. Resources for splices consolidation • Need to maintain a balance between “existing/experienced” resources and “newcomers” 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  22. Cost estimate of splices consolidation • 21.4 MCHF plus preparation in 2010-11 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  23. Additional magnets/splices work • a considerable amount of non-standard work !!! 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  24. Shutdown and resources issues • Moving magnets at Point 3 for collimators? • Same resources involved → there will be an inevitable time impact in the 2012 shutdown • Surface preparation work (busbar area setup and work, ….) • New Collaboration Agreement for Project Associates • we will first use all available resources on site, … • … but some resources will need to continue other critical activities • looking to set up a new Collaboration Agreement (“a la” Krakow Institutes for series production) • otherwise FSUs • and integrate first persons with existing resources already in 2010 • Xmas 2010 “Technical Stop”: • Could we consolidate 1 sector? → power and test the consolidated solution (and magnets), learning could allow optimization of 2012 shutdown • … or (not“and”) some of the “additional magnets/splices work” • If so needs to be decided by June 2010 (advice?) 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  25. Analysis of circuits • 13 kA: inside DFBAs in particular • 6 kA analysis started: • inventory of splices present: Points 2 and 4 done • Study failure mechanisms (multiple failures), quench detection, energy extraction → risk analysis • Slow progress (resources taken on LHC startup) Praying hands too! 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli

  26. Conclusions • 13 kA IC:  we have a candidate design, first test evidence is promising, Final Validation results by August • Scenario for 2012 Shutdown for 13 kA IC exists • Highlighted issues and current questions where adviceis welcome 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli