Borders to Beaches. Cameron County RMA. ADOPTED: First RMA Meeting – February 25, 2005 By Laws Adopted - April 4, 2005 Procurement Policies – April 14, 2005 Conflict of Interest policy for consultants – May 12, 2005 Disadvantaged Business Enterprise Policy Statement – May 12, 2005

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Borders to Beaches' - huela


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
cameron county rma
Cameron County RMA

ADOPTED:

  • First RMA Meeting – February 25, 2005
  • By Laws Adopted - April 4, 2005
  • Procurement Policies – April 14, 2005
  • Conflict of Interest policy for consultants

– May 12, 2005

  • Disadvantaged Business Enterprise Policy Statement

– May 12, 2005

  • Drug and Alcohol Policy – May 12, 2005
cameron county rma1
Cameron County RMA

SELECTED:

  • Financial Advisory Services Firm (Estrada Hinojosa & Company Inc.) -

January 12, 2006

  • General Engineering Consultant HNTB -January 23, 2006
cameron county rma2
Cameron County RMA

PROGRESS

  • Worked with TxDOT Pharr District to identify 9 Pass Through Toll Projects throughout Cameron County
  • Negotiated identical resolutions from the City of Port Isabel, the Town of South Padre and Cameron County regarding the proposed 2nd Causeway to South Padre Island
  • Presently working in conjunction with TxDOT on the West Loop environmental assessment.
  • TxDOT contracted Cal Y Mayor working on Level II Toll Feasibility Study for 2nd Causeway & West Loop
action items
Action Items:
  • Public Involvement Plan
  • Strategic Plan
  • Toll Equity Grant Application
  • Complete Level Two Toll Feasibility Studies.